Win Price: 0904-00-229

Potter · lets Dec 2, 2026 Sign up free

‹ All Win Price jobs Job page Bid Day Forecast

Safety Improvement Projects

Official

CCSJ 0904-00-229 · lets Wednesday, Dec 2, 2026 · Potter, Amarillo · Various

$1,887,704Predicted low bid-9.7% vs the engineer's estimate of $2,090,094
$1,671,202 – $2,082,530Likely rangeThe low bid lands here about half the time. 8 in 10: $1,445,989 to $2,321,513
2.4Expected bidders4 plan holders so far
MediumConfidenceBacked by 588 closely comparable lettings (1,926 in all)

Where the low bid should land

$1,445,989: 1 in 10 low bids go lower$2,321,513: 1 in 10 go higher

What it takes to be lowest

Bid undervs estimateChance you are lowest
$1,445,989-30.8% 90%
$1,671,202-20.0% 75%
$1,887,704-9.7% 50%
$2,082,530-0.4% 25%
$2,321,513+11.1% 10%

Chance that no other bid comes in under yours, from how low bids on jobs like this one landed, corrected by how our past predictions actually turned out.

Check my estimate

Add your priced items for a line-by-line check

With items and no total, your total is the sum of the items.

Your numbers are used for this check only and are not saved.

The field: who is likely to bid

Plan holders, last 3 years of Texas bids
Plan holderChance they bidBidsWinsAvg bid vs est.Their typical bid here
VIZCAINO, L.P.Bidders 60% 2510 -0.8% $2,074,285
CENTERLINE TECHNOLOGIES, LLCBidders 60% 9826 -14.5% $1,786,677
STRIPE-A-ZONE, LLCBidders 60% 18851 -8.9% $1,904,630
TRP INFRASTRUCTURE SERVICES, LLCBidders 60% 27278 -9.4% $1,893,765

Chance they bid comes from how often each company bids prime contracts and, where we can see it, how many of the plan sets they took turned into bids. Plan holders with no bids are usually suppliers and subs.

Lettings most like this one

The closest of the jobs behind this prediction
LetCCSJWhereWorkBiddersEstimateLow bidLow bidder
Dec 20250904-00-228 PotterAmarilloSafety Improvement Projects3 $1,971,041$1,124,670-42.9% STRIPE-A-ZONE, LLC
Mar 20260066-05-073 MooreAmarilloSafety Improvement Projects2 $1,274,759$1,004,804-21.2% VACA UNDERGROUND UTILITIES INC
Sep 20266480-09-001 PotterAmarilloRoutine Maintenance Project - Sealed3 $1,800,640$1,490,960-17.2% GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
Aug 20266505-50-001 HemphillAmarilloMaterial Maintenance Project2 $1,656,120$1,538,330-7.1% ERGON ASPHALT & EMULSIONS, INC.
Nov 20260947-03-034 JasperBeaumontSafety Improvement Projects2 $2,281,773$2,431,741+6.6% TEXAS MATERIALS GROUP, INC.
Aug 20260069-07-113 Tom GreenSan AngeloSafety Improvement Projects2 $1,800,040$2,825,728+57.0% REECE ALBERT, INC.
Dec 20256492-49-001 PotterAmarilloRoutine Maintenance Project - Sealed3 $2,272,700$1,794,755-21.0% TEXAS PANHANDLE CONSTRUCTION, INC.
Aug 20266505-41-001 HansfordAmarilloMaterial Maintenance Project2 $1,226,016$1,147,052-6.4% ERGON ASPHALT & EMULSIONS, INC.
Mar 20266497-48-001 HutchinsonAmarilloMaterial Maintenance Project2 $1,382,493$1,456,985+5.4% VOLCANIC STONE CO.
Aug 20261023-01-039 ChambersBeaumontSafety Improvement Projects3 $2,493,248$2,499,687+0.3% HAYDEN PAVING, INC.

How it works: Win Price weighs every Texas letting of the last 3 years by how much it is like this job (size, district, type of work, how recent, and the size of the field) and reads where their low bids landed against the estimate. See the accuracy test. A prediction, not a promise: always price the job yourself.