6485-78-001 Aggregate Karnes Area
6485-78-001 · let Jul 15, 2025 · Karnes, Corpus Christi · Material Maintenance Project
$480,500Low bid: BRAUNTEX MATERIALS, INC.-1.5% vs estimate $488,000
$2,312Left on the table0.5% gap to the second bid
4BiddersSpread 3% low to high
5Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BRAUNTEX MATERIALS, INC. | $480,500 | -1.5% | $2,312 | 0 | 0 | |
| 2 | COLORADO MATERIALS, LTD. | $482,812 | +0.5% | -1.1% | $14,183 | 0 | 0 |
| 3 | MARTIN MARIETTA MATERIALS, INC. | $496,995 | +3.4% | 1.8% | $305 | 0 | 0 |
| 4 | VULCAN CONSTRUCTION MATERIALS, LLC | $497,300 | +3.5% | 1.9% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
BRAUNTEX MATERIALS, INC. vs COLORADO MATERIALS, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8000-7269 AGGR (TY PB GR 3) (DEL) (ST3) | 1,500 TON | $75.00 | $73.49 | $75.00 | -$2,265 |
| 8000-7268 AGGR (TY PB GR 3) (DEL) (ST2) | 1,500 TON | $80.00 | $81.11 | $80.00 | $1,665 |
| 8000-7267 AGGR (TY PB GR 3) (DEL) (ST1) | 1,500 TON | $80.00 | $80.88 | $83.06 | $1,320 |
| 8000-7296 AGGR (TY PB GR 4) (DEL) (ST2) | 800 TON | $80.00 | $81.11 | $92.46 | $888 |
| 8000-7295 AGGR (TY PB GR 4) (DEL) (ST1) | 800 TON | $80.00 | $80.88 | $92.77 | $704 |
Positive: the low bidder was cheaper on that item. These 5 items account for $2,312 of the $2,312 gap.