Material Maintenance Project
OfficialCCSJ 6513-20-001 · lets Tuesday, Dec 15, 2026 · San Patricio, Corpus Christi · US0181
Where the low bid should land
What it takes to be lowest
| Bid under | vs estimate | Chance you are lowest |
|---|---|---|
| $520,270 | -31.0% | 90% |
| $607,348 | -19.4% | 75% |
| $680,260 | -9.8% | 50% |
| $742,306 | -1.6% | 25% |
| $809,861 | +7.4% | 10% |
Chance that no other bid comes in under yours, from how low bids on jobs like this one landed, corrected by how our past predictions actually turned out.
The field: who is likely to bid
Plan holders, last 3 years of Texas bids| Plan holder | Chance they bid | Bids | Wins | Avg bid vs est. | Their typical bid here |
|---|---|---|---|---|---|
| MARTIN MARIETTA MATERIALS, INC.Bidders | 60% | 243 | 64 | 15.3% | $869,333 |
| GREEN DREAM INTERNATIONAL LLCBidders | 60% | 24 | 11 | -11.1% | $670,346 |
| VULCAN CONSTRUCTION MATERIALS, LLCBidders | 60% | 220 | 106 | 4.9% | $790,679 |
| BRAUNTEX MATERIALS, INC.Bidders | 60% | 114 | 44 | 1.3% | $764,164 |
| TOUCHSTONE RESOURCES, LLCBidders | 60% | 413 | 170 | 11.0% | $837,169 |
Chance they bid comes from how often each company bids prime contracts and, where we can see it, how many of the plan sets they took turned into bids. Plan holders with no bids are usually suppliers and subs.
Lettings most like this one
The closest of the jobs behind this prediction| Let | CCSJ | Where | Work | Bidders | Estimate | Low bid | Low bidder |
|---|---|---|---|---|---|---|---|
| Nov 2026 | 6509-21-001 | Jim WellsCorpus Christi | Material Maintenance Project | 4 | $498,200 | $427,000-14.3% | CK NEWBERRY, LLC |
| Apr 2026 | 6500-30-001 | BeeCorpus Christi | Material Maintenance Project | 4 | $630,000 | $607,250-3.6% | BOBCAT MATERIALS LLC |
| Sep 2026 | 6509-58-001 | KarnesCorpus Christi | Material Maintenance Project | 3 | $855,000 | $760,500-11.1% | TEXAS MATERIALS GROUP, INC. |
| Nov 2026 | 6511-71-001 | KlebergCorpus Christi | Material Maintenance Project | 5 | $515,000 | $563,000+9.3% | BRAUNTEX MATERIALS, INC. |
| Jul 2026 | 6502-52-001 | NuecesCorpus Christi | Routine Maintenance Project - Sealed | 4 | $682,013 | $609,237-10.7% | TEXAS MATERIALS GROUP, INC. |
| May 2025 | 6484-16-001 | KarnesCorpus Christi | Material Maintenance Project | 4 | $792,000 | $769,500-2.8% | TEXAS MATERIALS GROUP, INC. |
| May 2026 | 6500-64-001 | GoliadCorpus Christi | Material Maintenance Project | 3 | $534,000 | $514,500-3.7% | TEXAS MATERIALS GROUP, INC. |
| Aug 2026 | 6505-11-001 | NuecesCorpus Christi | Material Maintenance Project | 2 | $751,500 | $673,575-10.4% | ANDERSON COLUMBIA CO., INC. |
| May 2026 | 6501-88-001 | RefugioCorpus Christi | Material Maintenance Project | 3 | $480,000 | $468,600-2.4% | BRAUNTEX MATERIALS, INC. |
| Jul 2025 | 6485-78-001 | KarnesCorpus Christi | Material Maintenance Project | 4 | $488,000 | $480,500-1.5% | BRAUNTEX MATERIALS, INC. |
How it works: Win Price weighs every Texas letting of the last 3 years by how much it is like this job (size, district, type of work, how recent, and the size of the field) and reads where their low bids landed against the estimate. See the accuracy test. A prediction, not a promise: always price the job yourself.