FY26 - Robertson Tree Removal -12
6492-80-001 · let Dec 10, 2025 · Robertson, Bryan · Routine Maintenance Project
$94,750Low bid: JACKSON EXCAVATION, LLC-25.1% vs estimate $126,500
$5,250Left on the table5.5% gap to the second bid
5BiddersSpread 120% low to high
11Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | JACKSON EXCAVATION, LLC | $94,750 | -25.1% | $5,250 | 1+$7,824 | 0 | |
| 2 | M&D CONSTRUCTION SERVICES | $100,000 | +5.5% | -20.9% | $73,000 | 1+$4,197 | 0 |
| 3 | GV LANDSCAPE AND CONSTRUCTION LLC | $173,000 | +82.6% | 36.8% | $14,510 | 2+$69,110 | 0 |
| 4 | JCW CONSTRUCTION, LLC | $187,510 | +97.9% | 48.2% | $20,540 | 8+$93,263 | 0 |
| 5 | ICOS MANAGEMENT, LLC | $208,050 | +119.6% | 64.5% | 8+$105,020 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
JACKSON EXCAVATION, LLC vs M&D CONSTRUCTION SERVICES, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 10 DAY | $1,000.00 | $0.0010 | $217.57 | -$10,000 |
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 300 EA | $100.00 | $70.00 | $60.77 | -$9,000 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 200 EA | $100.00 | $133.33 | $100.44 | $6,666 |
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 100 EA | $150.00 | $186.67 | $141.37 | $3,667 |
| 752-7008 TREE REMOVAL (24" - 30" DIA) | 40 EA | $150.00 | $240.00 | $208.61 | $3,600 |
| 500-7002 MOBILIZATION (CALLOUT) | 3 EA | $1,000.00 | $2,000.00 | $600.85 | $3,000 |
| 752-7012 TREE REMOVAL (48" - 60" DIA) | 10 EA | $250.00 | $480.00 | $450.06 | $2,300 |
| 752-7013 TREE REMOVAL (60" - 72" DIA) | 5 EA | $250.00 | $573.40 | $529.99 | $1,617 |
| 752-7011 TREE REMOVAL (42" - 48" DIA) | 10 EA | $250.00 | $400.00 | $436.67 | $1,500 |
| 752-7010 TREE REMOVAL (36" - 42" DIA) | 10 EA | $250.00 | $346.67 | $334.81 | $967 |
| 752-7009 TREE REMOVAL (30" - 36" DIA) | 10 EA | $200.00 | $293.33 | $293.05 | $933 |
Positive: the low bidder was cheaper on that item. These 11 items account for $5,250 of the $5,250 gap.
JACKSON EXCAVATION, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 10 DAY | $1,000.00 | $217.57 | 4.60x | $7,824 |
M&D CONSTRUCTION SERVICES: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 3 EA | $2,000.00 | $600.85 | 3.33x | $4,197 |
GV LANDSCAPE AND CONSTRUCTION LLC: unbalanced items
Placed 3JCW CONSTRUCTION, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 200 EA | $200.00 | $100.44 | 1.99x | $19,912 |
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 100 EA | $300.00 | $141.37 | 2.12x | $15,863 |
| 752-7011 TREE REMOVAL (42" - 48" DIA) | 10 EA | $2,000.00 | $436.67 | 4.58x | $15,633 |
| 752-7012 TREE REMOVAL (48" - 60" DIA) | 10 EA | $2,000.00 | $450.06 | 4.44x | $15,499 |
| 752-7013 TREE REMOVAL (60" - 72" DIA) | 5 EA | $2,500.00 | $529.99 | 4.72x | $9,850 |
| 752-7008 TREE REMOVAL (24" - 30" DIA) | 40 EA | $400.00 | $208.61 | 1.92x | $7,656 |
| 752-7010 TREE REMOVAL (36" - 42" DIA) | 10 EA | $800.00 | $334.81 | 2.39x | $4,652 |
| 500-7002 MOBILIZATION (CALLOUT) | 3 EA | $2,000.00 | $600.85 | 3.33x | $4,197 |
ICOS MANAGEMENT, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 752-7012 TREE REMOVAL (48" - 60" DIA) | 10 EA | $2,550.00 | $450.06 | 5.67x | $20,999 |
| 752-7013 TREE REMOVAL (60" - 72" DIA) | 5 EA | $3,740.00 | $529.99 | 7.06x | $16,050 |
| 752-7008 TREE REMOVAL (24" - 30" DIA) | 40 EA | $600.00 | $208.61 | 2.88x | $15,656 |
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 100 EA | $285.00 | $141.37 | 2.02x | $14,363 |
| 752-7011 TREE REMOVAL (42" - 48" DIA) | 10 EA | $1,850.00 | $436.67 | 4.24x | $14,133 |
| 752-7010 TREE REMOVAL (36" - 42" DIA) | 10 EA | $1,300.00 | $334.81 | 3.88x | $9,652 |
| 500-7002 MOBILIZATION (CALLOUT) | 3 EA | $3,300.00 | $600.85 | 5.49x | $8,097 |
| 752-7009 TREE REMOVAL (30" - 36" DIA) | 10 EA | $900.00 | $293.05 | 3.07x | $6,070 |