Bid Tab X-ray: 6493-43-001

Dec 9, 2025 · Walker Sign up free
Set your company to personalize scores

FY26 Huntsville AO Flexbase - 12

6493-43-001 · let Dec 9, 2025 · Walker, Bryan · Material Maintenance Project

$133,290Low bid: A. L. HELMCAMP, INC.-12.3% vs estimate $152,000
$7,710Left on the table5.8% gap to the second bid
6BiddersSpread 54% low to high
4Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1A. L. HELMCAMP, INC. $133,290-12.3% $7,710 0 0
2TOUCHSTONE RESOURCES, LLC $141,000+5.8%-7.2% $3,500 0 0
3SOUTHERN SOURCING SOLUTIONS, LLC $144,500+8.4%-4.9% $500 0 0
4M&D CONSTRUCTION SERVICES $145,000+8.8%-4.6% $6,510 0 0
5GREEN DREAM INTERNATIONAL LLC $151,510+13.7%-0.3% $53,590 0 0
6COLORADO MATERIALS, LTD. $205,100+53.9%34.9%

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

A. L. HELMCAMP, INC. vs TOUCHSTONE RESOURCES, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
8010-7024 FL BS(TY A GR 1-2)(DEL)(ST4)1,000 TON $26.48$32.00$31.87 $5,520
8010-7023 FL BS(TY A GR 1-2)(DEL)(ST3)1,000 TON $27.15$32.00$35.12 $4,850
8010-7022 FL BS(TY A GR 1-2)(DEL)(ST2)1,000 TON $37.10$33.00$42.69 -$4,100
8010-7021 FL BS(TY A GR 1-2)(DEL)(ST1)1,000 TON $42.56$44.00$39.77 $1,440

Positive: the low bidder was cheaper on that item. These 4 items account for $7,710 of the $7,710 gap.