US 84 at FM 489 - Turn Lanes FY 26
0057-05-033 · let Feb 5, 2026 · Freestone, Bryan · Safety Improvement Projects
$1,716,130Low bid: BIG CREEK CONSTRUCTION, LTD.+25.2% vs estimate $1,370,336
$81,912Left on the table4.8% gap to the second bid
5BiddersSpread 40% low to high
78Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BIG CREEK CONSTRUCTION, LTD. | $1,716,130 | 25.2% | $81,912 | 6+$107,496 | 3-$577,108 | |
| 2 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | $1,798,042 | +4.8% | 31.2% | $9,540 | 4+$142,462 | 4-$693,601 |
| 3 | KNIFE RIVER CORPORATION - SOUTH | $1,807,582 | +5.3% | 31.9% | $34,470 | 4+$89,316 | 5-$663,046 |
| 4 | TEXAS MATERIALS GROUP, INC. | $1,842,052 | +7.3% | 34.4% | $554,434 | 5+$130,144 | 6-$699,317 |
| 5 | A. L. HELMCAMP, INC. | $2,396,486 | +39.6% | 74.9% | 6+$294,104 | 3-$491,828 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
BIG CREEK CONSTRUCTION, LTD. vs CORNERSTONE PAVING AND CONSTRUCTION, L.L.C., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $170,000.00 | $80,000.00 | $523,850.32 | -$90,000 |
| 344-7020 SP MIXES SP-C SAC-A PG70-22 | 2,596 TON | $110.00 | $134.00 | $137.95 | $62,304 |
| 344-7041 SP MIXES SP-D PG64-22 | 1,805 TON | $110.00 | $140.16 | $134.97 | $54,439 |
| 344-7001 SP MIXES SP-B PG64-22 | 1,197 TON | $100.00 | $124.00 | $124.45 | $28,728 |
| 112-7001 SUBGR WIDEN (OC) | 31.56 STA | $1,000.00 | $1,840.00 | $458.34 | $26,510 |
| 247-7067 FL BS (CMP IN PLC)(TY A GR 1-2) (8") | 5,932 SY | $16.00 | $20.03 | $21.46 | $23,906 |
| 529-7011 CONCRETE GUTTER (MODIFIED) | 380 LF | $65.00 | $125.00 | $26.89 | $22,800 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $7,500.00 | $12,000.00 | $9,253.78 | $18,000 |
| 530-7002 INTERSECTIONS (ACP) | 733 SY | $35.00 | $58.00 | $50.74 | $16,859 |
| 100-7002 PREPARING ROW | 33.56 STA | $1,000.00 | $510.00 | $6,072.92 | -$16,444 |
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 26 EA | $1,500.00 | $950.00 | $1,176.76 | -$14,300 |
| 505-7001 TMA (STATIONARY) | 81 DAY | $250.00 | $75.00 | $217.57 | -$14,175 |
| 464-7003 RC PIPE (CL III)(18 IN) | 362 LF | $100.00 | $62.00 | $83.08 | -$13,756 |
| 530-7010 DRIVEWAYS (ACP) | 1,022 SY | $35.00 | $48.00 | $54.96 | $13,286 |
| 466-7188 WINGWALL (PW - 2) (HW=4 FT) | 2 EA | $15,000.00 | $8,500.00 | $14,120.48 | -$13,000 |
| 354-7033 PLANE ASPH CONC PAV(0" TO 3") | 16,407 SY | $3.00 | $2.25 | $3.11 | -$12,305 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 2,384 CY | $33.00 | $38.00 | $18.71 | $11,920 |
| 662-7035 WK ZN PAV MRK NON-REMOV (Y)4"(SLD) | 28,342 LF | $0.8500 | $0.4500 | $0.4002 | -$11,337 |
| 496-7007 REMOV STR (PIPE) | 431 LF | $20.00 | $40.00 | $23.96 | $8,620 |
| 496-7004 REMOV STR (SET) | 28 EA | $500.00 | $750.00 | $514.07 | $7,000 |
Positive: the low bidder was cheaper on that item. These 20 items account for $109,055 of the $81,912 gap.
BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 132-7005 EMBANK (FNL)(OC)(TY C) | 2,384 CY | $33.00 | $18.71 | 1.76x | $34,060 |
| 275-7011 CEMENT TRT (NEW BASE)(8") | 5,932 SY | $5.00 | $1.92 | 2.60x | $18,263 |
| 112-7001 SUBGR WIDEN (OC) | 31.56 STA | $1,000.00 | $458.34 | 2.18x | $17,095 |
| 529-7011 CONCRETE GUTTER (MODIFIED) | 380 LF | $65.00 | $26.89 | 2.42x | $14,483 |
| 662-7035 WK ZN PAV MRK NON-REMOV (Y)4"(SLD) | 28,342 LF | $0.8500 | $0.4002 | 2.12x | $12,748 |
| 134-7004 BACKFILL (TY A OR B) | 37.56 STA | $500.00 | $211.21 | 2.37x | $10,847 |
| 500-7001 MOBILIZATION | 1 LS | $170,000.00 | $523,850.32 | 0.32x | -$353,850 |
| 100-7002 PREPARING ROW | 33.56 STA | $1,000.00 | $6,072.92 | 0.16x | -$170,247 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $2,750.00 | $11,585.04 | 0.24x | -$53,010 |
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 132-7005 EMBANK (FNL)(OC)(TY C) | 2,384 CY | $38.00 | $18.71 | 2.03x | $45,980 |
| 112-7001 SUBGR WIDEN (OC) | 31.56 STA | $1,840.00 | $458.34 | 4.01x | $43,605 |
| 529-7011 CONCRETE GUTTER (MODIFIED) | 380 LF | $125.00 | $26.89 | 4.65x | $37,283 |
| 275-7011 CEMENT TRT (NEW BASE)(8") | 5,932 SY | $4.55 | $1.92 | 2.37x | $15,594 |
| 500-7001 MOBILIZATION | 1 LS | $80,000.00 | $523,850.32 | 0.15x | -$443,850 |
| 100-7002 PREPARING ROW | 33.56 STA | $510.00 | $6,072.92 | 0.08x | -$186,692 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $3,000.00 | $11,585.04 | 0.26x | -$51,510 |
| 505-7001 TMA (STATIONARY) | 81 DAY | $75.00 | $217.57 | 0.34x | -$11,548 |
KNIFE RIVER CORPORATION - SOUTH: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 529-7011 CONCRETE GUTTER (MODIFIED) | 380 LF | $134.00 | $26.89 | 4.98x | $40,703 |
| 505-7001 TMA (STATIONARY) | 81 DAY | $484.00 | $217.57 | 2.22x | $21,581 |
| 134-7004 BACKFILL (TY A OR B) | 37.56 STA | $650.00 | $211.21 | 3.08x | $16,481 |
| 275-7011 CEMENT TRT (NEW BASE)(8") | 5,932 SY | $3.70 | $1.92 | 1.93x | $10,552 |
| 500-7001 MOBILIZATION | 1 LS | $157,445.00 | $523,850.32 | 0.30x | -$366,405 |
| 100-7002 PREPARING ROW | 33.56 STA | $685.00 | $6,072.92 | 0.11x | -$180,819 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $3,315.00 | $11,585.04 | 0.29x | -$49,620 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $525.00 | $9,253.78 | 0.06x | -$34,915 |
| 354-7033 PLANE ASPH CONC PAV(0" TO 3") | 16,407 SY | $1.20 | $3.11 | 0.39x | -$31,287 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 132-7005 EMBANK (FNL)(OC)(TY C) | 2,384 CY | $49.33 | $18.71 | 2.64x | $72,991 |
| 275-7011 CEMENT TRT (NEW BASE)(8") | 5,932 SY | $4.70 | $1.92 | 2.45x | $16,484 |
| 134-7004 BACKFILL (TY A OR B) | 37.56 STA | $625.00 | $211.21 | 2.96x | $15,542 |
| 462-7056 CONC BOX CULV (3 FT X 2 FT)(EXTEND) | 19 LF | $1,289.00 | $588.77 | 2.19x | $13,304 |
| 529-7011 CONCRETE GUTTER (MODIFIED) | 380 LF | $58.00 | $26.89 | 2.16x | $11,823 |
| 500-7001 MOBILIZATION | 1 LS | $108,000.00 | $523,850.32 | 0.21x | -$415,850 |
| 100-7002 PREPARING ROW | 33.56 STA | $1,000.00 | $6,072.92 | 0.16x | -$170,247 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $1,000.00 | $11,585.04 | 0.09x | -$63,510 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $2,165.00 | $9,253.78 | 0.23x | -$28,355 |
| 505-7001 TMA (STATIONARY) | 81 DAY | $80.00 | $217.57 | 0.37x | -$11,143 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 9,920 SY | $0.4000 | $1.43 | 0.28x | -$10,211 |
A. L. HELMCAMP, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 530-7010 DRIVEWAYS (ACP) | 1,022 SY | $160.00 | $54.96 | 2.91x | $107,355 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 2,384 CY | $50.00 | $18.71 | 2.67x | $74,588 |
| 529-7011 CONCRETE GUTTER (MODIFIED) | 380 LF | $137.00 | $26.89 | 5.10x | $41,843 |
| 275-7011 CEMENT TRT (NEW BASE)(8") | 5,932 SY | $7.50 | $1.92 | 3.90x | $33,093 |
| 275-7004 CEMENT TRT (EXIST MATL)(10") | 6,633 SY | $7.50 | $3.71 | 2.02x | $25,163 |
| 105-7032 RMV (12") TRT/UNTRT BASE & ASPH PAV | 322 SY | $45.00 | $7.54 | 5.97x | $12,061 |
| 500-7001 MOBILIZATION | 1 LS | $225,000.00 | $523,850.32 | 0.43x | -$298,850 |
| 100-7002 PREPARING ROW | 33.56 STA | $1,500.00 | $6,072.92 | 0.25x | -$153,467 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $5,000.00 | $11,585.04 | 0.43x | -$39,510 |