FY26 - Huntsville AO Spot Mill
6483-01-001 · let May 2, 2025 · Walker, Bryan · Routine Maintenance Project - Sealed
$1,349,975Low bid: CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.+2.9% vs estimate $1,311,700
$38,175Left on the table2.8% gap to the second bid
5BiddersSpread 24% low to high
7Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | $1,349,975 | 2.9% | $38,175 | 0 | 1-$14,411 | |
| 2 | ELITE KINGS CONSTRUCTION, LLC | $1,388,150 | +2.8% | 5.8% | $145,725 | 2+$58,446 | 0 |
| 3 | BIG CREEK CONSTRUCTION, LTD. | $1,533,875 | +13.6% | 16.9% | $4,910 | 1+$25,885 | 0 |
| 4 | KNIFE RIVER CORPORATION - SOUTH | $1,538,785 | +14.0% | 17.3% | $137,434 | 0 | 1-$16,561 |
| 5 | TEXAS MATERIALS GROUP, INC. | $1,676,219 | +24.2% | 27.8% | 1+$38,798 | 1-$18,281 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. vs ELITE KINGS CONSTRUCTION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 344-7020 SP MIXES SP-C SAC-A PG70-22 | 6,875 TON | $178.00 | $158.00 | $137.95 | -$137,500 |
| 354-7082 PLANE ASPH CONC PAV (2.5") | 50,000 SY | $2.00 | $4.00 | $2.67 | $100,000 |
| 500-7002 MOBILIZATION (CALLOUT) | 2 EA | $500.00 | $25,000.00 | $600.85 | $49,000 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 86 DAY | $50.00 | $200.00 | $87.82 | $12,900 |
| 505-7001 TMA (STATIONARY) | 86 DAY | $50.00 | $200.00 | $217.57 | $12,900 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 2,000 EA | $1.00 | $2.00 | $0.5715 | $2,000 |
| 344-7077 TACK COAT | 4,500 GAL | $3.25 | $3.00 | $3.25 | -$1,125 |
Positive: the low bidder was cheaper on that item. These 7 items account for $38,175 of the $38,175 gap.
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 86 DAY | $50.00 | $217.57 | 0.23x | -$14,411 |
ELITE KINGS CONSTRUCTION, LLC: unbalanced items
Placed 2BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 344-7077 TACK COAT | 4,500 GAL | $9.00 | $3.25 | 2.77x | $25,885 |
KNIFE RIVER CORPORATION - SOUTH: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 86 DAY | $25.00 | $217.57 | 0.11x | -$16,561 |