FY26 - Huntsville AO Spot Mill
- Let date
- Friday, May 2, 2025
- CCSJ
- 6483-01-001
- District
- Bryan
- County
- Walker
- Highway
- IH0045
- Limits
- Various to Various
- Classification
- Routine Maintenance Project - Sealed · Maintenance
- Project number
- RMC - A00214914
- Working days
- 365
- DBE goal
- 0%
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,311,700 | ||
| 1 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. Low bidder | $1,349,975 | +2.9% | |
| 2 | ELITE KINGS CONSTRUCTION, LLC | $1,388,150 | +5.8% | +2.8% |
| 3 | BIG CREEK CONSTRUCTION, LTD. | $1,533,875 | +16.9% | +13.6% |
| 4 | KNIFE RIVER CORPORATION - SOUTH | $1,538,785 | +17.3% | +14.0% |
| 5 | TEXAS MATERIALS GROUP, INC. | $1,676,219 | +27.8% | +24.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 CORNERSTONE PAV… | #2 ELITE KINGS CON… | #3 BIG CREEK CONST… | #4 KNIFE RIVER COR… | #5 TEXAS MATERIALS… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 344-7020 | SP MIXES SP-C SAC-A PG70-22 | 6,875 | TON | $160.00 | $178.00 | $158.00 | $185.00 | $193.00 | $211.00 |
| 2 | 344-7077 | TACK COAT | 4,500 | GAL | $4.00 | $3.25 | $3.00 | $9.00 | $4.00 | $5.00 |
| 3 | 354-7082 | PLANE ASPH CONC PAV (2.5") | 50,000 | SY | $3.00 | $2.00 | $4.00 | $3.50 | $3.50 | $3.00 |
| 4 | 500-7002 | MOBILIZATION (CALLOUT) | 2 | EA | $1,000.00 | $500.00 | $25,000.00 | $250.00 | $3,800.00 | $20,000.00 |
| 5 | 503-7001 | PORTABLE CHANGEABLE MESSAGE SIGN | 86 | DAY | $100.00 | $50.00 | $200.00 | $150.00 | $60.00 | $124.00 |
| 6 | 505-7001 | TMA (STATIONARY) | 86 | DAY | $350.00 | $50.00 | $200.00 | $350.00 | $25.00 | $5.00 |
| 7 | 662-7114 | WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 2,000 | EA | $1.50 | $1.00 | $2.00 | $1.50 | $2.00 | $1.00 |