Win Price: 0917-16-046

Freestone, Leon · lets Dec 2, 2026 Sign up free

‹ All Win Price jobs Job page Bid Day Forecast

Safety Improvement Projects

Official

CCSJ 0917-16-046 · lets Wednesday, Dec 2, 2026 · Freestone, Leon, Bryan · Various

$164,740Predicted low bid-10.9% vs the engineer's estimate of $184,986
$146,173 – $182,004Likely rangeThe low bid lands here about half the time. 8 in 10: $126,725 to $199,635
5.4Expected bidders10 plan holders so far
MediumConfidenceBacked by 664 closely comparable lettings (1,833 in all)

Where the low bid should land

$126,725: 1 in 10 low bids go lower$199,635: 1 in 10 go higher

What it takes to be lowest

Bid undervs estimateChance you are lowest
$126,725-31.5% 90%
$146,173-21.0% 75%
$164,740-10.9% 50%
$182,004-1.6% 25%
$199,635+7.9% 10%

Chance that no other bid comes in under yours, from how low bids on jobs like this one landed, corrected by how our past predictions actually turned out.

Check my estimate

Add your priced items for a line-by-line check

With items and no total, your total is the sum of the items.

Your numbers are used for this check only and are not saved.

The field: who is likely to bid

Plan holders, last 3 years of Texas bids
Plan holderChance they bidBidsWinsAvg bid vs est.Their typical bid here
TRAF-TEX, INC.Bidders 60% 11322 7.6% $199,034
FLORIDA TRAFFIC CONTROL DEVICES, INC.Bidders 60% 1299 14.6% $211,975
THIRD COAST SERVICES LLCBidders 60% 10927 1.6% $187,920
LARRY YOUNG PAVING, INC.Bidders 60% 5815 5.2% $194,688
VACA UNDERGROUND UTILITIES INCBidders 60% 12640 -1.1% $183,027
ROAD SOLUTIONS L.L.C.Bidders 60% 353 11.7% $206,712
STRUCTURAL INTEGRITY GROUP LLCBidders 60% 20422 8.2% $200,195
NEWTON DIVERSIFIED LLCBidders 60% 100 8.4% $200,558
WG ENGINEERING & CONSTRUCTION, LLCBidders 60% 9013 9.2% $202,055
TEXAS PUBLIC WORKS LLCBidders 3% 00

Chance they bid comes from how often each company bids prime contracts and, where we can see it, how many of the plan sets they took turned into bids. Plan holders with no bids are usually suppliers and subs.

Lettings most like this one

The closest of the jobs behind this prediction
LetCCSJWhereWorkBiddersEstimateLow bidLow bidder
Jun 20266502-35-001 BurlesonBryanMaterial Maintenance Project5 $225,600$212,600-5.8% BIG CREEK CONSTRUCTION, LTD.
Jun 20266502-32-001 BrazosBryanRoutine Maintenance Project5 $231,369$244,833+5.8% D & M CONTRACTORS, LLC
Jun 20266502-33-001 FreestoneBryanRoutine Maintenance Project5 $245,888$294,937+19.9% GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
Jun 20266502-49-001 WalkerBryanRoutine Maintenance Project6 $243,600$210,258-13.7% ANTHONY SERVICES
Jul 20266503-91-001 WashingtonBryanMaterial Maintenance Project5 $120,000$115,500-3.8% TOUCHSTONE RESOURCES, LLC
Feb 20266496-33-001 BrazosBryanRoutine Maintenance Project - Sealed5 $264,890$216,800-18.2% PROFESSIONAL TRAFFIC CONTROL LLC
Dec 20256493-43-001 WalkerBryanMaterial Maintenance Project6 $152,000$133,290-12.3% A. L. HELMCAMP, INC.
Jan 20266495-51-001 BrazosBryanRoutine Maintenance Project6 $139,500$111,514-20.1% M&D CONSTRUCTION SERVICES
Jun 20266502-31-001 WashingtonBryanRoutine Maintenance Project4 $153,735$150,270-2.3% D & M CONTRACTORS, LLC
Dec 20256492-80-001 RobertsonBryanRoutine Maintenance Project5 $126,500$94,750-25.1% JACKSON EXCAVATION, LLC

How it works: Win Price weighs every Texas letting of the last 3 years by how much it is like this job (size, district, type of work, how recent, and the size of the field) and reads where their low bids landed against the estimate. See the accuracy test. A prediction, not a promise: always price the job yourself.