FY26 - District Illumination -02
6496-33-001 · let Feb 10, 2026 · Brazos, Bryan · Routine Maintenance Project - Sealed
$216,800Low bid: PROFESSIONAL TRAFFIC CONTROL LLC-18.2% vs estimate $264,890
$24,461Left on the table11.3% gap to the second bid
5BiddersSpread 41% low to high
14Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | PROFESSIONAL TRAFFIC CONTROL LLC | $216,800 | -18.2% | $24,461 | 1+$3,010 | 0 | |
| 2 | TRAF-TEX, INC. | $241,261 | +11.3% | -8.9% | $20,789 | 3+$82,489 | 1-$3,281 |
| 3 | BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. | $262,050 | +20.9% | -1.1% | $8,764 | 3+$93,853 | 1-$3,431 |
| 4 | WG ENGINEERING & CONSTRUCTION, LLC | $270,814 | +24.9% | 2.2% | $35,477 | 4+$121,742 | 0 |
| 5 | THIRD COAST SERVICES LLC | $306,291 | +41.3% | 15.6% | 5+$168,231 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
PROFESSIONAL TRAFFIC CONTROL LLC vs TRAF-TEX, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 690-7126 REPLACE LUMINAIRE POLE | 15 EA | $2,240.00 | $4,965.00 | $2,395.50 | $40,875 |
| 690-7071 INS OF TRF SIG PL FND (30" DRIL SHFT) | 40 LF | $850.00 | $403.00 | $521.70 | -$17,880 |
| 690-7125 INSTALL LUMINAIRE POLE | 5 EA | $1,890.00 | $4,965.00 | $1,721.87 | $15,375 |
| 690-7065 REPLACE OF LUMINAIRE HEAD | 50 EA | $986.00 | $741.00 | $623.02 | -$12,250 |
| 690-7019 REPLACE OF ELECTRICAL SERVICE | 6 EA | $6,986.00 | $8,908.00 | $4,286.17 | $11,532 |
| 690-7010 REPLACE OF CABLES | 1,000 LF | $7.86 | $3.15 | $6.43 | -$4,710 |
| 690-7008 INSTALL OF GROUND BOXES | 2 EA | $2,850.00 | $1,284.00 | $1,344.82 | -$3,132 |
| 690-7011 INSTALL OF CABLES | 800 LF | $6.86 | $3.00 | $5.39 | -$3,088 |
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $1,000.00 | $727.00 | $600.85 | -$1,638 |
| 505-7001 TMA (STATIONARY) | 60 DAY | $295.00 | $276.00 | $217.57 | -$1,140 |
| 690-7002 INSTALL OF CONDUIT BY TRENCHING | 250 LF | $10.86 | $15.40 | $14.44 | $1,135 |
| 690-7006 REMOVAL OF GROUND BOXES | 2 EA | $500.00 | $292.40 | $253.15 | -$415 |
| 690-7127 REMOVE LUMINAIRE POLE | 1 EA | $996.00 | $646.00 | $911.48 | -$350 |
| 690-7004 INSTALL OF CONDUIT BY BORING | 50 LF | $21.50 | $24.45 | $20.66 | $148 |
Positive: the low bidder was cheaper on that item. These 14 items account for $24,461 of the $24,461 gap.
PROFESSIONAL TRAFFIC CONTROL LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 690-7008 INSTALL OF GROUND BOXES | 2 EA | $2,850.00 | $1,344.82 | 2.12x | $3,010 |
TRAF-TEX, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 690-7126 REPLACE LUMINAIRE POLE | 15 EA | $4,965.00 | $2,395.50 | 2.07x | $38,542 |
| 690-7019 REPLACE OF ELECTRICAL SERVICE | 6 EA | $8,908.00 | $4,286.17 | 2.08x | $27,731 |
| 690-7125 INSTALL LUMINAIRE POLE | 5 EA | $4,965.00 | $1,721.87 | 2.88x | $16,216 |
| 690-7010 REPLACE OF CABLES | 1,000 LF | $3.15 | $6.43 | 0.49x | -$3,281 |
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 690-7126 REPLACE LUMINAIRE POLE | 15 EA | $6,500.00 | $2,395.50 | 2.71x | $61,567 |
| 690-7125 INSTALL LUMINAIRE POLE | 5 EA | $6,500.00 | $1,721.87 | 3.77x | $23,891 |
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $2,000.00 | $600.85 | 3.33x | $8,395 |
| 690-7010 REPLACE OF CABLES | 1,000 LF | $3.00 | $6.43 | 0.47x | -$3,431 |
WG ENGINEERING & CONSTRUCTION, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 690-7126 REPLACE LUMINAIRE POLE | 15 EA | $6,220.00 | $2,395.50 | 2.60x | $57,367 |
| 690-7019 REPLACE OF ELECTRICAL SERVICE | 6 EA | $9,925.00 | $4,286.17 | 2.32x | $33,833 |
| 690-7125 INSTALL LUMINAIRE POLE | 5 EA | $5,820.00 | $1,721.87 | 3.38x | $20,491 |
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $2,276.00 | $600.85 | 3.79x | $10,051 |
THIRD COAST SERVICES LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 690-7019 REPLACE OF ELECTRICAL SERVICE | 6 EA | $17,202.08 | $4,286.17 | 4.01x | $77,495 |
| 690-7126 REPLACE LUMINAIRE POLE | 15 EA | $5,961.26 | $2,395.50 | 2.49x | $53,486 |
| 690-7125 INSTALL LUMINAIRE POLE | 5 EA | $5,961.26 | $1,721.87 | 3.46x | $21,197 |
| 505-7001 TMA (STATIONARY) | 60 DAY | $409.18 | $217.57 | 1.88x | $11,496 |
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $1,360.06 | $600.85 | 2.26x | $4,555 |