Bid Tab X-ray: 0261-01-041

Mar 4, 2026 · Ellis Sign up free
Set your company to personalize scores

US 67 AT LAKE RIDGE PKWY.

0261-01-041 · let Mar 4, 2026 · Ellis, Dallas · Interchange (New or Reconstructed)

$63,703,074Low bid: HIGHWAY 19 CONSTRUCTION LLC-0.1% vs estimate $63,765,204
$1,055,934Left on the table1.7% gap to the second bid
9BiddersSpread 35% low to high
425Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1HIGHWAY 19 CONSTRUCTION LLC $63,703,074-0.1% $1,055,934 3+$7,387,983 3-$2,603,095
2RPM XCONSTRUCTION, LLC $64,759,007+1.7%1.6% $1,579,008 1+$5,876,150 2-$1,312,493
3HARPER BROTHERS CONSTRUCTION LLC $66,338,016+4.1%4.0% $1,102,030 2+$4,114,303 1-$1,123,405
4WEBBER, LLC $67,440,046+5.9%5.8% $1,419,591 4+$12,115,661 2-$862,424
5GRANITE CONSTRUCTION COMPANY $68,859,637+8.1%8.0% $4,500,668 3+$11,681,194 2-$1,176,409
6MARIO SINACOLA & SONS EXCAVATING, INC. $73,360,305+15.2%15.0% $500,770
7ZACHRY CONSTRUCTION CORPORATION $73,861,075+15.9%15.8% $1,128,310
8SEMA CONSTRUCTION, INC. $74,989,385+17.7%17.6% $11,109,885
9AUSTIN BRIDGE & ROAD SERVICES, LP $86,099,270+35.2%35.0%

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

HIGHWAY 19 CONSTRUCTION LLC vs RPM XCONSTRUCTION, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
132-7008 EMBANK (FNL)(DC)(TY C1)341,039.83 CY $11.00$19.50$17.39 $2,898,839
360-7007 CONC PVMT (CRCP) (13")77,416 SY $104.00$87.00$97.71 -$1,316,072
403-7001 TEMPORARY SPL SHORING41,080 SF $55.00$28.00$25.56 -$1,109,160
100-7002 PREPARING ROW125 STA $300.00$9,000.00$6,072.92 $1,087,500
360-7005 CONC PVMT (CRCP) (11")89,247 SY $95.00$85.00$94.72 -$892,470
104-7001 REMOV CONC (PAV)59,167 SY $13.00$2.50$11.85 -$621,254
512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1)18,316 LF $79.00$49.00$40.65 -$549,480
476-7023 JACK BOR OR TUN PIPE(36 IN)(RC)(CL IV)466 LF $350.00$1,445.00$852.92 $510,270
422-7002 REINF CONC SLAB (HPC)55,308 SF $19.00$28.00$26.91 $497,772
423-7001 RETAINING WALL (MSE)45,663 SF $80.00$71.00$74.07 -$410,967
260-7008 LIME TRT (EXIST MATL)(10")97,228 SY $7.00$2.80$5.92 -$408,358
500-7001 MOBILIZATION1 LS $6,000,000.00$6,400,000.00$523,850.32 $400,000
110-7001 EXCAV (ROADWAY)168,119.08 CY $4.52$6.80$11.68 $383,312
512-7053 PORT CTB (REMOVE)(F-SHAPE)(TY 1)18,316 LF $25.00$4.80$13.39 -$369,983
260-7009 LIME TRT (EXIST MATL)(12")87,218 SY $7.00$3.20$3.88 -$331,428
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING32 MO $5,000.00$15,000.00$11,585.04 $320,000
508-7001 CONSTRUCTING DETOURS23,650 SY $75.00$88.00$83.58 $307,450
533-7007 FILL MILLED CONCR RUMBLE STRIPS (SHLDR)23,539 LF $1.00$14.00$6.86 $306,007
423-7029 RETAINING WALL (SPECIAL)4,586 SF $92.00$157.00$142.60 $298,090
132-7010 EMBANK (FNL)(DC)(TY C2)18,515.52 CY $11.00$27.00$22.38 $296,248

Positive: the low bidder was cheaper on that item. These 20 items account for $1,296,316 of the $1,055,934 gap.

HIGHWAY 19 CONSTRUCTION LLC: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $6,000,000.00$523,850.3211.45x$5,476,150
403-7001 TEMPORARY SPL SHORING41,080 SF $55.00$25.562.15x$1,209,371
512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1)18,316 LF $79.00$40.651.94x$702,463
110-7001 EXCAV (ROADWAY)168,119.08 CY $4.52$11.680.39x-$1,204,102
100-7002 PREPARING ROW125 STA $300.00$6,072.920.05x-$721,615
168-7001 VEGETATIVE WATERING91,122.55 TGL $1.00$8.430.12x-$677,378

RPM XCONSTRUCTION, LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $6,400,000.00$523,850.3212.22x$5,876,150
168-7001 VEGETATIVE WATERING91,122.55 TGL $0.1000$8.430.01x-$759,388
104-7001 REMOV CONC (PAV)59,167 SY $2.50$11.850.21x-$553,105

HARPER BROTHERS CONSTRUCTION LLC: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $4,300,000.00$523,850.328.21x$3,776,150
260-7009 LIME TRT (EXIST MATL)(12")87,218 SY $7.76$3.882.00x$338,153
110-7001 EXCAV (ROADWAY)168,119.08 CY $5.00$11.680.43x-$1,123,405

WEBBER, LLC: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $6,744,000.00$523,850.3212.87x$6,220,150
100-7002 PREPARING ROW125 STA $27,609.00$6,072.924.55x$2,692,010
132-7010 EMBANK (FNL)(DC)(TY C2)18,515.52 CY $149.00$22.386.66x$2,344,463
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING32 MO $38,430.00$11,585.043.32x$859,039
423-7029 RETAINING WALL (SPECIAL)4,586 SF $41.00$142.600.29x-$465,927
512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1)18,316 LF $19.00$40.650.47x-$396,497

GRANITE CONSTRUCTION COMPANY: unbalanced items

Placed 5
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $6,000,000.00$523,850.3211.45x$5,476,150
100-7002 PREPARING ROW125 STA $49,400.00$6,072.928.13x$5,415,885
132-7010 EMBANK (FNL)(DC)(TY C2)18,515.52 CY $65.00$22.382.90x$789,159
168-7001 VEGETATIVE WATERING91,122.55 TGL $0.1000$8.430.01x-$759,388
104-7001 REMOV CONC (PAV)59,167 SY $4.80$11.850.41x-$417,021