NuecesIH37RRBridgeRemoval
0074-06-256 · let Nov 4, 2026 · Nueces, Corpus Christi · Bridge Maintenance
$849,655Low bid: RELMCO, INC.-46.8% vs estimate $1,598,349
$129,345Left on the table15.2% gap to the second bid
4BiddersSpread 207% low to high
27Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | RELMCO, INC. | $849,655 | -46.8% | $129,345 | 9+$267,428 | 1-$453,850 | |
| 2 | DIGG COMMERCIAL, LLC | $979,000 | +15.2% | -38.7% | $1,155,370 | 10+$302,601 | 2-$386,793 |
| 3 | BLACKSMITH VENTURES LLC | $2,134,370 | +151.2% | 33.5% | $470,217 | 11+$1,422,422 | 3-$352,590 |
| 4 | TEXAS MATERIALS GROUP, INC. | $2,604,587 | +206.5% | 63.0% | 14+$1,876,309 | 3-$373,570 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
RELMCO, INC. vs DIGG COMMERCIAL, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $245,000.00 | $100,000.00 | $136,676.66 | -$145,000 |
| 505-7001 TMA (STATIONARY) | 76 DAY | $150.00 | $1,500.00 | $217.57 | $102,600 |
| 500-7001 MOBILIZATION | 1 LS | $70,000.00 | $158,200.00 | $523,850.32 | $88,200 |
| 496-7025 REMOV STR (RR TIMBER TIES) | 10 EA | $6,500.00 | $400.00 | $2,514.29 | -$61,000 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 171 DAY | $150.00 | $500.00 | $87.82 | $59,850 |
| 496-7015 REMOV STR (BENT) | 5 EA | $15,000.00 | $25,000.00 | $23,727.35 | $50,000 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 700 LF | $50.00 | $100.00 | $52.29 | $35,000 |
| 5011-7002 REMOVE LEAD-CONTAINING COATING (OTHER) | 1 LS | $55,000.00 | $20,000.00 | $15,780.56 | -$35,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $6,500.00 | $14,000.00 | $11,585.04 | $30,000 |
| 505-7003 TMA (MOBILE OPERATION) | 23 DAY | $150.00 | $1,000.00 | $229.60 | $19,550 |
| 432-7001 RIPRAP (CONC)(4 IN) | 20 CY | $750.00 | $1,500.00 | $573.24 | $15,000 |
| 545-7006 CRASH CUSH ATTEN (INSTL)(L)(N)(TL3) | 2 EA | $38,500.00 | $33,000.00 | $26,188.60 | -$11,000 |
| 514-7001 PERM CTB (SGL SLOPE) (TY 1) (42 ) | 95 LF | $200.00 | $300.00 | $86.62 | $9,500 |
| 104-7035 REMOV CONC (TRAFFIC BARRIER) | 168 LF | $100.00 | $50.00 | $16.21 | -$8,400 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 700 LF | $40.00 | $30.00 | $12.08 | -$7,000 |
| 764-7001 DRAIN INLET CLEANING | 3 EA | $2,500.00 | $200.00 | $124.25 | -$6,900 |
| 496-7014 REMOV STR (ABUTMENT) | 2 EA | $10,500.00 | $7,500.00 | $7,175.00 | -$6,000 |
| 506-7044 BIODEG EROSN CONT LOGS (INSTL) (12") | 80 LF | $15.00 | $50.00 | $5.23 | $2,800 |
| 110-7003 EXCAV (SPECIAL) | 15 CY | $300.00 | $142.00 | $18.78 | -$2,370 |
| 496-7026 REMOV STR (RR TRACK) | 75 LF | $50.00 | $80.00 | $64.68 | $2,250 |
Positive: the low bidder was cheaper on that item. These 20 items account for $132,080 of the $129,345 gap.
RELMCO, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $245,000.00 | $136,676.66 | 1.79x | $108,323 |
| 496-7025 REMOV STR (RR TIMBER TIES) | 10 EA | $6,500.00 | $2,514.29 | 2.59x | $39,857 |
| 5011-7002 REMOVE LEAD-CONTAINING COATING (OTHER) | 1 LS | $55,000.00 | $15,780.56 | 3.49x | $39,219 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 700 LF | $40.00 | $12.08 | 3.31x | $19,542 |
| 5009-7001 ABATE ASBESTOS (COATINGS) | 500 SF | $44.00 | $9.62 | 4.58x | $17,192 |
| 104-7035 REMOV CONC (TRAFFIC BARRIER) | 168 LF | $100.00 | $16.21 | 6.17x | $14,076 |
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 75 SY | $200.00 | $49.06 | 4.08x | $11,320 |
| 514-7001 PERM CTB (SGL SLOPE) (TY 1) (42 ) | 95 LF | $200.00 | $86.62 | 2.31x | $10,771 |
| 764-7001 DRAIN INLET CLEANING | 3 EA | $2,500.00 | $124.25 | 20.12x | $7,127 |
| 500-7001 MOBILIZATION | 1 LS | $70,000.00 | $523,850.32 | 0.13x | -$453,850 |
DIGG COMMERCIAL, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 76 DAY | $1,500.00 | $217.57 | 6.89x | $97,465 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 171 DAY | $500.00 | $87.82 | 5.69x | $70,483 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 700 LF | $100.00 | $52.29 | 1.91x | $33,398 |
| 514-7001 PERM CTB (SGL SLOPE) (TY 1) (42 ) | 95 LF | $300.00 | $86.62 | 3.46x | $20,271 |
| 432-7001 RIPRAP (CONC)(4 IN) | 20 CY | $1,500.00 | $573.24 | 2.62x | $18,535 |
| 505-7003 TMA (MOBILE OPERATION) | 23 DAY | $1,000.00 | $229.60 | 4.36x | $17,719 |
| 5009-7001 ABATE ASBESTOS (COATINGS) | 500 SF | $40.00 | $9.62 | 4.16x | $15,192 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 700 LF | $30.00 | $12.08 | 2.48x | $12,542 |
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 75 SY | $200.00 | $49.06 | 4.08x | $11,320 |
| 104-7035 REMOV CONC (TRAFFIC BARRIER) | 168 LF | $50.00 | $16.21 | 3.08x | $5,676 |
| 500-7001 MOBILIZATION | 1 LS | $158,200.00 | $523,850.32 | 0.30x | -$365,650 |
| 496-7025 REMOV STR (RR TIMBER TIES) | 10 EA | $400.00 | $2,514.29 | 0.16x | -$21,143 |
BLACKSMITH VENTURES LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $450,000.00 | $136,676.66 | 3.29x | $313,323 |
| 496-7015 REMOV STR (BENT) | 5 EA | $75,000.00 | $23,727.35 | 3.16x | $256,363 |
| 5011-7002 REMOVE LEAD-CONTAINING COATING (OTHER) | 1 LS | $260,000.00 | $15,780.56 | 16.48x | $244,219 |
| 496-7014 REMOV STR (ABUTMENT) | 2 EA | $120,000.00 | $7,175.00 | 16.72x | $225,650 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $60,000.00 | $11,585.04 | 5.18x | $193,660 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 700 LF | $140.00 | $52.29 | 2.68x | $61,398 |
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 75 SY | $500.00 | $49.06 | 10.19x | $33,820 |
| 104-7035 REMOV CONC (TRAFFIC BARRIER) | 168 LF | $200.00 | $16.21 | 12.34x | $30,876 |
| 5009-7001 ABATE ASBESTOS (COATINGS) | 500 SF | $60.00 | $9.62 | 6.24x | $25,192 |
| 514-7001 PERM CTB (SGL SLOPE) (TY 1) (42 ) | 95 LF | $300.00 | $86.62 | 3.46x | $20,271 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |
| 496-7025 REMOV STR (RR TIMBER TIES) | 10 EA | $800.00 | $2,514.29 | 0.32x | -$17,143 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 171 DAY | $20.00 | $87.82 | 0.23x | -$11,597 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $1,350,000.00 | $136,676.66 | 9.88x | $1,213,323 |
| 496-7015 REMOV STR (BENT) | 5 EA | $49,200.00 | $23,727.35 | 2.07x | $127,363 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 700 LF | $110.00 | $12.08 | 9.10x | $68,542 |
| 5009-7001 ABATE ASBESTOS (COATINGS) | 500 SF | $140.00 | $9.62 | 14.56x | $65,192 |
| 5011-7002 REMOVE LEAD-CONTAINING COATING (OTHER) | 1 LS | $70,000.00 | $15,780.56 | 4.44x | $54,219 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $25,000.00 | $11,585.04 | 2.16x | $53,660 |
| 496-7014 REMOV STR (ABUTMENT) | 2 EA | $33,900.00 | $7,175.00 | 4.72x | $53,450 |
| 514-7001 PERM CTB (SGL SLOPE) (TY 1) (42 ) | 95 LF | $630.00 | $86.62 | 7.27x | $51,621 |
| 505-7001 TMA (STATIONARY) | 76 DAY | $860.00 | $217.57 | 3.95x | $48,825 |
| 432-7001 RIPRAP (CONC)(4 IN) | 20 CY | $2,600.00 | $573.24 | 4.54x | $40,535 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |
| 545-7006 CRASH CUSH ATTEN (INSTL)(L)(N)(TL3) | 2 EA | $10,800.00 | $26,188.60 | 0.41x | -$30,777 |
| 496-7025 REMOV STR (RR TIMBER TIES) | 10 EA | $620.00 | $2,514.29 | 0.25x | -$18,943 |