Win Price: 6509-76-001

Harrison · lets Dec 11, 2026 Sign up free

‹ All Win Price jobs Job page Bid Day Forecast

Routine Maintenance Project

Official

CCSJ 6509-76-001 · lets Friday, Dec 11, 2026 · Harrison, Atlanta · US0080

$310,314Predicted low bid-4.4% vs the engineer's estimate of $324,574
$277,590 – $337,099Likely rangeThe low bid lands here about half the time. 8 in 10: $243,679 to $375,060
1.2Expected bidders3 plan holders so far
HighConfidenceBacked by 828 closely comparable lettings (2,565 in all)

Where the low bid should land

$243,679: 1 in 10 low bids go lower$375,060: 1 in 10 go higher

What it takes to be lowest

Bid undervs estimateChance you are lowest
$243,679-24.9% 90%
$277,590-14.5% 75%
$310,314-4.4% 50%
$337,099+3.9% 25%
$375,060+15.6% 10%

Chance that no other bid comes in under yours, from how low bids on jobs like this one landed, corrected by how our past predictions actually turned out.

Check my estimate

Add your priced items for a line-by-line check

With items and no total, your total is the sum of the items.

Your numbers are used for this check only and are not saved.

The field: who is likely to bid

Plan holders, last 3 years of Texas bids
Plan holderChance they bidBidsWinsAvg bid vs est.Their typical bid here
CENTRAL NORTH CONSTRUCTION, LLCBidders 60% 6212 5.7% $342,962
HX FARMS, INC.Bidders 60% 305 12.5% $365,156
ROTOLO CONSULTANTS, INC.Bidders 3% 00

Chance they bid comes from how often each company bids prime contracts and, where we can see it, how many of the plan sets they took turned into bids. Plan holders with no bids are usually suppliers and subs.

Lettings most like this one

The closest of the jobs behind this prediction
LetCCSJWhereWorkBiddersEstimateLow bidLow bidder
Oct 20266509-83-001 UpshurAtlantaMaterial Maintenance Project1 $390,400$405,480+3.9% LONGVIEW ASPHALT, INC.
Oct 20266509-84-001 MarionAtlantaMaterial Maintenance Project1 $396,480$405,480+2.3% LONGVIEW ASPHALT, INC.
Oct 20266509-86-001 HarrisonAtlantaMaterial Maintenance Project1 $396,480$405,480+2.3% LONGVIEW ASPHALT, INC.
Oct 20266509-70-001 HarrisonAtlantaRoutine Maintenance Project3 $242,535$297,000+22.5% HOLMES AND HOLMES CONTRACTING
Oct 20266509-87-001 TitusAtlantaMaterial Maintenance Project2 $381,700$310,000-18.8% C-RAE MATERIALS LLC
Oct 20266509-82-001 MorrisAtlantaMaterial Maintenance Project2 $382,800$311,000-18.8% C-RAE MATERIALS LLC
Oct 20266509-81-001 PanolaAtlantaMaterial Maintenance Project2 $396,480$405,480+2.3% LONGVIEW ASPHALT, INC.
Oct 20266509-69-001 BowieAtlantaRoutine Maintenance Project3 $223,850$204,500-8.6% HOLMES AND HOLMES CONTRACTING
Oct 20266509-89-001 BowieAtlantaMaterial Maintenance Project2 $399,000$306,000-23.3% C-RAE MATERIALS LLC
Oct 20266509-88-001 BowieAtlantaMaterial Maintenance Project2 $399,500$306,000-23.4% C-RAE MATERIALS LLC

How it works: Win Price weighs every Texas letting of the last 3 years by how much it is like this job (size, district, type of work, how recent, and the size of the field) and reads where their low bids landed against the estimate. See the accuracy test. A prediction, not a promise: always price the job yourself.