Callout Illumination
6494-19-001 · let Feb 11, 2026 · Taylor, Abilene · Routine Maintenance Project - Sealed
$881,525Low bid: VACA UNDERGROUND UTILITIES INC-11.2% vs estimate $992,225
$151,199Left on the table17.2% gap to the second bid
2BiddersSpread 17% low to high
25Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | VACA UNDERGROUND UTILITIES INC | $881,525 | -11.2% | $151,199 | 4+$128,468 | 1-$15,661 | |
| 2 | WG ENGINEERING & CONSTRUCTION, LLC | $1,032,724 | +17.2% | 4.1% | 10+$228,934 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
VACA UNDERGROUND UTILITIES INC vs WG ENGINEERING & CONSTRUCTION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 690-7165 INSTALL ROADWAY ILLUM ASSEMBLY (LED) | 45 EA | $2,500.00 | $4,757.00 | $2,412.45 | $101,565 |
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $10,000.00 | $2,250.00 | $600.85 | -$46,500 |
| 500-7003 MOBILIZATION (CALLOUT 1) | 6 EA | $10,000.00 | $2,455.00 | $599.93 | -$45,270 |
| 690-7242 TROUBLESHOOT FOR REPAIRS | 125 HR | $200.00 | $350.00 | $142.93 | $18,750 |
| 618-7055 CONDT (PVC) (SCH 80) (2") (BORE) | 1,000 LF | $20.00 | $38.00 | $20.33 | $18,000 |
| 416-7040 DRILL SHAFT (RDWY ILL POLE) (30 IN) | 272 LF | $300.00 | $362.00 | $270.84 | $16,864 |
| 690-7218 REPLACE FUSE | 60 EA | $75.00 | $350.00 | $47.51 | $16,500 |
| 690-7197 REPLACE TRANSFORMER BASE | 30 EA | $900.00 | $1,355.00 | $806.00 | $13,650 |
| 618-7054 CONDT (PVC) (SCH 80) (2") | 1,000 LF | $15.00 | $24.00 | $12.03 | $9,000 |
| 628-7002 REMOVE ELECTRICAL SERVICES | 13 EA | $750.00 | $1,400.00 | $671.28 | $8,450 |
| 505-7001 TMA (STATIONARY) | 80 DAY | $150.00 | $250.00 | $217.57 | $8,000 |
| 690-7065 REPLACE OF LUMINAIRE HEAD | 45 EA | $275.00 | $450.00 | $623.02 | $7,875 |
| 690-7157 INSTALL ELECTRICAL SPLICE | 25 EA | $175.00 | $400.00 | $52.25 | $5,625 |
| 624-7002 GROUND BOX TY A (122311)W/APRON | 60 EA | $1,400.00 | $1,488.00 | $1,460.15 | $5,280 |
| 620-7007 ELEC CONDR (NO.8) BARE | 10,000 LF | $2.50 | $3.00 | $1.94 | $5,000 |
| 620-7008 ELEC CONDR (NO.8) INSULATED | 20,000 LF | $2.75 | $3.00 | $2.11 | $5,000 |
| 690-7006 REMOVAL OF GROUND BOXES | 45 EA | $450.00 | $350.00 | $253.15 | -$4,500 |
| 618-7052 CONDT (PVC) (SCH 80) (1 1/2") | 1,000 LF | $11.00 | $15.00 | $12.49 | $4,000 |
| 690-7219 REPLACE FUSE HOLDER | 50 EA | $275.00 | $350.00 | $138.71 | $3,750 |
| 690-7063 REMOVAL OF CONCRETE FOUNDATIONS | 20 EA | $1,000.00 | $850.00 | $1,138.28 | -$3,000 |
Positive: the low bidder was cheaper on that item. These 20 items account for $148,039 of the $151,199 gap.
VACA UNDERGROUND UTILITIES INC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7003 MOBILIZATION (CALLOUT 1) | 6 EA | $10,000.00 | $599.93 | 16.67x | $56,400 |
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $10,000.00 | $600.85 | 16.64x | $56,395 |
| 690-7006 REMOVAL OF GROUND BOXES | 45 EA | $450.00 | $253.15 | 1.78x | $8,858 |
| 690-7219 REPLACE FUSE HOLDER | 50 EA | $275.00 | $138.71 | 1.98x | $6,814 |
| 690-7065 REPLACE OF LUMINAIRE HEAD | 45 EA | $275.00 | $623.02 | 0.44x | -$15,661 |
WG ENGINEERING & CONSTRUCTION, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 690-7165 INSTALL ROADWAY ILLUM ASSEMBLY (LED) | 45 EA | $4,757.00 | $2,412.45 | 1.97x | $105,505 |
| 690-7242 TROUBLESHOOT FOR REPAIRS | 125 HR | $350.00 | $142.93 | 2.45x | $25,883 |
| 690-7218 REPLACE FUSE | 60 EA | $350.00 | $47.51 | 7.37x | $18,150 |
| 618-7055 CONDT (PVC) (SCH 80) (2") (BORE) | 1,000 LF | $38.00 | $20.33 | 1.87x | $17,674 |
| 618-7054 CONDT (PVC) (SCH 80) (2") | 1,000 LF | $24.00 | $12.03 | 1.99x | $11,966 |
| 500-7003 MOBILIZATION (CALLOUT 1) | 6 EA | $2,455.00 | $599.93 | 4.09x | $11,130 |
| 690-7219 REPLACE FUSE HOLDER | 50 EA | $350.00 | $138.71 | 2.52x | $10,564 |
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $2,250.00 | $600.85 | 3.74x | $9,895 |
| 628-7002 REMOVE ELECTRICAL SERVICES | 13 EA | $1,400.00 | $671.28 | 2.09x | $9,473 |
| 690-7157 INSTALL ELECTRICAL SPLICE | 25 EA | $400.00 | $52.25 | 7.66x | $8,694 |