FY26 - Huntsville AO Mill & Inlay - 07
6503-27-001 · let Jul 2, 2026 · Walker, Bryan · Routine Maintenance Project - Sealed
$1,433,238Low bid: BIG CREEK CONSTRUCTION, LTD.-11.6% vs estimate $1,620,840
$141,534Left on the table9.9% gap to the second bid
4BiddersSpread 47% low to high
8Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BIG CREEK CONSTRUCTION, LTD. | $1,433,238 | -11.6% | $141,534 | 0 | 1-$17,819 | |
| 2 | KNIFE RIVER CORPORATION - SOUTH | $1,574,771 | +9.9% | -2.8% | $12,204 | 1+$68,398 | 1-$14,019 |
| 3 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | $1,586,975 | +10.7% | -2.1% | $519,757 | 0 | 0 |
| 4 | HAYDEN PAVING, INC. | $2,106,732 | +47.0% | 30.0% | 1+$14,798 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
BIG CREEK CONSTRUCTION, LTD. vs KNIFE RIVER CORPORATION - SOUTH, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 344-7020 SP MIXES SP-C SAC-A PG70-22 | 7,563 TON | $162.50 | $172.00 | $137.95 | $71,849 |
| 500-7002 MOBILIZATION (CALLOUT) | 2 EA | $500.00 | $34,800.00 | $600.85 | $68,600 |
| 354-7082 PLANE ASPH CONC PAV (2.5") | 55,000 SY | $3.00 | $3.10 | $2.67 | $5,500 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 95 DAY | $75.00 | $20.00 | $87.82 | -$5,225 |
| 505-7001 TMA (STATIONARY) | 95 DAY | $30.00 | $70.00 | $217.57 | $3,800 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 2,000 EA | $1.50 | $1.00 | $1.03 | -$1,000 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 2,000 EA | $1.50 | $1.00 | $0.5715 | -$1,000 |
| 344-7077 TACK COAT | 4,950 GAL | $4.50 | $4.30 | $3.25 | -$990 |
Positive: the low bidder was cheaper on that item. These 8 items account for $141,534 of the $141,534 gap.
BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 95 DAY | $30.00 | $217.57 | 0.14x | -$17,819 |
KNIFE RIVER CORPORATION - SOUTH: unbalanced items
Placed 2HAYDEN PAVING, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 2 EA | $8,000.00 | $600.85 | 13.31x | $14,798 |