ELP_BU0054A_2-TAR (2022)
0167-02-092 · let May 7, 2026 · El Paso, El Paso · Safety Improvement Projects
$2,479,055Low bid: INTERNATIONAL EAGLE ENTERPRISES, INC.-17.5% vs estimate $3,003,442
$279,945Left on the table11.3% gap to the second bid
3BiddersSpread 34% low to high
219Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | INTERNATIONAL EAGLE ENTERPRISES, INC. | $2,479,055 | -17.5% | $279,945 | 4+$85,893 | 3-$724,648 | |
| 2 | Horizone Construction I, Ltd | $2,759,000 | +11.3% | -8.1% | $560,132 | 5+$141,069 | 1-$435,892 |
| 3 | HAWK CONSTRUCTION | $3,319,132 | +33.9% | 10.5% | 7+$217,272 | 2-$690,382 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
INTERNATIONAL EAGLE ENTERPRISES, INC. vs Horizone Construction I, Ltd, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 45 STA | $280.00 | $3,997.45 | $6,072.92 | $167,285 |
| 530-7006 DRIVEWAYS (CONC) | 4,778 SY | $65.00 | $83.00 | $109.20 | $86,004 |
| 104-7011 REMOV CONC (DRIVEWAYS) | 5,215 SY | $30.00 | $13.96 | $19.70 | -$83,649 |
| 531-7001 CONC SIDEWALKS (4") | 4,894 SY | $45.00 | $62.00 | $70.57 | $83,198 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $18,000.00 | $13,979.32 | $11,585.04 | -$48,248 |
| 6073-7001 REC RAPID FLASH BEACON (2-WAY SOLAR) | 14 EA | $8,800.00 | $10,858.57 | $9,005.00 | $28,820 |
| 104-7046 REMOV CONC (MISC) | 1,494 SY | $35.00 | $17.45 | $23.49 | -$26,220 |
| 505-7001 TMA (STATIONARY) | 267 DAY | $280.00 | $209.34 | $217.57 | -$18,866 |
| 666-7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL) | 3,836 LF | $16.00 | $11.21 | $7.19 | -$18,374 |
| 687-7001 PED POLE ASSEMBLY | 23 EA | $3,500.00 | $4,281.98 | $2,930.76 | $17,986 |
| 6075-7002 INSTALL SOLAR-POWERED DFSSA | 6 EA | $9,600.00 | $11,772.06 | $5,896.82 | $13,032 |
| 500-7001 MOBILIZATION | 1 LS | $75,000.00 | $87,958.79 | $523,850.32 | $12,959 |
| 150-7001 BLADING | 45 STA | $500.00 | $233.16 | $152.64 | -$12,008 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 7,259 LF | $6.50 | $5.04 | $3.92 | -$10,598 |
| 529-7012 CONC CURB (DOWELED) | 830 LF | $18.00 | $30.53 | $18.32 | $10,400 |
| 644-7001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) | 58 EA | $1,200.00 | $1,378.80 | $696.14 | $10,370 |
| 550-7001 CHAIN LINK FENCE (INSTALL) (6') | 121 LF | $80.00 | $163.12 | $42.32 | $10,058 |
| 680-7011 INSTALL HWY TRF SIG (UPGRADE) | 2 EA | $20,000.00 | $24,816.75 | $8,031.16 | $9,634 |
| 688-7001 PED DETECT PUSH BUTTON (APS) | 28 EA | $1,200.00 | $1,474.91 | $1,056.39 | $7,697 |
| 527-7003 COLORED TEXTURED CONC (6") | 558 SY | $85.00 | $97.70 | $127.53 | $7,087 |
Positive: the low bidder was cheaper on that item. These 20 items account for $246,566 of the $279,945 gap.
INTERNATIONAL EAGLE ENTERPRISES, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 666-7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL) | 3,836 LF | $16.00 | $7.19 | 2.23x | $33,807 |
| 680-7011 INSTALL HWY TRF SIG (UPGRADE) | 2 EA | $20,000.00 | $8,031.16 | 2.49x | $23,938 |
| 150-7001 BLADING | 45 STA | $500.00 | $152.64 | 3.28x | $15,631 |
| 618-7036 CONDT (PVC) (SCH 40) (3") | 635 LF | $35.00 | $15.29 | 2.29x | $12,517 |
| 500-7001 MOBILIZATION | 1 LS | $75,000.00 | $523,850.32 | 0.14x | -$448,850 |
| 100-7002 PREPARING ROW | 45 STA | $280.00 | $6,072.92 | 0.05x | -$260,681 |
| 531-7007 CURB RAMPS (TY 3) | 8 EA | $1,500.00 | $3,389.47 | 0.44x | -$15,116 |
Horizone Construction I, Ltd: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 644-7001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) | 58 EA | $1,378.80 | $696.14 | 1.98x | $39,594 |
| 6075-7002 INSTALL SOLAR-POWERED DFSSA | 6 EA | $11,772.06 | $5,896.82 | 2.00x | $35,251 |
| 680-7011 INSTALL HWY TRF SIG (UPGRADE) | 2 EA | $24,816.75 | $8,031.16 | 3.09x | $33,571 |
| 618-7036 CONDT (PVC) (SCH 40) (3") | 635 LF | $43.69 | $15.29 | 2.86x | $18,035 |
| 550-7001 CHAIN LINK FENCE (INSTALL) (6') | 121 LF | $163.12 | $42.32 | 3.85x | $14,616 |
| 500-7001 MOBILIZATION | 1 LS | $87,958.79 | $523,850.32 | 0.17x | -$435,892 |
HAWK CONSTRUCTION: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 529-7002 CONC CURB (TY II) | 913 LF | $72.00 | $26.45 | 2.72x | $41,587 |
| 644-7001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) | 58 EA | $1,370.00 | $696.14 | 1.97x | $39,084 |
| 6075-7002 INSTALL SOLAR-POWERED DFSSA | 6 EA | $11,700.00 | $5,896.82 | 1.98x | $34,819 |
| 680-7011 INSTALL HWY TRF SIG (UPGRADE) | 2 EA | $24,650.00 | $8,031.16 | 3.07x | $33,238 |
| 531-7023 CURB RAMPS (TY 21) | 39 SY | $1,050.00 | $221.36 | 4.74x | $32,317 |
| 618-7036 CONDT (PVC) (SCH 40) (3") | 635 LF | $44.00 | $15.29 | 2.88x | $18,232 |
| 529-7012 CONC CURB (DOWELED) | 830 LF | $40.00 | $18.32 | 2.18x | $17,995 |
| 500-7001 MOBILIZATION | 1 LS | $55,000.00 | $523,850.32 | 0.10x | -$468,850 |
| 100-7002 PREPARING ROW | 45 STA | $1,150.00 | $6,072.92 | 0.19x | -$221,531 |