Win Price: 0042-01-032

Carson, Potter · lets Dec 2, 2026 Sign up free

‹ All Win Price jobs Job page Bid Day Forecast

Safety Improvement Projects

Official

CCSJ 0042-01-032 · lets Wednesday, Dec 2, 2026 · Carson, Potter, Amarillo · IH 40, SS 228, US 287 · Intersection Improvements With Right And/Or Left T

$7,076,202Predicted low bid-9.1% vs the engineer's estimate of $7,782,909
$6,349,092 – $7,744,260Likely rangeThe low bid lands here about half the time. 8 in 10: $5,484,950 to $8,483,710
2.4Expected bidders4 plan holders so far
HighConfidenceBacked by 367 closely comparable lettings (1,009 in all)

Where the low bid should land

$5,484,950: 1 in 10 low bids go lower$8,483,710: 1 in 10 go higher

What it takes to be lowest

Bid undervs estimateChance you are lowest
$5,484,950-29.5% 90%
$6,349,092-18.4% 75%
$7,076,202-9.1% 50%
$7,744,260-0.5% 25%
$8,483,710+9.0% 10%

Chance that no other bid comes in under yours, from how low bids on jobs like this one landed, corrected by how our past predictions actually turned out.

Check my estimate

Add your priced items for a line-by-line check

With items and no total, your total is the sum of the items.

Your numbers are used for this check only and are not saved.

The field: who is likely to bid

Plan holders, last 3 years of Texas bids
Plan holderChance they bidBidsWinsAvg bid vs est.Their typical bid here
L A FULLER & SONS CONSTRUCTION, LTD.Bidders 60% 4219 3.7% $8,068,886
J. LEE MILLIGAN, INC.Bidders 60% 4911 10.6% $8,605,742
GILVIN-TERRILL, LTD.Bidders 60% 746 23.4% $9,603,552
RK HALL, LLCBidders 60% 17273 3.2% $8,033,052

Chance they bid comes from how often each company bids prime contracts and, where we can see it, how many of the plan sets they took turned into bids. Plan holders with no bids are usually suppliers and subs.

Lettings most like this one

The closest of the jobs behind this prediction
LetCCSJWhereWorkBiddersEstimateLow bidLow bidder
Nov 20266510-98-001 GrayAmarilloMaterial Maintenance Project3 $5,284,907$3,073,285-41.8% L A FULLER & SONS CONSTRUCTION, LTD.
Jul 20261421-01-027 LibertyBeaumontSafety Improvement Projects3 $6,892,327$5,657,771-17.9% DURWOOD GREENE CONSTRUCTION CO.
May 20266497-68-001 PotterAmarilloRoutine Maintenance Project - Sealed1 $6,607,850$6,531,750-1.2% J. LEE MILLIGAN, INC.
Aug 20260420-01-051 JacksonYoakumSafety Improvement Projects3 $5,670,190$5,347,067-5.7% STX CIVIL
Aug 20266505-55-001 HutchinsonAmarilloMaterial Maintenance Project2 $4,090,043$4,484,629+9.6% NSG LOGISTICS, LLC
May 20260176-01-116 NacogdochesLufkinSafety Improvement Projects3 $6,169,821$5,689,159-7.8% TEXAS MATERIALS GROUP, INC.
Jun 20260042-05-033 ArmstrongAmarilloSafety Improvement Projects6 $8,256,774$6,922,966-16.2% HJC FARMS, INC.
Jan 20250066-04-084 MooreAmarilloSafety Improvement Projects4 $5,971,613$5,565,020-6.8% HJC FARMS, INC.
Aug 20262552-04-055 El PasoEl PasoSafety Improvement Projects4 $6,949,288$6,996,636+0.7% ALBATROSS CONSTRUCTION LLC
Sep 20260056-02-034 LimestoneWacoSeal Coat2 $8,515,420$8,156,832-4.2% COX PAVING OF TEXAS, INC.

How it works: Win Price weighs every Texas letting of the last 3 years by how much it is like this job (size, district, type of work, how recent, and the size of the field) and reads where their low bids landed against the estimate. See the accuracy test. A prediction, not a promise: always price the job yourself.