‹ All Win Price jobs Job page Bid Day Forecast
Intersection & Operational Imprv
OfficialCCSJ 2850-01-020 · lets Wednesday, Dec 2, 2026 · Walker, Bryan · FM 2821 · Construct TWLTL
Where the low bid should land
What it takes to be lowest
| Bid under | vs estimate | Chance you are lowest |
|---|---|---|
| $1,185,905 | -33.9% | 90% |
| $1,368,331 | -23.7% | 75% |
| $1,560,888 | -12.9% | 50% |
| $1,742,521 | -2.8% | 25% |
| $1,936,434 | +8.0% | 10% |
Chance that no other bid comes in under yours, from how low bids on jobs like this one landed, corrected by how our past predictions actually turned out.
The field: who is likely to bid
Plan holders, last 3 years of Texas bids| Plan holder | Chance they bid | Bids | Wins | Avg bid vs est. | Their typical bid here |
|---|---|---|---|---|---|
| FORDE CONSTRUCTION COMPANY, INC.Bidders | 60% | 82 | 10 | 18.5% | $2,125,364 |
| BIG CREEK CONSTRUCTION, LTD.Bidders | 60% | 239 | 106 | -4.9% | $1,705,498 |
| A. L. HELMCAMP, INC.Bidders | 60% | 210 | 38 | 8.8% | $1,951,735 |
| LARRY YOUNG PAVING, INC.Bidders | 60% | 58 | 15 | 5.2% | $1,887,114 |
| KNIFE RIVER CORPORATION - SOUTHBidders | 60% | 234 | 48 | 2.9% | $1,845,292 |
| DURWOOD GREENE CONSTRUCTION CO.Bidders | 60% | 69 | 25 | 3.0% | $1,846,236 |
| BRAZOS PAVING, INC.Bidders | 60% | 54 | 5 | 8.9% | $1,952,778 |
| TEXAS MATERIALS GROUP, INC.Bidders | 60% | 710 | 181 | 3.6% | $1,858,351 |
| Rucoba & Maya Construction, LLCBidders | 45% | 9 | 3 | 14.3% | $2,049,643 |
Chance they bid comes from how often each company bids prime contracts and, where we can see it, how many of the plan sets they took turned into bids. Plan holders with no bids are usually suppliers and subs.
Lettings most like this one
The closest of the jobs behind this prediction| Let | CCSJ | Where | Work | Bidders | Estimate | Low bid | Low bidder |
|---|---|---|---|---|---|---|---|
| Jul 2026 | 6503-24-001 | WashingtonBryan | Routine Maintenance Project - Sealed | 5 | $1,239,700 | $1,091,717-11.9% | BRAZOS PAVING, INC. |
| May 2026 | 0110-01-052 | WalkerBryan | Safety Improvement Projects | 5 | $2,628,065 | $2,980,129+13.4% | BIG CREEK CONSTRUCTION, LTD. |
| Feb 2026 | 0057-05-033 | FreestoneBryan | Safety Improvement Projects | 5 | $1,370,336 | $1,716,130+25.2% | BIG CREEK CONSTRUCTION, LTD. |
| May 2026 | 6488-81-001 | RobertsonBryan | Routine Maintenance Project - Sealed | 5 | $2,801,463 | $2,266,508-19.1% | LONE STAR PAVING COMPANY |
| Jul 2026 | 6503-27-001 | WalkerBryan | Routine Maintenance Project - Sealed | 4 | $1,620,840 | $1,433,238-11.6% | BIG CREEK CONSTRUCTION, LTD. |
| Jul 2026 | 0057-03-052 | FreestoneBryan | Traffic Control Devices | 7 | $1,664,116 | $1,300,246-21.9% | L&L COMPANY |
| Aug 2026 | 6503-26-001 | BrazosBryan | Routine Maintenance Project - Sealed | 4 | $1,123,615 | $987,331-12.1% | BIG CREEK CONSTRUCTION, LTD. |
| Sep 2025 | 0187-01-047 | WashingtonBryan | Pedestrian, Sidewalks & Curb Ramps | 6 | $2,187,752 | $2,318,046+6.0% | JFO SERVICES, LLC |
| Sep 2026 | 0549-02-038 | FanninParis | Intersection & Operational Imprv | 4 | $1,829,363 | $1,979,905+8.2% | HIGHWAY 19 CONSTRUCTION LLC |
| May 2025 | 6483-01-001 | WalkerBryan | Routine Maintenance Project - Sealed | 5 | $1,311,700 | $1,349,975+2.9% | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. |
How it works: Win Price weighs every Texas letting of the last 3 years by how much it is like this job (size, district, type of work, how recent, and the size of the field) and reads where their low bids landed against the estimate. See the accuracy test. A prediction, not a promise: always price the job yourself.