Bid Tab X-ray: 1023-01-039

Aug 5, 2026 · Chambers Sign up free
Set your company to personalize scores

2023 HSIP CURVE (FM 563) CHEVRONS, RS

1023-01-039 · let Aug 5, 2026 · Chambers, Beaumont · Safety Improvement Projects

$2,499,687Low bid: HAYDEN PAVING, INC.+0.3% vs estimate $2,493,248
$16,090Left on the table0.6% gap to the second bid
3BiddersSpread 16% low to high
73Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1HAYDEN PAVING, INC. $2,499,6870.3% $16,090 3+$93,382 2-$426,732
2DURWOOD GREENE CONSTRUCTION CO. $2,515,777+0.6%0.9% $387,611 1+$91,240 1-$403,850
3TEXAS MATERIALS GROUP, INC. $2,903,388+16.2%16.5% 4+$555,818 3-$499,567

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.

Where the job was won

HAYDEN PAVING, INC. vs DURWOOD GREENE CONSTRUCTION CO., biggest item swings
ItemQtyLow2ndMarket2nd minus low
530-7025 DRIVEWAYS AND TURNOUTS (ACP)4,789 SY $16.86$35.00$15.95 $86,872
134-7004 BACKFILL (TY A OR B)24 STA $2,300.00$500.00$211.21 -$43,200
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING4 MO $15,000.00$6,000.00$11,585.04 -$36,000
530-7015 DRIVEWAYS (BASE)1,385 SY $23.00$35.00$27.85 $16,620
500-7001 MOBILIZATION1 LS $133,775.00$120,000.00$523,850.32 -$13,775
100-7002 PREPARING ROW9 STA $2,000.00$3,500.00$6,072.92 $13,500
341-7064 D-GR HMA TY-D PG 64-22 (EXEMPT)4,482 TON $137.00$140.00$152.88 $13,446
341-7082 TACK COAT2,173 GAL $10.00$4.00$3.93 -$13,038
351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")464 SY $125.00$100.00$60.19 -$11,600
6068-7003 LED CHEVRON76 EA $2,650.00$2,500.00$1,639.96 -$11,400
666-7023 REFL PAV MRK TY I (W)8"(SLD)(090MIL)675 LF $1.00$13.50$0.9036 $8,438
666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL)36,548 LF $0.7900$1.00$0.6515 $7,675
662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-22,595 EA $0.5000$3.00$0.5715 $6,488
344-7030 SP MIXES SP-C SAC-A PG76-225,975 TON $158.00$157.00$138.38 -$5,975
533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE)18,274 LF $0.4200$0.6500$0.2394 $4,203
666-7422 REFL PAV MRK TY I (Y)6"(SLD)(090MIL)14,816 LF $0.6200$0.9000$0.5014 $4,148
685-7001 INSTALL RDSD FLASH BEACON ASSEMBLY13 EA $5,500.00$5,200.00$5,349.14 -$3,900
560-7008 MAILBOX INSTALL-S (TWW-POST) TY 417 EA $525.00$325.00$337.58 -$3,400
344-7077 TACK COAT3,260 GAL $5.00$4.00$3.25 -$3,260
505-7001 TMA (STATIONARY)31 DAY $425.00$350.00$217.57 -$2,325

Positive: the low bidder was cheaper on that item. These 20 items account for $13,517 of the $16,090 gap.

HAYDEN PAVING, INC.: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
134-7004 BACKFILL (TY A OR B)24 STA $2,300.00$211.2110.89x$50,131
351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")464 SY $125.00$60.192.08x$30,071
341-7082 TACK COAT2,173 GAL $10.00$3.932.54x$13,180
500-7001 MOBILIZATION1 LS $133,775.00$523,850.320.26x-$390,075
100-7002 PREPARING ROW9 STA $2,000.00$6,072.920.33x-$36,656

DURWOOD GREENE CONSTRUCTION CO.: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
530-7025 DRIVEWAYS AND TURNOUTS (ACP)4,789 SY $35.00$15.952.19x$91,240
500-7001 MOBILIZATION1 LS $120,000.00$523,850.320.23x-$403,850

TEXAS MATERIALS GROUP, INC.: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
6068-7003 LED CHEVRON76 EA $7,300.00$1,639.964.45x$430,163
685-7001 INSTALL RDSD FLASH BEACON ASSEMBLY13 EA $9,975.00$5,349.141.86x$60,136
134-7004 BACKFILL (TY A OR B)24 STA $2,000.00$211.219.47x$42,931
6068-7001 LEAD LED CHEVRON6 EA $6,011.00$2,246.282.68x$22,588
500-7001 MOBILIZATION1 LS $91,500.00$523,850.320.17x-$432,350
100-7002 PREPARING ROW9 STA $1,600.00$6,072.920.26x-$40,256
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING4 MO $4,845.00$11,585.040.42x-$26,960