FY27 - Bryan AO Crack Seal -06
6502-32-001 · let Jun 10, 2026 · Brazos, Bryan · Routine Maintenance Project
$244,833Low bid: D & M CONTRACTORS, LLC+5.8% vs estimate $231,369
$34,619Left on the table14.1% gap to the second bid
5BiddersSpread 67% low to high
3Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | D & M CONTRACTORS, LLC | $244,833 | 5.8% | $34,619 | 0 | 2-$519,337 | |
| 2 | FYL ENTERPRISES, LLC | $279,452 | +14.1% | 20.8% | $42,933 | 0 | 2-$514,289 |
| 3 | GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY | $322,385 | +31.7% | 39.3% | $60,730 | 0 | 2-$523,765 |
| 4 | ORTEGA'S LAWN AND LANDSCAPING, LLC | $383,115 | +56.5% | 65.6% | $25,764 | 0 | 1-$508,850 |
| 5 | CRACKSEAL OF TEXAS, LLC | $408,879 | +67.0% | 76.7% | 0 | 1-$433,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
D & M CONTRACTORS, LLC vs FYL ENTERPRISES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 712-7001 JT / CRCK SEAL (RUBBER - ASPHALT) | 240.41 LMI | $977.00 | $1,100.00 | $868.20 | $29,570 |
| 500-7001 MOBILIZATION | 1 LS | $9,777.77 | $15,000.00 | $523,850.32 | $5,222 |
| 505-7001 TMA (STATIONARY) | 25 DAY | $7.00 | $0.0400 | $217.57 | -$174 |
Positive: the low bidder was cheaper on that item. These 3 items account for $34,619 of the $34,619 gap.
D & M CONTRACTORS, LLC: unbalanced items
Placed 1FYL ENTERPRISES, LLC: unbalanced items
Placed 2GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY: unbalanced items
Placed 3ORTEGA'S LAWN AND LANDSCAPING, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $15,000.00 | $523,850.32 | 0.03x | -$508,850 |
CRACKSEAL OF TEXAS, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $90,000.00 | $523,850.32 | 0.17x | -$433,850 |