Hot Mix Daingerfield FY 27
6509-82-001 · let Oct 22, 2026 · Morris, Atlanta · Material Maintenance Project
$311,000Low bid: C-RAE MATERIALS LLC-18.8% vs estimate $382,800
$10,000Left on the table3.2% gap to the second bid
2BiddersSpread 3% low to high
4Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | C-RAE MATERIALS LLC | $311,000 | -18.8% | $10,000 | 0 | 0 | |
| 2 | RK HALL, LLC | $321,000 | +3.2% | -16.1% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
C-RAE MATERIALS LLC vs RK HALL, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8011-7055 D-GR HMA TY D PG 64-22 (PICKUP) | 1,100 TON | $90.00 | $95.00 | $89.12 | $5,500 |
| 8011-7145 D-GR HMA TY D PG 70-22 (PICKUP) | 1,100 TON | $95.00 | $100.00 | $111.44 | $5,500 |
| 8011-7056 D-GR HMA TY D PG 64-22 (DEL) SITE 1 | 500 TON | $105.00 | $104.00 | $99.54 | -$500 |
| 8011-7146 D-GR HMA TY D PG 70-22 (DEL) SITE 1 | 500 TON | $110.00 | $109.00 | $117.96 | -$500 |
Positive: the low bidder was cheaper on that item. These 4 items account for $10,000 of the $10,000 gap.