IH35 from N of Rector to S of FM 455
0195-02-092 · let Nov 4, 2026 · Denton, Dallas · Widen Freeway
$138,145,038Low bid: INDUS ROAD & BRIDGE, INC.-4.3% vs estimate $144,352,231
$5,131,824Left on the table3.7% gap to the second bid
6BiddersSpread 12% low to high
351Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | INDUS ROAD & BRIDGE, INC. | $138,145,038 | -4.3% | $5,131,824 | 3+$17,927,737 | 1-$844,740 | |
| 2 | RPM XCONSTRUCTION, LLC | $143,276,861 | +3.7% | -0.7% | $9,302,215 | 4+$17,527,926 | 0 |
| 3 | MARIO SINACOLA & SONS EXCAVATING, INC. | $152,579,077 | +10.4% | 5.7% | $920,075 | 5+$24,925,386 | 2-$7,866,255 |
| 4 | WEBBER, LLC | $153,499,152 | +11.1% | 6.3% | $636,876 | 4+$24,846,069 | 0 |
| 5 | SEMA CONSTRUCTION, INC. | $154,136,028 | +11.6% | 6.8% | $737,402 | 4+$32,332,883 | 2-$2,039,854 |
| 6 | ZACHRY CONSTRUCTION CORPORATION | $154,873,429 | +12.1% | 7.3% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
INDUS ROAD & BRIDGE, INC. vs RPM XCONSTRUCTION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 130.066 STA | $36,031.36 | $14,906.00 | $6,072.92 | -$2,747,691 |
| 132-7010 EMBANK (FNL)(DC)(TY C2) | 74,240 CY | $11.00 | $42.75 | $22.38 | $2,357,120 |
| 422-7002 REINF CONC SLAB (HPC) | 361,248 SF | $20.00 | $26.00 | $26.91 | $2,167,488 |
| 423-7001 RETAINING WALL (MSE) | 81,164 SF | $75.50 | $60.00 | $74.07 | -$1,258,042 |
| 360-7005 CONC PVMT (CRCP) (11") | 100,018 SY | $80.00 | $91.50 | $94.72 | $1,150,207 |
| 432-7041 RIPRAP (STONE PROTECTION)(12 IN) | 12,465.6 CY | $100.00 | $185.00 | $179.97 | $1,059,576 |
| 110-7001 EXCAV (ROADWAY) | 130,961 CY | $15.00 | $7.30 | $11.68 | -$1,008,400 |
| 508-7001 CONSTRUCTING DETOURS | 56,603 SY | $95.00 | $112.00 | $83.58 | $962,251 |
| 360-7007 CONC PVMT (CRCP) (13") | 152,882 SY | $90.00 | $96.00 | $97.71 | $917,292 |
| 420-7023 CL C CONC (CAP)(HPC) | 1,503.4 CY | $1,135.00 | $1,575.00 | $1,420.15 | $661,496 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 41 MO | $30,000.00 | $45,500.00 | $11,585.04 | $635,500 |
| 260-7005 LIME (COM OR QK)(SLURRY) | 8,788 TON | $360.00 | $292.00 | $295.18 | -$597,584 |
| 512-7029 PORT CTB (MOVE)(F-SHAPE)(TY 1) | 95,100 LF | $9.00 | $2.95 | $9.04 | -$575,355 |
| 420-7054 CL C CONC (RAIL FOUNDATION)(HPC) | 2,139 CY | $500.00 | $695.00 | $544.02 | $417,105 |
| 260-7009 LIME TRT (EXIST MATL)(12") | 294,558 SY | $6.50 | $5.10 | $3.88 | -$412,381 |
| 425-7005 PRESTR CONC GIRDER (TX54) | 40,233.23 LF | $226.00 | $236.00 | $215.33 | $402,332 |
| 419-7001 SOUND WALL | 21,760 SF | $54.00 | $72.00 | $42.21 | $391,680 |
| 420-7039 CL C CONC (COLUMN)(HPC) | 1,200.3 CY | $1,065.00 | $1,380.00 | $1,492.16 | $378,095 |
| 450-7066 RAIL (TY SSTR)(MOD) | 2,302 LF | $225.00 | $67.50 | $93.58 | -$362,565 |
| 168-7001 VEGETATIVE WATERING | 51,732 TGL | $7.00 | $0.0100 | $8.43 | -$361,607 |
Positive: the low bidder was cheaper on that item. These 20 items account for $4,176,517 of the $5,131,824 gap.
INDUS ROAD & BRIDGE, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $13,800,000.00 | $523,850.32 | 26.34x | $13,276,150 |
| 100-7002 PREPARING ROW | 130.066 STA | $36,031.36 | $6,072.92 | 5.93x | $3,896,574 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 41 MO | $30,000.00 | $11,585.04 | 2.59x | $755,013 |
| 132-7010 EMBANK (FNL)(DC)(TY C2) | 74,240 CY | $11.00 | $22.38 | 0.49x | -$844,740 |
RPM XCONSTRUCTION, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $14,000,000.00 | $523,850.32 | 26.73x | $13,476,150 |
| 132-7010 EMBANK (FNL)(DC)(TY C2) | 74,240 CY | $42.75 | $22.38 | 1.91x | $1,512,380 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 41 MO | $45,500.00 | $11,585.04 | 3.93x | $1,390,513 |
| 100-7002 PREPARING ROW | 130.066 STA | $14,906.00 | $6,072.92 | 2.45x | $1,148,883 |
MARIO SINACOLA & SONS EXCAVATING, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $15,000,000.00 | $523,850.32 | 28.63x | $14,476,150 |
| 100-7002 PREPARING ROW | 130.066 STA | $42,800.00 | $6,072.92 | 7.05x | $4,776,944 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 41 MO | $85,000.00 | $11,585.04 | 7.34x | $3,010,013 |
| 110-7001 EXCAV (ROADWAY) | 130,961 CY | $25.00 | $11.68 | 2.14x | $1,744,112 |
| 260-7009 LIME TRT (EXIST MATL)(12") | 294,558 SY | $7.00 | $3.88 | 1.80x | $918,167 |
| 403-7001 TEMPORARY SPL SHORING | 173,740 SF | $1.00 | $25.56 | 0.04x | -$4,267,159 |
| 508-7001 CONSTRUCTING DETOURS | 56,603 SY | $20.00 | $83.58 | 0.24x | -$3,599,096 |
WEBBER, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $15,126,689.45 | $523,850.32 | 28.88x | $14,602,839 |
| 100-7002 PREPARING ROW | 130.066 STA | $56,900.00 | $6,072.92 | 9.37x | $6,610,875 |
| 132-7010 EMBANK (FNL)(DC)(TY C2) | 74,240 CY | $54.24 | $22.38 | 2.42x | $2,365,398 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 41 MO | $42,486.45 | $11,585.04 | 3.67x | $1,266,958 |
SEMA CONSTRUCTION, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $15,448,246.03 | $523,850.32 | 29.49x | $14,924,396 |
| 100-7002 PREPARING ROW | 130.066 STA | $115,121.70 | $6,072.92 | 18.96x | $14,183,538 |
| 132-7010 EMBANK (FNL)(DC)(TY C2) | 74,240 CY | $51.23 | $22.38 | 2.29x | $2,141,935 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 41 MO | $38,000.00 | $11,585.04 | 3.28x | $1,083,013 |
| 110-7001 EXCAV (ROADWAY) | 130,961 CY | $3.13 | $11.68 | 0.27x | -$1,120,005 |
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 28,560 LF | $8.44 | $40.65 | 0.21x | -$919,849 |