‹ All Win Price jobs Job page Bid Day Forecast

Routine Maintenance Project - Sealed

Unofficial

CCSJ 6509-62-001 · lets Thursday, Dec 10, 2026 · Val Verde, Laredo · US0090

$635,402Predicted low bid-6.6% vs the engineer's estimate of $680,095
$557,766 – $705,805Likely rangeThe low bid lands here about half the time. 8 in 10: $472,628 to $796,360
1.8Expected bidders3 plan holders so far
MediumConfidenceBacked by 927 closely comparable lettings (2,753 in all)

Where the low bid should land

$472,628: 1 in 10 low bids go lower$796,360: 1 in 10 go higher

What it takes to be lowest

Bid undervs estimateChance you are lowest
$472,628-30.5% 90%
$557,766-18.0% 75%
$635,402-6.6% 50%
$705,805+3.8% 25%
$796,360+17.1% 10%

Chance that no other bid comes in under yours, from how low bids on jobs like this one landed, corrected by how our past predictions actually turned out.

Check my estimate

Add your priced items for a line-by-line check

With items and no total, your total is the sum of the items.

Your numbers are used for this check only and are not saved.

The field: who is likely to bid

Plan holders, last 3 years of Texas bids
Plan holderChance they bidBidsWinsAvg bid vs est.Their typical bid here
T&L CLEANING SERVICES LLCBidders 60% 10529 4.7% $712,342
LUCANIA CONTRACTORS LLCBidders 60% 4612 12.8% $767,393
ROSS SA ENTERPRISE LLCBidders 60% 9840 -19.4% $548,180

Chance they bid comes from how often each company bids prime contracts and, where we can see it, how many of the plan sets they took turned into bids. Plan holders with no bids are usually suppliers and subs.

Lettings most like this one

The closest of the jobs behind this prediction
LetCCSJWhereWorkBiddersEstimateLow bidLow bidder
Jun 20266499-00-001 WebbLaredoRoutine Maintenance Project - Sealed1 $789,624$885,125+12.1% RK POWER DRIVE SERVICES, INC.
May 20266498-99-001 La SalleLaredoRoutine Maintenance Project - Sealed1 $531,343$632,346+19.0% R&M INCORPORATED
Jun 20266499-01-001 WebbLaredoRoutine Maintenance Project - Sealed3 $597,459$623,184+4.3% CRACKSEAL OF TEXAS, LLC
Nov 20256492-75-001 DuvalLaredoRoutine Maintenance Project - Sealed2 $478,179$569,033+19.0% R&M INCORPORATED
Oct 20266506-34-001 DuvalLaredoMaterial Maintenance Project - Sealed1 $577,160$534,600-7.4% ERGON ASPHALT & EMULSIONS, INC.
Apr 20266498-98-001 DuvalLaredoMaterial Maintenance Project - Sealed2 $800,000$903,920+13.0% VULCAN CONSTRUCTION MATERIALS, LLC
Jun 20266500-57-001 MaverickLaredoRoutine Maintenance Project - Sealed3 $439,480$460,615+4.8% R&M INCORPORATED
Nov 20256492-99-001 Val VerdeLaredoRoutine Maintenance Project - Sealed3 $558,680$528,285-5.4% ABESCAPE GROUP LLC
Feb 20256477-87-001 WebbLaredoRoutine Maintenance Project - Sealed2 $822,872$746,057-9.3% R&M INCORPORATED
Oct 20266506-54-001 TarrantFort WorthRoutine Maintenance Project - Sealed2 $640,890$439,494-31.4% TRP INFRASTRUCTURE SERVICES, LLC

How it works: Win Price weighs every Texas letting of the last 3 years by how much it is like this job (size, district, type of work, how recent, and the size of the field) and reads where their low bids landed against the estimate. See the accuracy test. A prediction, not a promise: always price the job yourself.