FY27 - Brenham AO Mill & Inlay - 07
6503-24-001 · let Jul 1, 2026 · Washington, Bryan · Routine Maintenance Project - Sealed
$1,091,717Low bid: BRAZOS PAVING, INC.-11.9% vs estimate $1,239,700
$43,493Left on the table4.0% gap to the second bid
5BiddersSpread 28% low to high
8Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BRAZOS PAVING, INC. | $1,091,717 | -11.9% | $43,493 | 2+$23,134 | 0 | |
| 2 | BIG CREEK CONSTRUCTION, LTD. | $1,135,210 | +4.0% | -8.4% | $10,165 | 0 | 1-$15,166 |
| 3 | KNIFE RIVER CORPORATION - SOUTH | $1,145,375 | +4.9% | -7.6% | $74,188 | 1+$54,198 | 1-$11,806 |
| 4 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | $1,219,563 | +11.7% | -1.6% | $180,138 | 0 | 0 |
| 5 | TEXAS MATERIALS GROUP, INC. | $1,399,700 | +28.2% | 12.9% | 2+$43,393 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
BRAZOS PAVING, INC. vs BIG CREEK CONSTRUCTION, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 354-7082 PLANE ASPH CONC PAV (2.5") | 42,000 SY | $1.75 | $3.50 | $2.67 | $73,500 |
| 505-7001 TMA (STATIONARY) | 80 DAY | $341.00 | $28.00 | $217.57 | -$25,040 |
| 500-7002 MOBILIZATION (CALLOUT) | 2 EA | $8,000.00 | $500.00 | $600.85 | -$15,000 |
| 344-7020 SP MIXES SP-C SAC-A PG70-22 | 5,775 TON | $162.75 | $165.00 | $137.95 | $12,994 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 73 DAY | $202.00 | $145.00 | $87.82 | -$4,161 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 1,500 EA | $1.10 | $1.50 | $1.03 | $600 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 1,500 EA | $1.10 | $1.50 | $0.5715 | $600 |
| 344-7077 TACK COAT | 3,780 GAL | $4.50 | $4.50 | $3.25 | $0 |
Positive: the low bidder was cheaper on that item. These 8 items account for $43,493 of the $43,493 gap.
BRAZOS PAVING, INC.: unbalanced items
Placed 1BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 80 DAY | $28.00 | $217.57 | 0.13x | -$15,166 |