FY26 Brenham AO TY B Gr 5 - 07
6503-91-001 · let Jul 15, 2026 · Washington, Bryan · Material Maintenance Project
$115,500Low bid: TOUCHSTONE RESOURCES, LLC-3.8% vs estimate $120,000
$2,600Left on the table2.3% gap to the second bid
5BiddersSpread 48% low to high
3Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TOUCHSTONE RESOURCES, LLC | $115,500 | -3.8% | $2,600 | 0 | 0 | |
| 2 | DIGG COMMERCIAL, LLC | $118,100 | +2.3% | -1.6% | $6,900 | 0 | 0 |
| 3 | TEXAS MATERIALS GROUP, INC. | $125,000 | +8.2% | 4.2% | $20,000 | 0 | 0 |
| 4 | KNIFE RIVER CORPORATION - SOUTH | $145,000 | +25.5% | 20.8% | $25,825 | 0 | 0 |
| 5 | MARTIN MARIETTA MATERIALS, INC. | $170,825 | +47.9% | 42.4% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
TOUCHSTONE RESOURCES, LLC vs DIGG COMMERCIAL, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8000-7113 AGGR (TY B GR 5) (DEL) (ST1) | 500 TON | $77.00 | $82.04 | $67.38 | $2,520 |
| 8000-7114 AGGR (TY B GR 5) (DEL) (ST2) | 500 TON | $77.00 | $78.31 | $67.10 | $655 |
| 8000-7115 AGGR (TY B GR 5) (DEL) (ST3) | 500 TON | $77.00 | $75.85 | $66.22 | -$575 |
Positive: the low bidder was cheaper on that item. These 3 items account for $2,600 of the $2,600 gap.