Dumas Area Gr 4 & Gr 5 Aggregate
6497-48-001 · let Mar 4, 2026 · Hutchinson, Amarillo · Material Maintenance Project
$1,456,985Low bid: VOLCANIC STONE CO.+5.4% vs estimate $1,382,493
$23,050Left on the table1.6% gap to the second bid
2BiddersSpread 2% low to high
10Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | VOLCANIC STONE CO. | $1,456,985 | 5.4% | $23,050 | 0 | 0 | |
| 2 | SOUTHERN SOURCING SOLUTIONS, LLC | $1,480,035 | +1.6% | 7.1% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
VOLCANIC STONE CO. vs SOUTHERN SOURCING SOLUTIONS, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8000-7190 AGGR (TY E GR 4) (DEL) (ST8) | 7,000 TON | $72.42 | $84.56 | $80.95 | $84,980 |
| 8000-7191 AGGR (TY E GR 4) (DEL) (ST9) | 4,000 TON | $84.68 | $72.69 | $79.55 | -$47,960 |
| 8000-7185 AGGR (TY E GR 4) (DEL) (ST3) | 500 TON | $96.66 | $63.56 | $91.35 | -$16,550 |
| 8000-7192 AGGR (TY E GR 4) (DEL) (ST10) | 500 TON | $93.15 | $72.99 | $88.73 | -$10,080 |
| 8000-7218 AGGR (TY E GR 5) (DEL) (ST8) | 500 TON | $66.07 | $84.56 | $87.33 | $9,245 |
| 8000-7224 AGGR (TY E GR 5) (DEL) (ST14) | 500 TON | $75.70 | $82.73 | $80.94 | $3,515 |
| 8000-7219 AGGR (TY E GR 5) (DEL) (ST9) | 500 TON | $78.33 | $72.69 | $89.63 | -$2,820 |
| 8000-7196 AGGR (TY E GR 4) (DEL) (ST14) | 2,000 TON | $82.05 | $82.73 | $88.55 | $1,360 |
| 8000-7216 AGGR (TY E GR 5) (DEL) (ST6) | 200 TON | $74.83 | $81.21 | $95.12 | $1,276 |
| 8000-7188 AGGR (TY E GR 4) (DEL) (ST6) | 2,800 TON | $81.18 | $81.21 | $81.10 | $84 |
Positive: the low bidder was cheaper on that item. These 10 items account for $23,050 of the $23,050 gap.