FY27 - Bryan AO Mill & Inlay - 08
6503-26-001 · let Aug 6, 2026 · Brazos, Bryan · Routine Maintenance Project - Sealed
$987,331Low bid: BIG CREEK CONSTRUCTION, LTD.-12.1% vs estimate $1,123,615
$4,470Left on the table0.5% gap to the second bid
4BiddersSpread 13% low to high
8Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BIG CREEK CONSTRUCTION, LTD. | $987,331 | -12.1% | $4,470 | 0 | 1-$10,400 | |
| 2 | BRAZOS PAVING, INC. | $991,801 | +0.5% | -11.7% | $34,486 | 1+$21,918 | 0 |
| 3 | KNIFE RIVER CORPORATION - SOUTH | $1,026,287 | +3.9% | -8.7% | $92,843 | 1+$6,798 | 1-$11,390 |
| 4 | TEXAS MATERIALS GROUP, INC. | $1,119,130 | +13.3% | -0.4% | 1+$88,750 | 1-$14,294 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
BIG CREEK CONSTRUCTION, LTD. vs BRAZOS PAVING, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 354-7082 PLANE ASPH CONC PAV (2.5") | 38,100 SY | $3.00 | $1.75 | $2.67 | -$47,625 |
| 344-7020 SP MIXES SP-C SAC-A PG70-22 | 5,239 TON | $160.00 | $164.60 | $137.95 | $24,099 |
| 500-7002 MOBILIZATION (CALLOUT) | 2 EA | $500.00 | $11,560.00 | $600.85 | $22,120 |
| 505-7001 TMA (STATIONARY) | 66 DAY | $60.00 | $225.00 | $217.57 | $10,890 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 66 DAY | $150.00 | $100.00 | $87.82 | -$3,300 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 1,500 EA | $1.50 | $1.10 | $1.03 | -$600 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 1,500 EA | $1.50 | $1.10 | $0.5715 | -$600 |
| 344-7077 TACK COAT | 3,429 GAL | $4.50 | $4.35 | $3.25 | -$514 |
Positive: the low bidder was cheaper on that item. These 8 items account for $4,470 of the $4,470 gap.
BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 66 DAY | $60.00 | $217.57 | 0.28x | -$10,400 |
BRAZOS PAVING, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 2 EA | $11,560.00 | $600.85 | 19.24x | $21,918 |