Bid Tab X-ray: 6496-33-001

Feb 10, 2026 · Brazos Sign up free
Set your company to personalize scores

FY26 - District Illumination -02

6496-33-001 · let Feb 10, 2026 · Brazos, Bryan · Routine Maintenance Project - Sealed

$216,800Low bid: PROFESSIONAL TRAFFIC CONTROL LLC-18.2% vs estimate $264,890
$24,461Left on the table11.3% gap to the second bid
5BiddersSpread 41% low to high
14Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1PROFESSIONAL TRAFFIC CONTROL LLC $216,800-18.2% $24,461 1+$3,010 0
2TRAF-TEX, INC. $241,261+11.3%-8.9% $20,789 3+$82,489 1-$3,281
3BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. $262,050+20.9%-1.1% $8,764 3+$93,853 1-$3,431
4WG ENGINEERING & CONSTRUCTION, LLC $270,814+24.9%2.2% $35,477 4+$121,742 0
5THIRD COAST SERVICES LLC $306,291+41.3%15.6% 5+$168,231 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

PROFESSIONAL TRAFFIC CONTROL LLC vs TRAF-TEX, INC., biggest item swings
ItemQtyLow2ndMarket2nd minus low
690-7126 REPLACE LUMINAIRE POLE15 EA $2,240.00$4,965.00$2,395.50 $40,875
690-7071 INS OF TRF SIG PL FND (30" DRIL SHFT)40 LF $850.00$403.00$521.70 -$17,880
690-7125 INSTALL LUMINAIRE POLE5 EA $1,890.00$4,965.00$1,721.87 $15,375
690-7065 REPLACE OF LUMINAIRE HEAD50 EA $986.00$741.00$623.02 -$12,250
690-7019 REPLACE OF ELECTRICAL SERVICE6 EA $6,986.00$8,908.00$4,286.17 $11,532
690-7010 REPLACE OF CABLES1,000 LF $7.86$3.15$6.43 -$4,710
690-7008 INSTALL OF GROUND BOXES2 EA $2,850.00$1,284.00$1,344.82 -$3,132
690-7011 INSTALL OF CABLES800 LF $6.86$3.00$5.39 -$3,088
500-7002 MOBILIZATION (CALLOUT)6 EA $1,000.00$727.00$600.85 -$1,638
505-7001 TMA (STATIONARY)60 DAY $295.00$276.00$217.57 -$1,140
690-7002 INSTALL OF CONDUIT BY TRENCHING250 LF $10.86$15.40$14.44 $1,135
690-7006 REMOVAL OF GROUND BOXES2 EA $500.00$292.40$253.15 -$415
690-7127 REMOVE LUMINAIRE POLE1 EA $996.00$646.00$911.48 -$350
690-7004 INSTALL OF CONDUIT BY BORING50 LF $21.50$24.45$20.66 $148

Positive: the low bidder was cheaper on that item. These 14 items account for $24,461 of the $24,461 gap.

PROFESSIONAL TRAFFIC CONTROL LLC: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
690-7008 INSTALL OF GROUND BOXES2 EA $2,850.00$1,344.822.12x$3,010

TRAF-TEX, INC.: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
690-7126 REPLACE LUMINAIRE POLE15 EA $4,965.00$2,395.502.07x$38,542
690-7019 REPLACE OF ELECTRICAL SERVICE6 EA $8,908.00$4,286.172.08x$27,731
690-7125 INSTALL LUMINAIRE POLE5 EA $4,965.00$1,721.872.88x$16,216
690-7010 REPLACE OF CABLES1,000 LF $3.15$6.430.49x-$3,281

BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
690-7126 REPLACE LUMINAIRE POLE15 EA $6,500.00$2,395.502.71x$61,567
690-7125 INSTALL LUMINAIRE POLE5 EA $6,500.00$1,721.873.77x$23,891
500-7002 MOBILIZATION (CALLOUT)6 EA $2,000.00$600.853.33x$8,395
690-7010 REPLACE OF CABLES1,000 LF $3.00$6.430.47x-$3,431

WG ENGINEERING & CONSTRUCTION, LLC: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
690-7126 REPLACE LUMINAIRE POLE15 EA $6,220.00$2,395.502.60x$57,367
690-7019 REPLACE OF ELECTRICAL SERVICE6 EA $9,925.00$4,286.172.32x$33,833
690-7125 INSTALL LUMINAIRE POLE5 EA $5,820.00$1,721.873.38x$20,491
500-7002 MOBILIZATION (CALLOUT)6 EA $2,276.00$600.853.79x$10,051

THIRD COAST SERVICES LLC: unbalanced items

Placed 5
ItemQtyTheir priceMarketx market$ vs market
690-7019 REPLACE OF ELECTRICAL SERVICE6 EA $17,202.08$4,286.174.01x$77,495
690-7126 REPLACE LUMINAIRE POLE15 EA $5,961.26$2,395.502.49x$53,486
690-7125 INSTALL LUMINAIRE POLE5 EA $5,961.26$1,721.873.46x$21,197
505-7001 TMA (STATIONARY)60 DAY $409.18$217.571.88x$11,496
500-7002 MOBILIZATION (CALLOUT)6 EA $1,360.06$600.852.26x$4,555