Carthage Hot Mix FY 27
6509-81-001 · let Oct 22, 2026 · Panola, Atlanta · Material Maintenance Project
$405,480Low bid: LONGVIEW ASPHALT, INC.+2.3% vs estimate $396,480
$37,520Left on the table9.3% gap to the second bid
2BiddersSpread 9% low to high
4Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | LONGVIEW ASPHALT, INC. | $405,480 | 2.3% | $37,520 | 0 | 0 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $443,000 | +9.3% | 11.7% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
LONGVIEW ASPHALT, INC. vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8011-7056 D-GR HMA TY D PG 64-22 (DEL) SITE 1 | 500 TON | $135.90 | $160.00 | $99.54 | $12,050 |
| 8011-7146 D-GR HMA TY D PG 70-22 (DEL) SITE 1 | 500 TON | $140.90 | $165.00 | $117.96 | $12,050 |
| 8011-7055 D-GR HMA TY D PG 64-22 (PICKUP) | 1,100 TON | $118.90 | $125.00 | $89.12 | $6,710 |
| 8011-7145 D-GR HMA TY D PG 70-22 (PICKUP) | 1,100 TON | $123.90 | $130.00 | $111.44 | $6,710 |
Positive: the low bidder was cheaper on that item. These 4 items account for $37,520 of the $37,520 gap.