US 287 SAFETY LIGHTING 1/1
0042-05-033 · let Jun 2, 2026 · Armstrong, Amarillo · Safety Improvement Projects
$6,922,966Low bid: HJC FARMS, INC.-16.2% vs estimate $8,256,774
$563,011Left on the table8.1% gap to the second bid
6BiddersSpread 43% low to high
171Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | HJC FARMS, INC. | $6,922,966 | -16.2% | $563,011 | 0 | 1-$82,850 | |
| 2 | GILVIN-TERRILL, LTD. | $7,485,977 | +8.1% | -9.3% | $397,087 | 3+$516,870 | 0 |
| 3 | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC | $7,883,063 | +13.9% | -4.5% | $351,352 | 4+$457,394 | 0 |
| 4 | GRATIOT CONSTRUCTION, LTD. | $8,234,416 | +18.9% | -0.3% | $1,067,444 | 3+$709,170 | 2-$100,374 |
| 5 | TI-ZACK CONCRETE, LLC | $9,301,859 | +34.4% | 12.7% | $621,962 | 6+$1,129,345 | 0 |
| 6 | ROADWAY SPECIALTIES, INC. | $9,923,822 | +43.3% | 20.2% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
HJC FARMS, INC. vs GILVIN-TERRILL, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $400,000.00 | $700,000.00 | $523,850.32 | $300,000 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 18,510 CY | $19.75 | $35.00 | $12.93 | $282,278 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 10 MO | $3,300.00 | $20,000.00 | $11,585.04 | $167,000 |
| 543-7002 CABLE BARRIER SYSTEM (INSTALL)(TL-4) | 57,253 LF | $12.50 | $10.50 | $12.40 | -$114,506 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 4,546 CY | $457.00 | $475.00 | $616.83 | $81,828 |
| 344-7057 SP MIXES SP-D SAC-A PG70-28 | 3,066 TON | $200.00 | $175.00 | $121.94 | -$76,650 |
| 247-7133 FL BS (CMP IN PLC)(TY A OR B GR 4)(12") | 8,906 SY | $48.00 | $40.00 | $33.10 | -$71,248 |
| 618-7054 CONDT (PVC) (SCH 80) (2") | 10,089 LF | $19.00 | $12.00 | $12.03 | -$70,623 |
| 505-7001 TMA (STATIONARY) | 293 DAY | $150.00 | $375.00 | $217.57 | $65,925 |
| 543-7018 CABLE BARRIER TERM SEC (INSTL)(TL-4) | 38 EA | $4,200.00 | $2,500.00 | $2,822.11 | -$64,600 |
| 314-7011 EMULS ASPH (EROSN CONT)(CSS-1H) | 55,660 GAL | $5.15 | $4.10 | $3.76 | -$58,443 |
| 110-7001 EXCAV (ROADWAY) | 2,402 CY | $17.00 | $35.00 | $11.68 | $43,236 |
| 624-7014 INSTL GROUND BOX (W/SECURE LID) | 52 EA | $1,700.00 | $2,500.00 | $2,115.04 | $41,600 |
| 416-7040 DRILL SHAFT (RDWY ILL POLE) (30 IN) | 360 LF | $365.00 | $250.00 | $270.84 | -$41,400 |
| 105-7038 RMV (18") TRT/UNTRT BASE & ASPH PAV | 4,692 SY | $13.75 | $20.00 | $8.86 | $29,325 |
| 104-7041 REMOV CONC (FLUME) | 2,223 SY | $16.00 | $27.00 | $18.83 | $24,453 |
| 514-7001 PERM CTB (SGL SLOPE) (TY 1) (42 ) | 2,272 LF | $100.00 | $110.00 | $86.62 | $22,720 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $7,500.00 | $18,500.00 | $9,253.78 | $22,000 |
| 150-7002 BLADING | 300 HR | $75.00 | $145.00 | $171.50 | $21,000 |
| 506-7037 SANDBAGS FOR EROSION CONTROL (8") | 1,000 LF | $20.00 | $5.00 | $21.48 | -$15,000 |
Positive: the low bidder was cheaper on that item. These 20 items account for $588,895 of the $563,011 gap.
HJC FARMS, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 10 MO | $3,300.00 | $11,585.04 | 0.28x | -$82,850 |
GILVIN-TERRILL, LTD.: unbalanced items
Placed 2HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 10 MO | $33,124.78 | $11,585.04 | 2.86x | $215,397 |
| 354-7051 PLANE ASPH CONC PAV(2") | 3,190 SY | $42.75 | $1.86 | 23.02x | $130,449 |
| 164-7058 STRAW/HAY MLCH SEED(PERM_RURAL_CLAY) | 46 AC | $3,009.00 | $1,450.00 | 2.08x | $71,714 |
| 105-7038 RMV (18") TRT/UNTRT BASE & ASPH PAV | 4,692 SY | $17.35 | $8.86 | 1.96x | $39,834 |
GRATIOT CONSTRUCTION, LTD.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 132-7004 EMBANK (FNL)(DC)(TY B) | 18,510 CY | $33.00 | $12.93 | 2.55x | $371,573 |
| 344-7057 SP MIXES SP-D SAC-A PG70-28 | 3,066 TON | $215.00 | $121.94 | 1.76x | $285,329 |
| 105-7038 RMV (18") TRT/UNTRT BASE & ASPH PAV | 4,692 SY | $20.00 | $8.86 | 2.26x | $52,267 |
| 505-7001 TMA (STATIONARY) | 293 DAY | $25.00 | $217.57 | 0.11x | -$56,424 |
| 150-7002 BLADING | 300 HR | $25.00 | $171.50 | 0.15x | -$43,950 |
TI-ZACK CONCRETE, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 344-7057 SP MIXES SP-D SAC-A PG70-28 | 3,066 TON | $228.00 | $121.94 | 1.87x | $325,187 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 18,510 CY | $27.25 | $12.93 | 2.11x | $265,085 |
| 514-7001 PERM CTB (SGL SLOPE) (TY 1) (42 ) | 2,272 LF | $198.00 | $86.62 | 2.29x | $253,055 |
| 105-7038 RMV (18") TRT/UNTRT BASE & ASPH PAV | 4,692 SY | $30.00 | $8.86 | 3.39x | $99,187 |
| 618-7054 CONDT (PVC) (SCH 80) (2") | 10,089 LF | $21.60 | $12.03 | 1.79x | $96,515 |
| 110-7001 EXCAV (ROADWAY) | 2,402 CY | $49.28 | $11.68 | 4.22x | $90,315 |