2023 HSIP CURVE (FM 563) CHEVRONS, RS
1023-01-039 · let Aug 5, 2026 · Chambers, Beaumont · Safety Improvement Projects
$2,499,687Low bid: HAYDEN PAVING, INC.+0.3% vs estimate $2,493,248
$16,090Left on the table0.6% gap to the second bid
3BiddersSpread 16% low to high
73Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | HAYDEN PAVING, INC. | $2,499,687 | 0.3% | $16,090 | 3+$93,382 | 2-$426,732 | |
| 2 | DURWOOD GREENE CONSTRUCTION CO. | $2,515,777 | +0.6% | 0.9% | $387,611 | 1+$91,240 | 1-$403,850 |
| 3 | TEXAS MATERIALS GROUP, INC. | $2,903,388 | +16.2% | 16.5% | 4+$555,818 | 3-$499,567 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
HAYDEN PAVING, INC. vs DURWOOD GREENE CONSTRUCTION CO., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 530-7025 DRIVEWAYS AND TURNOUTS (ACP) | 4,789 SY | $16.86 | $35.00 | $15.95 | $86,872 |
| 134-7004 BACKFILL (TY A OR B) | 24 STA | $2,300.00 | $500.00 | $211.21 | -$43,200 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $15,000.00 | $6,000.00 | $11,585.04 | -$36,000 |
| 530-7015 DRIVEWAYS (BASE) | 1,385 SY | $23.00 | $35.00 | $27.85 | $16,620 |
| 500-7001 MOBILIZATION | 1 LS | $133,775.00 | $120,000.00 | $523,850.32 | -$13,775 |
| 100-7002 PREPARING ROW | 9 STA | $2,000.00 | $3,500.00 | $6,072.92 | $13,500 |
| 341-7064 D-GR HMA TY-D PG 64-22 (EXEMPT) | 4,482 TON | $137.00 | $140.00 | $152.88 | $13,446 |
| 341-7082 TACK COAT | 2,173 GAL | $10.00 | $4.00 | $3.93 | -$13,038 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 464 SY | $125.00 | $100.00 | $60.19 | -$11,600 |
| 6068-7003 LED CHEVRON | 76 EA | $2,650.00 | $2,500.00 | $1,639.96 | -$11,400 |
| 666-7023 REFL PAV MRK TY I (W)8"(SLD)(090MIL) | 675 LF | $1.00 | $13.50 | $0.9036 | $8,438 |
| 666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL) | 36,548 LF | $0.7900 | $1.00 | $0.6515 | $7,675 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 2,595 EA | $0.5000 | $3.00 | $0.5715 | $6,488 |
| 344-7030 SP MIXES SP-C SAC-A PG76-22 | 5,975 TON | $158.00 | $157.00 | $138.38 | -$5,975 |
| 533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE) | 18,274 LF | $0.4200 | $0.6500 | $0.2394 | $4,203 |
| 666-7422 REFL PAV MRK TY I (Y)6"(SLD)(090MIL) | 14,816 LF | $0.6200 | $0.9000 | $0.5014 | $4,148 |
| 685-7001 INSTALL RDSD FLASH BEACON ASSEMBLY | 13 EA | $5,500.00 | $5,200.00 | $5,349.14 | -$3,900 |
| 560-7008 MAILBOX INSTALL-S (TWW-POST) TY 4 | 17 EA | $525.00 | $325.00 | $337.58 | -$3,400 |
| 344-7077 TACK COAT | 3,260 GAL | $5.00 | $4.00 | $3.25 | -$3,260 |
| 505-7001 TMA (STATIONARY) | 31 DAY | $425.00 | $350.00 | $217.57 | -$2,325 |
Positive: the low bidder was cheaper on that item. These 20 items account for $13,517 of the $16,090 gap.
HAYDEN PAVING, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 134-7004 BACKFILL (TY A OR B) | 24 STA | $2,300.00 | $211.21 | 10.89x | $50,131 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 464 SY | $125.00 | $60.19 | 2.08x | $30,071 |
| 341-7082 TACK COAT | 2,173 GAL | $10.00 | $3.93 | 2.54x | $13,180 |
| 500-7001 MOBILIZATION | 1 LS | $133,775.00 | $523,850.32 | 0.26x | -$390,075 |
| 100-7002 PREPARING ROW | 9 STA | $2,000.00 | $6,072.92 | 0.33x | -$36,656 |
DURWOOD GREENE CONSTRUCTION CO.: unbalanced items
Placed 2TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 6068-7003 LED CHEVRON | 76 EA | $7,300.00 | $1,639.96 | 4.45x | $430,163 |
| 685-7001 INSTALL RDSD FLASH BEACON ASSEMBLY | 13 EA | $9,975.00 | $5,349.14 | 1.86x | $60,136 |
| 134-7004 BACKFILL (TY A OR B) | 24 STA | $2,000.00 | $211.21 | 9.47x | $42,931 |
| 6068-7001 LEAD LED CHEVRON | 6 EA | $6,011.00 | $2,246.28 | 2.68x | $22,588 |
| 500-7001 MOBILIZATION | 1 LS | $91,500.00 | $523,850.32 | 0.17x | -$432,350 |
| 100-7002 PREPARING ROW | 9 STA | $1,600.00 | $6,072.92 | 0.26x | -$40,256 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $4,845.00 | $11,585.04 | 0.42x | -$26,960 |