Bid Tab X-ray: 6503-27-001

Jul 2, 2026 · Walker Sign up free
Set your company to personalize scores

FY26 - Huntsville AO Mill & Inlay - 07

6503-27-001 · let Jul 2, 2026 · Walker, Bryan · Routine Maintenance Project - Sealed

$1,433,238Low bid: BIG CREEK CONSTRUCTION, LTD.-11.6% vs estimate $1,620,840
$141,534Left on the table9.9% gap to the second bid
4BiddersSpread 47% low to high
8Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1BIG CREEK CONSTRUCTION, LTD. $1,433,238-11.6% $141,534 0 1-$17,819
2KNIFE RIVER CORPORATION - SOUTH $1,574,771+9.9%-2.8% $12,204 1+$68,398 1-$14,019
3CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. $1,586,975+10.7%-2.1% $519,757 0 0
4HAYDEN PAVING, INC. $2,106,732+47.0%30.0% 1+$14,798 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.

Where the job was won

BIG CREEK CONSTRUCTION, LTD. vs KNIFE RIVER CORPORATION - SOUTH, biggest item swings
ItemQtyLow2ndMarket2nd minus low
344-7020 SP MIXES SP-C SAC-A PG70-227,563 TON $162.50$172.00$137.95 $71,849
500-7002 MOBILIZATION (CALLOUT)2 EA $500.00$34,800.00$600.85 $68,600
354-7082 PLANE ASPH CONC PAV (2.5")55,000 SY $3.00$3.10$2.67 $5,500
503-7001 PORTABLE CHANGEABLE MESSAGE SIGN95 DAY $75.00$20.00$87.82 -$5,225
505-7001 TMA (STATIONARY)95 DAY $30.00$70.00$217.57 $3,800
662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W2,000 EA $1.50$1.00$1.03 -$1,000
662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-22,000 EA $1.50$1.00$0.5715 -$1,000
344-7077 TACK COAT4,950 GAL $4.50$4.30$3.25 -$990

Positive: the low bidder was cheaper on that item. These 8 items account for $141,534 of the $141,534 gap.

BIG CREEK CONSTRUCTION, LTD.: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
505-7001 TMA (STATIONARY)95 DAY $30.00$217.570.14x-$17,819

KNIFE RIVER CORPORATION - SOUTH: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
500-7002 MOBILIZATION (CALLOUT)2 EA $34,800.00$600.8557.92x$68,398
505-7001 TMA (STATIONARY)95 DAY $70.00$217.570.32x-$14,019

HAYDEN PAVING, INC.: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
500-7002 MOBILIZATION (CALLOUT)2 EA $8,000.00$600.8513.31x$14,798