Win Price: 0069-10-003

Howard · lets Jan 6, 2027 Sign up free

‹ All Win Price jobs Job page Bid Day Forecast

Bridge Maintenance

Unofficial

CCSJ 0069-10-003 · lets Wednesday, Jan 6, 2027 · Howard, Abilene · US 87 · Bridge Maintenance

$1,178,443Predicted low bid-13.1% vs the engineer's estimate of $1,356,095
$1,017,797 – $1,321,365Likely rangeThe low bid lands here about half the time. 8 in 10: $882,965 to $1,463,412
5.0Expected biddersFrom similar jobs; no plan holders posted yet
MediumConfidenceBacked by 1,373 closely comparable lettings (2,353 in all)

Where the low bid should land

$882,965: 1 in 10 low bids go lower$1,463,412: 1 in 10 go higher

What it takes to be lowest

Bid undervs estimateChance you are lowest
$882,965-34.9% 90%
$1,017,797-24.9% 75%
$1,178,443-13.1% 50%
$1,321,365-2.6% 25%
$1,463,412+7.9% 10%

Chance that no other bid comes in under yours, from how low bids on jobs like this one landed, corrected by how our past predictions actually turned out.

Check my estimate

Add your priced items for a line-by-line check

With items and no total, your total is the sum of the items.

Your numbers are used for this check only and are not saved.

The field: who is likely to bid

Plan holders, last 3 years of Texas bids

No plan holders posted for this job yet. The expected field comes from similar jobs until they are.

Lettings most like this one

The closest of the jobs behind this prediction
LetCCSJWhereWorkBiddersEstimateLow bidLow bidder
Oct 20266505-07-001 HowardAbileneRoutine Maintenance Project - Sealed4 $994,160$672,620-32.3% ROSS SA ENTERPRISE LLC
Oct 20266505-06-001 TaylorAbileneRoutine Maintenance Project - Sealed3 $983,600$640,990-34.8% ROSS SA ENTERPRISE LLC
Oct 20266505-56-001 HowardAbileneRoutine Maintenance Project - Sealed4 $961,136$1,017,742+5.9% T&L CLEANING SERVICES LLC
May 20252398-01-057 TaylorAbileneBridge Maintenance9 $1,390,494$1,338,127-3.8% TI-ZACK CONCRETE, LLC
Aug 20266506-65-001 NolanAbileneMaterial Maintenance Project1 $994,550$991,674-0.3% J. H. STRAIN & SONS, INC.
Sep 20266492-74-001 TaylorAbileneBridge Preventative Maintenance12 $937,100$685,424-26.9% BLACKSMITH VENTURES LLC
Jul 20260053-08-077 ScurryAbileneSafety Improvement Projects6 $1,032,036$814,950-21.0% WILLIS ELECTRIC CO., LP
Nov 20260074-06-256 NuecesCorpus ChristiBridge Maintenance4 $1,598,349$849,655-46.8% RELMCO, INC.
Dec 20256492-52-001 TaylorAbileneRoutine Maintenance Project - Sealed4 $1,381,930$845,277-38.8% BK FIELD OPERATIONS LLC
Feb 20266494-19-001 TaylorAbileneRoutine Maintenance Project - Sealed2 $992,225$881,525-11.2% VACA UNDERGROUND UTILITIES INC

How it works: Win Price weighs every Texas letting of the last 3 years by how much it is like this job (size, district, type of work, how recent, and the size of the field) and reads where their low bids landed against the estimate. See the accuracy test. A prediction, not a promise: always price the job yourself.