FY26 Huntsville AO Flexbase - 12
6493-43-001 · let Dec 9, 2025 · Walker, Bryan · Material Maintenance Project
$133,290Low bid: A. L. HELMCAMP, INC.-12.3% vs estimate $152,000
$7,710Left on the table5.8% gap to the second bid
6BiddersSpread 54% low to high
4Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | A. L. HELMCAMP, INC. | $133,290 | -12.3% | $7,710 | 0 | 0 | |
| 2 | TOUCHSTONE RESOURCES, LLC | $141,000 | +5.8% | -7.2% | $3,500 | 0 | 0 |
| 3 | SOUTHERN SOURCING SOLUTIONS, LLC | $144,500 | +8.4% | -4.9% | $500 | 0 | 0 |
| 4 | M&D CONSTRUCTION SERVICES | $145,000 | +8.8% | -4.6% | $6,510 | 0 | 0 |
| 5 | GREEN DREAM INTERNATIONAL LLC | $151,510 | +13.7% | -0.3% | $53,590 | 0 | 0 |
| 6 | COLORADO MATERIALS, LTD. | $205,100 | +53.9% | 34.9% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
A. L. HELMCAMP, INC. vs TOUCHSTONE RESOURCES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8010-7024 FL BS(TY A GR 1-2)(DEL)(ST4) | 1,000 TON | $26.48 | $32.00 | $31.87 | $5,520 |
| 8010-7023 FL BS(TY A GR 1-2)(DEL)(ST3) | 1,000 TON | $27.15 | $32.00 | $35.12 | $4,850 |
| 8010-7022 FL BS(TY A GR 1-2)(DEL)(ST2) | 1,000 TON | $37.10 | $33.00 | $42.69 | -$4,100 |
| 8010-7021 FL BS(TY A GR 1-2)(DEL)(ST1) | 1,000 TON | $42.56 | $44.00 | $39.77 | $1,440 |
Positive: the low bidder was cheaper on that item. These 4 items account for $7,710 of the $7,710 gap.