FY 26 Districtwide Thermo Pav Markings
0904-00-228 · let Dec 3, 2025 · Potter, Amarillo · Safety Improvement Projects
$1,124,670Low bid: STRIPE-A-ZONE, LLC-42.9% vs estimate $1,971,041
$99,028Left on the table8.8% gap to the second bid
3BiddersSpread 15% low to high
45Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | STRIPE-A-ZONE, LLC | $1,124,670 | -42.9% | $99,028 | 0 | 5-$653,234 | |
| 2 | TRP INFRASTRUCTURE SERVICES, LLC | $1,223,698 | +8.8% | -37.9% | $66,178 | 1+$6,192 | 6-$631,539 |
| 3 | CENTERLINE TECHNOLOGIES, LLC | $1,289,876 | +14.7% | -34.6% | 0 | 7-$584,977 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
STRIPE-A-ZONE, LLC vs TRP INFRASTRUCTURE SERVICES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 666-7068 REFL PAV MRK TY I(W)(ENTR GORE)(090MIL) | 57 EA | $300.00 | $800.00 | $600.59 | $28,500 |
| 505-7003 TMA (MOBILE OPERATION) | 252 DAY | $1.00 | $100.00 | $229.60 | $24,948 |
| 666-7071 REFL PAV MRK TY I(W)(EXIT GORE)(090MIL) | 59 EA | $500.00 | $800.00 | $639.71 | $17,700 |
| 666-7292 TY I HIGH PERF PM (W)6"(SLD)(090MIL) | 279,525 LF | $0.4900 | $0.5500 | $0.6513 | $16,772 |
| 677-7002 ELIM EXT PM & MRKS (6") | 517,532 LF | $0.3300 | $0.3000 | $0.2755 | -$15,526 |
| 666-7304 TY I HIGH PERF PM (Y)6"(SLD)(090MIL) | 256,410 LF | $0.5100 | $0.5500 | $0.6851 | $10,256 |
| 668-7023 PREFAB PM TY B (W)(ARROW) | 40 EA | $500.00 | $275.00 | $610.38 | -$9,000 |
| 666-7248 RE PM TY III (Y)(6")(SLD) | 275,564 LF | $0.5200 | $0.5500 | $0.7409 | $8,267 |
| 668-7031 PREFAB PM TY B (W)(WORD) | 26 EA | $700.00 | $400.00 | $817.99 | -$7,800 |
| 666-7289 TY I HIGH PERF PM (W)6"(BRK)(090MIL) | 54,620 LF | $0.5300 | $0.6500 | $0.8121 | $6,554 |
| 666-7236 RE PM TY III (W)(6")(SLD) | 217,578 LF | $0.5200 | $0.5500 | $0.6919 | $6,527 |
| 666-7029 REFL PAV MRK TY I (W)12"(SLD)(090MIL) | 11,044 LF | $3.50 | $4.00 | $2.32 | $5,522 |
| 672-7015 PLOWABLE REFL PAV MRKR TY II-C-R | 100 EA | $30.00 | $80.00 | $41.29 | $5,000 |
| 666-7424 REFL PAV MRK TY I (W)12"(DOT)(100MIL) | 1,890 LF | $3.50 | $6.00 | $2.72 | $4,725 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $1.00 | $1,000.00 | $11,585.04 | $3,996 |
| 672-7004 REFL PAV MRKR TY II-A-A | 1,588 EA | $7.00 | $5.00 | $3.97 | -$3,176 |
| 668-7030 PREFAB PM TY B (W)(NUMBER) | 8 EA | $800.00 | $425.00 | $800.00 | -$3,000 |
| 677-7006 ELIM EXT PM & MRKS (12") | 2,530 LF | $1.00 | $2.00 | $1.27 | $2,530 |
| 672-7006 REFL PAV MRKR TY II-C-R | 1,200 EA | $7.00 | $5.00 | $4.19 | -$2,400 |
| 666-7008 REFL PAV MRK TY I (W)6"(DOT)(090MIL) | 9,250 LF | $0.7500 | $1.00 | $0.9352 | $2,313 |
Positive: the low bidder was cheaper on that item. These 20 items account for $102,708 of the $99,028 gap.
STRIPE-A-ZONE, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $10,000.00 | $523,850.32 | 0.02x | -$513,850 |
| 505-7003 TMA (MOBILE OPERATION) | 252 DAY | $1.00 | $229.60 | 0.00x | -$57,606 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $1.00 | $11,585.04 | 0.00x | -$46,336 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $100.00 | $9,253.78 | 0.01x | -$18,308 |
| 666-7068 REFL PAV MRK TY I(W)(ENTR GORE)(090MIL) | 57 EA | $300.00 | $600.59 | 0.50x | -$17,134 |
TRP INFRASTRUCTURE SERVICES, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 666-7424 REFL PAV MRK TY I (W)12"(DOT)(100MIL) | 1,890 LF | $6.00 | $2.72 | 2.20x | $6,192 |
| 500-7001 MOBILIZATION | 1 LS | $10,000.00 | $523,850.32 | 0.02x | -$513,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $1,000.00 | $11,585.04 | 0.09x | -$42,340 |
| 505-7003 TMA (MOBILE OPERATION) | 252 DAY | $100.00 | $229.60 | 0.44x | -$32,658 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $50.00 | $9,253.78 | 0.01x | -$18,408 |
| 668-7023 PREFAB PM TY B (W)(ARROW) | 40 EA | $275.00 | $610.38 | 0.45x | -$13,415 |
| 668-7031 PREFAB PM TY B (W)(WORD) | 26 EA | $400.00 | $817.99 | 0.49x | -$10,868 |
CENTERLINE TECHNOLOGIES, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 505-7003 TMA (MOBILE OPERATION) | 252 DAY | $1.00 | $229.60 | 0.00x | -$57,606 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $1.00 | $11,585.04 | 0.00x | -$46,336 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $250.00 | $9,253.78 | 0.03x | -$18,008 |
| 666-7029 REFL PAV MRK TY I (W)12"(SLD)(090MIL) | 11,044 LF | $1.00 | $2.32 | 0.43x | -$14,594 |
| 668-7023 PREFAB PM TY B (W)(ARROW) | 40 EA | $300.00 | $610.38 | 0.49x | -$12,415 |
| 668-7031 PREFAB PM TY B (W)(WORD) | 26 EA | $350.00 | $817.99 | 0.43x | -$12,168 |