IH 30 AT BASS PRO DRIVE
0009-11-248 · let Oct 6, 2026 · Dallas, Dallas · Interchange (New or Reconstructed)
$54,378,798Low bid: RAGLE CONSTRUCTION, INC.+5.1% vs estimate $51,740,494
$3,607,302Left on the table6.6% gap to the second bid
7BiddersSpread 48% low to high
320Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | RAGLE CONSTRUCTION, INC. | $54,378,798 | 5.1% | $3,607,302 | 4+$11,294,935 | 1-$1,174,301 | |
| 2 | WEBBER, LLC | $57,986,100 | +6.6% | 12.1% | $1,726,196 | 4+$11,164,238 | 1-$374,114 |
| 3 | PULICE CONSTRUCTION, INC. | $59,712,296 | +9.8% | 15.4% | -$712,296 | 4+$10,878,494 | 0 |
| 4 | REYES TX, INC. | $59,000,000 | +8.5% | 14.0% | -$30,450 | 6+$12,925,083 | 2-$785,542 |
| 5 | JAMES CONSTRUCTION GROUP, LLC | $58,969,550 | +8.4% | 14.0% | $12,990,964 | 6+$15,970,554 | 1-$341,336 |
| 6 | BALFOUR BEATTY INFRASTRUCTURE, INC. | $71,960,515 | +32.3% | 39.1% | $8,614,628 | ||
| 7 | MARIO SINACOLA & SONS EXCAVATING, INC. | $80,575,143 | +48.2% | 55.7% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
RAGLE CONSTRUCTION, INC. vs WEBBER, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 47.91 STA | $112,700.00 | $83,037.00 | $6,072.92 | -$1,421,154 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 163,281 CY | $6.00 | $14.20 | $13.19 | $1,338,904 |
| 508-7001 CONSTRUCTING DETOURS | 24,793 SY | $103.00 | $147.00 | $83.58 | $1,090,892 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $1,125,000.00 | $148,138.03 | $136,676.66 | -$976,862 |
| 360-7007 CONC PVMT (CRCP) (13") | 57,999 SY | $103.00 | $116.00 | $97.71 | $753,987 |
| 403-7001 TEMPORARY SPL SHORING | 53,828 SF | $18.50 | $31.00 | $25.56 | $672,850 |
| 423-7001 RETAINING WALL (MSE) | 71,487 SF | $100.00 | $109.00 | $74.07 | $643,383 |
| 512-7005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | 22,230 LF | $50.00 | $22.10 | $40.65 | -$620,217 |
| 360-7004 CONC PVMT (CRCP) (10") | 29,500 SY | $87.00 | $102.00 | $87.39 | $442,500 |
| 500-7001 MOBILIZATION | 1 LS | $5,400,000.00 | $5,798,610.00 | $523,850.32 | $398,610 |
| 276-7165 CEM TRT(PLNT MX)(CL L)(TYD)(GR1-2)(6") | 58,182 SY | $16.50 | $10.80 | $18.52 | -$331,637 |
| 260-7019 LIME TRT (EXIST MATL)(18") | 58,182 SY | $3.45 | $8.85 | $6.97 | $314,183 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 24 MO | $25,000.00 | $37,830.00 | $11,585.04 | $307,920 |
| 168-7001 VEGETATIVE WATERING | 7,405 TGL | $1.00 | $35.00 | $8.43 | $251,770 |
| 416-7006 DRILL SHAFT (36 IN) | 4,686 LF | $290.00 | $246.00 | $280.58 | -$206,184 |
| 260-7009 LIME TRT (EXIST MATL)(12") | 18,707 SY | $3.65 | $11.20 | $3.88 | $141,238 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 5 EA | $50,000.00 | $24,530.00 | $9,253.78 | -$127,350 |
| 464-7005 RC PIPE (CL III)(24 IN) | 4,475 LF | $75.00 | $102.00 | $108.34 | $120,825 |
| 344-7041 SP MIXES SP-D PG64-22 | 4,012 TON | $155.00 | $132.00 | $134.97 | -$92,276 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 4,760 LF | $50.00 | $30.75 | $43.56 | -$91,630 |
Positive: the low bidder was cheaper on that item. These 20 items account for $2,609,751 of the $3,607,302 gap.
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 47.91 STA | $112,700.00 | $6,072.92 | 18.56x | $5,108,503 |
| 500-7001 MOBILIZATION | 1 LS | $5,400,000.00 | $523,850.32 | 10.31x | $4,876,150 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $1,125,000.00 | $136,676.66 | 8.23x | $988,323 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 24 MO | $25,000.00 | $11,585.04 | 2.16x | $321,959 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 163,281 CY | $6.00 | $13.19 | 0.45x | -$1,174,301 |
WEBBER, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $5,798,610.00 | $523,850.32 | 11.07x | $5,274,760 |
| 100-7002 PREPARING ROW | 47.91 STA | $83,037.00 | $6,072.92 | 13.67x | $3,687,349 |
| 508-7001 CONSTRUCTING DETOURS | 24,793 SY | $147.00 | $83.58 | 1.76x | $1,572,251 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 24 MO | $37,830.00 | $11,585.04 | 3.27x | $629,879 |
| 476-7035 JACK BOR OR TUN PIPE(48 IN)(RC)(CL V) | 251 LF | $1,140.00 | $2,630.49 | 0.43x | -$374,114 |
PULICE CONSTRUCTION, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $5,971,229.55 | $523,850.32 | 11.40x | $5,447,379 |
| 100-7002 PREPARING ROW | 47.91 STA | $95,000.00 | $6,072.92 | 15.64x | $4,260,496 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 24 MO | $41,885.05 | $11,585.04 | 3.62x | $727,200 |
| 512-7029 PORT CTB (MOVE)(F-SHAPE)(TY 1) | 48,300 LF | $18.22 | $9.04 | 2.02x | $443,418 |
REYES TX, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $5,563,735.85 | $523,850.32 | 10.62x | $5,039,886 |
| 423-7001 RETAINING WALL (MSE) | 71,487 SF | $144.00 | $74.07 | 1.94x | $4,998,957 |
| 100-7002 PREPARING ROW | 47.91 STA | $29,163.45 | $6,072.92 | 4.80x | $1,106,267 |
| 425-7004 PRESTR CONC GIRDER (TX46) | 2,880 LF | $454.00 | $236.72 | 1.92x | $625,772 |
| 425-7005 PRESTR CONC GIRDER (TX54) | 3,262.94 LF | $404.00 | $215.33 | 1.88x | $615,617 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $675,260.00 | $136,676.66 | 4.94x | $538,583 |
| 105-7014 RMV (14"-18") TRT/UNTRT BASE & ASPH PAV | 73,690 SY | $3.60 | $9.39 | 0.38x | -$426,488 |
| 476-7035 JACK BOR OR TUN PIPE(48 IN)(RC)(CL V) | 251 LF | $1,200.00 | $2,630.49 | 0.46x | -$359,054 |
JAMES CONSTRUCTION GROUP, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $5,800,000.00 | $523,850.32 | 11.07x | $5,276,150 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 163,281 CY | $40.97 | $13.19 | 3.11x | $4,535,636 |
| 100-7002 PREPARING ROW | 47.91 STA | $96,487.62 | $6,072.92 | 15.89x | $4,331,768 |
| 276-7165 CEM TRT(PLNT MX)(CL L)(TYD)(GR1-2)(6") | 58,182 SY | $34.13 | $18.52 | 1.84x | $908,198 |
| 260-7019 LIME TRT (EXIST MATL)(18") | 58,182 SY | $17.12 | $6.97 | 2.46x | $590,640 |
| 168-7001 VEGETATIVE WATERING | 7,405 TGL | $52.75 | $8.43 | 6.25x | $328,162 |
| 476-7035 JACK BOR OR TUN PIPE(48 IN)(RC)(CL V) | 251 LF | $1,270.59 | $2,630.49 | 0.48x | -$341,336 |