FM 1413-2020 HSIP (STFO, MILLED E/L RS)
1421-01-027 · let Jul 2, 2026 · Liberty, Beaumont · Safety Improvement Projects
$5,657,771Low bid: DURWOOD GREENE CONSTRUCTION CO.-17.9% vs estimate $6,892,327
$5,676Left on the table0.1% gap to the second bid
3BiddersSpread 20% low to high
110Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | DURWOOD GREENE CONSTRUCTION CO. | $5,657,771 | -17.9% | $5,676 | 1+$47,959 | 2-$1,038,601 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $5,663,447 | +0.1% | -17.8% | $1,137,081 | 3+$187,703 | 3-$1,098,221 |
| 3 | HAYDEN PAVING, INC. | $6,800,528 | +20.2% | -1.3% | 4+$632,597 | 3-$1,114,621 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
DURWOOD GREENE CONSTRUCTION CO. vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 973 CY | $700.00 | $479.00 | $616.83 | -$215,033 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 22,175 LF | $28.00 | $22.85 | $25.60 | -$114,201 |
| 500-7001 MOBILIZATION | 1 LS | $142,000.00 | $225,000.00 | $523,850.32 | $83,000 |
| 134-7004 BACKFILL (TY A OR B) | 289 STA | $250.00 | $528.00 | $211.21 | $80,342 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $6,000.00 | $1,350.00 | $11,585.04 | -$55,800 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 23 EA | $3,750.00 | $6,120.00 | $3,190.07 | $54,510 |
| 341-7064 D-GR HMA TY-D PG 64-22 (EXEMPT) | 6,718 TON | $124.00 | $131.00 | $152.88 | $47,026 |
| 530-7022 INTRSCT, DRVWAYS, & TURNOUT (ACP) | 2,552 SY | $26.00 | $44.00 | $42.62 | $45,936 |
| 316-7067 ASPH (AC-20-5TR OR AC-20XP) | 34,518 GAL | $3.30 | $4.50 | $3.44 | $41,422 |
| 505-7003 TMA (MOBILE OPERATION) | 50 DAY | $200.00 | $626.00 | $229.60 | $21,300 |
| 658-7036 INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2 | 1,117 EA | $22.00 | $41.00 | $37.39 | $21,223 |
| 100-7002 PREPARING ROW | 120 STA | $600.00 | $435.00 | $6,072.92 | -$19,800 |
| 354-7032 PLANE ASPH CONC PAV(0" TO 2") | 6,094 SY | $10.00 | $6.85 | $2.13 | -$19,196 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 7,380 SY | $80.00 | $77.50 | $60.19 | -$18,450 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $10,000.00 | $18,590.00 | $9,253.78 | $17,180 |
| 341-7001 D-GR HMA TY-B PG64-22 | 62 TON | $130.00 | $376.00 | $97.82 | $15,252 |
| 540-7015 DOWNSTREAM ANCHOR TERMINAL SECTION | 2 EA | $1,400.00 | $8,960.00 | $1,297.32 | $15,120 |
| 544-7003 GUARDRAIL END TREATMENT (REMOVE) | 6 EA | $300.00 | $2,700.00 | $284.94 | $14,400 |
| 467-7328 SET (TY II) (24 IN) (RCP) (6: 1) (P) | 18 EA | $2,700.00 | $1,950.00 | $1,883.43 | -$13,500 |
| 530-7015 DRIVEWAYS (BASE) | 774 SY | $25.00 | $41.00 | $27.85 | $12,384 |
Positive: the low bidder was cheaper on that item. These 20 items account for $13,114 of the $5,676 gap.
DURWOOD GREENE CONSTRUCTION CO.: unbalanced items
Placed 1TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 134-7004 BACKFILL (TY A OR B) | 289 STA | $528.00 | $211.21 | 2.50x | $91,552 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 23 EA | $6,120.00 | $3,190.07 | 1.92x | $67,388 |
| 354-7032 PLANE ASPH CONC PAV(0" TO 2") | 6,094 SY | $6.85 | $2.13 | 3.22x | $28,762 |
| 100-7002 PREPARING ROW | 120 STA | $435.00 | $6,072.92 | 0.07x | -$676,551 |
| 500-7001 MOBILIZATION | 1 LS | $225,000.00 | $523,850.32 | 0.43x | -$298,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $1,350.00 | $11,585.04 | 0.12x | -$122,821 |
HAYDEN PAVING, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 7,380 SY | $108.00 | $60.19 | 1.79x | $352,829 |
| 316-7245 AGGR (TY-PB OR PL, GR-4)(SAC-B) | 738 CY | $344.00 | $165.18 | 2.08x | $131,971 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 23 EA | $7,181.00 | $3,190.07 | 2.25x | $91,791 |
| 134-7004 BACKFILL (TY A OR B) | 289 STA | $405.00 | $211.21 | 1.92x | $56,005 |
| 100-7002 PREPARING ROW | 120 STA | $1,050.00 | $6,072.92 | 0.17x | -$602,751 |
| 500-7001 MOBILIZATION | 1 LS | $85,000.00 | $523,850.32 | 0.16x | -$438,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $5,500.00 | $11,585.04 | 0.47x | -$73,021 |