Bid Tab X-ray: 6509-82-001

Oct 22, 2026 · Morris Sign up free
Set your company to personalize scores

Hot Mix Daingerfield FY 27

6509-82-001 · let Oct 22, 2026 · Morris, Atlanta · Material Maintenance Project

$311,000Low bid: C-RAE MATERIALS LLC-18.8% vs estimate $382,800
$10,000Left on the table3.2% gap to the second bid
2BiddersSpread 3% low to high
4Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1C-RAE MATERIALS LLC $311,000-18.8% $10,000 0 0
2RK HALL, LLC $321,000+3.2%-16.1% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.

Where the job was won

C-RAE MATERIALS LLC vs RK HALL, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
8011-7055 D-GR HMA TY D PG 64-22 (PICKUP)1,100 TON $90.00$95.00$89.12 $5,500
8011-7145 D-GR HMA TY D PG 70-22 (PICKUP)1,100 TON $95.00$100.00$111.44 $5,500
8011-7056 D-GR HMA TY D PG 64-22 (DEL) SITE 1500 TON $105.00$104.00$99.54 -$500
8011-7146 D-GR HMA TY D PG 70-22 (DEL) SITE 1500 TON $110.00$109.00$117.96 -$500

Positive: the low bidder was cheaper on that item. These 4 items account for $10,000 of the $10,000 gap.