On Call Striping District Wide FY 26
6492-49-001 · let Dec 2, 2025 · Potter, Amarillo · Routine Maintenance Project - Sealed
$1,794,755Low bid: TEXAS PANHANDLE CONSTRUCTION, INC.-21.0% vs estimate $2,272,700
$130,460Left on the table7.3% gap to the second bid
3BiddersSpread 9% low to high
49Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TEXAS PANHANDLE CONSTRUCTION, INC. | $1,794,755 | -21.0% | $130,460 | 0 | 3-$52,563 | |
| 2 | L&L COMPANY | $1,925,215 | +7.3% | -15.3% | $35,835 | 0 | 1-$22,860 |
| 3 | TRP INFRASTRUCTURE SERVICES, LLC | $1,961,050 | +9.3% | -13.7% | 2+$24,639 | 1-$21,960 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
TEXAS PANHANDLE CONSTRUCTION, INC. vs L&L COMPANY, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 668-7012 PREFAB PM TY B (W)(6")(BRK)CONTRAST | 50,000 LF | $6.40 | $9.00 | $10.48 | $130,000 |
| 666-7422 REFL PAV MRK TY I (Y)6"(SLD)(090MIL) | 700,000 LF | $0.5500 | $0.5000 | $0.5014 | -$35,000 |
| 666-7023 REFL PAV MRK TY I (W)8"(SLD)(090MIL) | 100,000 LF | $0.8800 | $0.6000 | $0.9036 | -$28,000 |
| 666-7410 REFL PAV MRK TY I (W)6"(SLD)(090MIL) | 500,000 LF | $0.5500 | $0.5000 | $0.4886 | -$25,000 |
| 668-7024 PREFAB PM TY B (W)(DBL ARROW) | 100 EA | $490.00 | $300.00 | $556.90 | -$19,000 |
| 677-7002 ELIM EXT PM & MRKS (6") | 100,000 LF | $0.2900 | $0.4500 | $0.2755 | $16,000 |
| 677-7008 ELIM EXT PM & MRKS (24") | 10,000 LF | $0.8000 | $2.00 | $2.87 | $12,000 |
| 672-7001 REFL PAV MRKR TY I-A | 5,000 EA | $2.75 | $5.00 | $3.89 | $11,250 |
| 672-7002 REFL PAV MRKR TY I-C | 5,000 EA | $2.75 | $5.00 | $4.04 | $11,250 |
| 672-7004 REFL PAV MRKR TY II-A-A | 5,000 EA | $2.95 | $5.00 | $3.97 | $10,250 |
| 672-7006 REFL PAV MRKR TY II-C-R | 5,000 EA | $3.00 | $5.00 | $4.19 | $10,000 |
| 666-7407 REFL PAV MRK TY I (W)6"(BRK)(090MIL) | 100,000 LF | $0.5700 | $0.5000 | $0.5397 | -$7,000 |
| 666-7080 REFL PAV MRK TY I (W)(RR XING)(090MIL) | 50 EA | $275.00 | $400.00 | $484.40 | $6,250 |
| 666-7212 RE PM TY II (Y) 6" (DOT) | 20,000 LF | $0.0100 | $0.3000 | $0.0424 | $5,800 |
| 533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE) | 100,000 LF | $0.2700 | $0.2200 | $0.2394 | -$5,000 |
| 666-7008 REFL PAV MRK TY I (W)6"(DOT)(090MIL) | 20,000 LF | $0.5500 | $0.8000 | $0.9352 | $5,000 |
| 677-7010 ELIM EXT PM & MRKS (DBL ARROW) | 110 EA | $15.00 | $60.00 | $65.64 | $4,950 |
| 666-7035 REFL PAV MRK TY I (W)24"(SLD)(090MIL) | 10,000 LF | $4.45 | $4.00 | $7.10 | -$4,500 |
| 666-7239 RE PM TY III (W)(8")(SLD) | 10,000 LF | $0.7500 | $1.20 | $1.06 | $4,500 |
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR) | 100,000 LF | $0.2400 | $0.2000 | $0.2040 | -$4,000 |
Positive: the low bidder was cheaper on that item. These 20 items account for $99,750 of the $130,460 gap.
TEXAS PANHANDLE CONSTRUCTION, INC.: unbalanced items
Placed 1L&L COMPANY: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 100 DAY | $1.00 | $229.60 | 0.00x | -$22,860 |