ELP_SL0375_1-SYS (2022)
2552-04-055 · let Aug 6, 2026 · El Paso, El Paso · Safety Improvement Projects
$6,996,636Low bid: ALBATROSS CONSTRUCTION LLC+0.7% vs estimate $6,949,288
$661,556Left on the table9.5% gap to the second bid
4BiddersSpread 26% low to high
74Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ALBATROSS CONSTRUCTION LLC | $6,996,636 | 0.7% | $661,556 | 3+$236,776 | 1-$78,429 | |
| 2 | MARTINEZ BROS. CONTRACTORS, LLC | $7,658,192 | +9.5% | 10.2% | $252,851 | 1+$72,784 | 0 |
| 3 | TRI STATE ELECTRIC, LTD. | $7,911,043 | +13.1% | 13.8% | $897,111 | 5+$385,531 | 1-$513,850 |
| 4 | DIGG COMMERCIAL, LLC | $8,808,153 | +25.9% | 26.7% | 4+$1,107,345 | 1-$136,575 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
ALBATROSS CONSTRUCTION LLC vs MARTINEZ BROS. CONTRACTORS, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 613-7005 HI MST IL POLE (150 FT)( 80 MPH) | 40 EA | $47,382.85 | $55,200.00 | $51,496.56 | $312,686 |
| 614-7010 LED HI MST IL ASM(6 FIXT) (TY B)SHLD | 34 EA | $39,305.21 | $46,718.75 | $39,795.15 | $252,060 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 10 MO | $3,742.10 | $14,938.50 | $11,585.04 | $111,964 |
| 610-7008 REMOVE RD IL ASM (CTB MOUNT) | 129 EA | $266.26 | $1,035.00 | $470.78 | $99,167 |
| 500-7001 MOBILIZATION | 1 LS | $354,456.70 | $270,000.00 | $523,850.32 | -$84,457 |
| 514-7013 PERM CTB (F-SHAPE) (TY 1) | 330 LF | $402.50 | $165.60 | $94.94 | -$78,177 |
| 545-7015 CRASH CUSH ATTEN (INSTL)(S)(W)(TL2) | 9 EA | $16,675.00 | $11,500.00 | $16,675.00 | -$46,575 |
| 618-7030 CONDT (PVC) (SCH 40) (2") | 28,040 LF | $13.35 | $14.95 | $13.17 | $44,864 |
| 614-7003 LED HI MST IL ASM (6 FIXT) (TY B) | 6 EA | $38,185.68 | $45,568.75 | $41,290.78 | $44,298 |
| 620-7010 ELEC CONDR (NO.6) INSULATED | 98,070 LF | $1.89 | $2.30 | $2.58 | $40,209 |
| 618-7031 CONDT (PVC) (SCH 40) (2") (BORE) | 3,480 LF | $45.06 | $34.50 | $25.51 | -$36,749 |
| 540-7002 MTL W-BEAM GD FEN (STEEL POST) | 2,750 LF | $55.20 | $43.70 | $30.74 | -$31,625 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 107.46 CY | $977.50 | $690.00 | $616.83 | -$30,895 |
| 624-7002 GROUND BOX TY A (122311)W/APRON | 100 EA | $972.81 | $1,265.00 | $1,460.15 | $29,219 |
| 505-7001 TMA (STATIONARY) | 180 DAY | $225.00 | $373.75 | $217.57 | $26,775 |
| 6106-7002 REMOVE EXISTING CABLES (POWER) | 33,930 LF | $0.4300 | $1.15 | $0.9415 | $24,430 |
| 110-7003 EXCAV (SPECIAL) | 21 CY | $212.75 | $856.75 | $18.78 | $13,524 |
| 432-7001 RIPRAP (CONC)(4 IN) | 61.44 CY | $902.75 | $690.00 | $573.24 | -$13,071 |
| 6103-7001 MODIFY EXISTING ELECTRICAL SERVICE | 6 EA | $6,771.66 | $4,600.00 | $4,515.00 | -$13,030 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $20,125.00 | $14,950.00 | $9,253.78 | -$10,350 |
Positive: the low bidder was cheaper on that item. These 20 items account for $654,268 of the $661,556 gap.
ALBATROSS CONSTRUCTION LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 514-7013 PERM CTB (F-SHAPE) (TY 1) | 330 LF | $402.50 | $94.94 | 4.24x | $101,494 |
| 618-7031 CONDT (PVC) (SCH 40) (2") (BORE) | 3,480 LF | $45.06 | $25.51 | 1.77x | $68,026 |
| 540-7002 MTL W-BEAM GD FEN (STEEL POST) | 2,750 LF | $55.20 | $30.74 | 1.80x | $67,255 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 10 MO | $3,742.10 | $11,585.04 | 0.32x | -$78,429 |
MARTINEZ BROS. CONTRACTORS, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 610-7008 REMOVE RD IL ASM (CTB MOUNT) | 129 EA | $1,035.00 | $470.78 | 2.20x | $72,784 |
TRI STATE ELECTRIC, LTD.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 514-7013 PERM CTB (F-SHAPE) (TY 1) | 330 LF | $395.00 | $94.94 | 4.16x | $99,019 |
| 540-7002 MTL W-BEAM GD FEN (STEEL POST) | 2,750 LF | $60.00 | $30.74 | 1.95x | $80,455 |
| 540-7015 DOWNSTREAM ANCHOR TERMINAL SECTION | 18 EA | $5,632.00 | $1,297.32 | 4.34x | $78,024 |
| 6106-7002 REMOVE EXISTING CABLES (POWER) | 33,930 LF | $2.95 | $0.9415 | 3.13x | $68,148 |
| 610-7008 REMOVE RD IL ASM (CTB MOUNT) | 129 EA | $935.00 | $470.78 | 1.99x | $59,884 |
| 500-7001 MOBILIZATION | 1 LS | $10,000.00 | $523,850.32 | 0.02x | -$513,850 |
DIGG COMMERCIAL, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 618-7030 CONDT (PVC) (SCH 40) (2") | 28,040 LF | $30.00 | $13.17 | 2.28x | $471,846 |
| 505-7001 TMA (STATIONARY) | 180 DAY | $2,500.00 | $217.57 | 11.49x | $410,837 |
| 618-7031 CONDT (PVC) (SCH 40) (2") (BORE) | 3,480 LF | $70.00 | $25.51 | 2.74x | $154,818 |
| 6106-7002 REMOVE EXISTING CABLES (POWER) | 33,930 LF | $3.00 | $0.9415 | 3.19x | $69,845 |
| 545-7015 CRASH CUSH ATTEN (INSTL)(S)(W)(TL2) | 9 EA | $1,500.00 | $16,675.00 | 0.09x | -$136,575 |