FY26 - Calvert Mill & Inlay
6488-81-001 · let May 7, 2026 · Robertson, Bryan · Routine Maintenance Project - Sealed
$2,266,508Low bid: LONE STAR PAVING COMPANY-19.1% vs estimate $2,801,463
$20,846Left on the table0.9% gap to the second bid
5BiddersSpread 35% low to high
23Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | LONE STAR PAVING COMPANY | $2,266,508 | -19.1% | $20,846 | 0 | 2-$530,020 | |
| 2 | BIG CREEK CONSTRUCTION, LTD. | $2,287,353 | +0.9% | -18.4% | $26,986 | 0 | 2-$511,020 |
| 3 | KNIFE RIVER CORPORATION - SOUTH | $2,314,339 | +2.1% | -17.4% | $477,085 | 0 | 2-$501,405 |
| 4 | TEXAS MATERIALS GROUP, INC. | $2,791,424 | +23.2% | -0.4% | $279,391 | 0 | 2-$467,020 |
| 5 | BRAZOS PAVING, INC. | $3,070,815 | +35.5% | 9.6% | 0 | 1-$305,450 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
LONE STAR PAVING COMPANY vs BIG CREEK CONSTRUCTION, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 346-7009 STONE-MTRX-ASPH SMA-D SAC-A PG76-22 | 12,892 TON | $149.00 | $145.00 | $152.44 | -$51,568 |
| 354-7002 PLANE & TEXT ASPH CONC PAV(0" TO 2") | 117,121 SY | $1.15 | $1.50 | $2.24 | $40,992 |
| 500-7001 MOBILIZATION | 1 LS | $13,000.00 | $26,000.00 | $523,850.32 | $13,000 |
| 3007-7001 BONDING COURSE | 11,720 GAL | $3.15 | $4.00 | $3.32 | $9,962 |
| 134-7004 BACKFILL (TY A OR B) | 239 STA | $288.00 | $250.00 | $211.21 | -$9,082 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $2,000.00 | $5,000.00 | $11,585.04 | $6,000 |
| 438-7004 CLEANING AND SEALING EXIST JOINTS (CL3) | 220 LF | $42.00 | $55.00 | $19.19 | $2,860 |
| 505-7003 TMA (MOBILE OPERATION) | 10 DAY | $275.00 | $550.00 | $229.60 | $2,750 |
| 662-7012 WK ZN PAV MRK NON-REMOV (W)8"(SLD) | 3,825 LF | $0.4000 | $0.7500 | $0.6092 | $1,339 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 24,290 LF | $0.5600 | $0.6000 | $0.4757 | $972 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 23,581 LF | $0.5600 | $0.6000 | $0.4986 | $943 |
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR) | 46,847 LF | $0.2700 | $0.2500 | $0.2040 | -$937 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 34 DAY | $100.00 | $125.00 | $87.82 | $850 |
| 662-7008 WK ZN PAV MRK NON-REMOV (W)6"(SLD) | 5,508 LF | $0.4000 | $0.5500 | $0.2750 | $826 |
| 505-7001 TMA (STATIONARY) | 29 DAY | $275.00 | $300.00 | $217.57 | $725 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 1,828 EA | $1.25 | $1.50 | $1.03 | $457 |
| 666-7024 REFL PAV MRK TY I (W)8"(SLD)(100MIL) | 3,825 LF | $0.9000 | $1.00 | $0.9489 | $383 |
| 666-7408 REFL PAV MRK TY I (W)6"(BRK)(100MIL) | 6,170 LF | $0.6500 | $0.6000 | $0.5627 | -$309 |
| 672-7006 REFL PAV MRKR TY II-C-R | 304 EA | $4.00 | $5.00 | $4.19 | $304 |
| 662-7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) | 5,328 LF | $0.5000 | $0.5500 | $0.2770 | $266 |
Positive: the low bidder was cheaper on that item. These 20 items account for $20,734 of the $20,846 gap.
LONE STAR PAVING COMPANY: unbalanced items
Placed 1BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 2KNIFE RIVER CORPORATION - SOUTH: unbalanced items
Placed 3TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 4BRAZOS PAVING, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $218,400.00 | $523,850.32 | 0.42x | -$305,450 |