Win Price: 1127-05-024

Ector · lets Dec 2, 2026 Sign up free

‹ All Win Price jobs Job page Bid Day Forecast

Safety Improvement Projects

Official

CCSJ 1127-05-024 · lets Wednesday, Dec 2, 2026 · Ector, Odessa · FM 866 · Hazard Elimination & Safety

$1,857,709Predicted low bid-10.9% vs the engineer's estimate of $2,084,737
$1,667,407 – $2,067,217Likely rangeThe low bid lands here about half the time. 8 in 10: $1,429,593 to $2,314,899
3.0Expected bidders5 plan holders so far
MediumConfidenceBacked by 674 closely comparable lettings (1,928 in all)

Where the low bid should land

$1,429,593: 1 in 10 low bids go lower$2,314,899: 1 in 10 go higher

What it takes to be lowest

Bid undervs estimateChance you are lowest
$1,429,593-31.4% 90%
$1,667,407-20.0% 75%
$1,857,709-10.9% 50%
$2,067,217-0.8% 25%
$2,314,899+11.0% 10%

Chance that no other bid comes in under yours, from how low bids on jobs like this one landed, corrected by how our past predictions actually turned out.

Check my estimate

Add your priced items for a line-by-line check

With items and no total, your total is the sum of the items.

Your numbers are used for this check only and are not saved.

The field: who is likely to bid

Plan holders, last 3 years of Texas bids
Plan holderChance they bidBidsWinsAvg bid vs est.Their typical bid here
REECE ALBERT, INC.Bidders 60% 5310 10.9% $2,312,214
JONES BROS. DIRT & PAVING CONTRACTORS, INC.Bidders 60% 4219 10.2% $2,297,361
DAN WILLIAMS COMPANYBidders 60% 10831 4.1% $2,170,267
A. L. HELMCAMP, INC.Bidders 60% 21038 8.8% $2,269,207
RAGLE CONSTRUCTION, INC.Bidders 60% 25138 13.0% $2,355,642

Chance they bid comes from how often each company bids prime contracts and, where we can see it, how many of the plan sets they took turned into bids. Plan holders with no bids are usually suppliers and subs.

Lettings most like this one

The closest of the jobs behind this prediction
LetCCSJWhereWorkBiddersEstimateLow bidLow bidder
Jul 20250906-06-055 EctorOdessaSafety Improvement Projects3 $2,314,854$1,911,951-17.4% VACA UNDERGROUND UTILITIES INC
Feb 20260103-01-046 ReevesOdessaSafety Improvement Projects4 $1,728,243$1,752,100+1.4% A. L. HELMCAMP, INC.
Nov 20266508-84-001 MidlandOdessaRoutine Maintenance Project - Sealed4 $1,540,045$1,285,507-16.5% RAGLE CONSTRUCTION, INC.
Aug 20261023-01-039 ChambersBeaumontSafety Improvement Projects3 $2,493,248$2,499,687+0.3% HAYDEN PAVING, INC.
May 20260463-07-055 EctorOdessaIntersection & Operational Imprv3 $1,299,947$1,275,100-1.9% RAGLE CONSTRUCTION, INC.
Jul 20260054-06-113 BrownBrownwoodSafety Improvement Projects3 $2,463,639$2,313,829-6.1% GRATIOT CONSTRUCTION, LTD.
Apr 20260269-10-028 LavacaYoakumSafety Improvement Projects3 $2,177,688$2,566,089+17.8% HUNTER INDUSTRIES, LTD.
Nov 20260947-03-034 JasperBeaumontSafety Improvement Projects2 $2,281,773$2,431,741+6.6% TEXAS MATERIALS GROUP, INC.
May 20260167-02-092 El PasoEl PasoSafety Improvement Projects3 $3,003,442$2,479,055-17.5% INTERNATIONAL EAGLE ENTERPRISES, INC.
Dec 20250904-00-228 PotterAmarilloSafety Improvement Projects3 $1,971,041$1,124,670-42.9% STRIPE-A-ZONE, LLC

How it works: Win Price weighs every Texas letting of the last 3 years by how much it is like this job (size, district, type of work, how recent, and the size of the field) and reads where their low bids landed against the estimate. See the accuracy test. A prediction, not a promise: always price the job yourself.