FY26 Burleson Hot Mix - 06
6502-35-001 · let Jun 9, 2026 · Burleson, Bryan · Material Maintenance Project
$212,600Low bid: BIG CREEK CONSTRUCTION, LTD.-5.8% vs estimate $225,600
$4,800Left on the table2.3% gap to the second bid
5BiddersSpread 27% low to high
2Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BIG CREEK CONSTRUCTION, LTD. | $212,600 | -5.8% | $4,800 | 0 | 0 | |
| 2 | KNIFE RIVER CORPORATION - SOUTH | $217,400 | +2.3% | -3.6% | $5,550 | 0 | 0 |
| 3 | TEXAS MATERIALS GROUP, INC. | $222,950 | +4.9% | -1.2% | $12,350 | 0 | 0 |
| 4 | BRAZOS PAVING, INC. | $235,300 | +10.7% | 4.3% | $34,700 | 0 | 0 |
| 5 | AMERICAN MATERIALS, INC. | $270,000 | +27.0% | 19.7% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
BIG CREEK CONSTRUCTION, LTD. vs KNIFE RIVER CORPORATION - SOUTH, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8011-7146 D-GR HMA TY D PG 70-22 (DEL) SITE 1 | 2,000 TON | $98.00 | $100.00 | $117.96 | $4,000 |
| 8011-7145 D-GR HMA TY D PG 70-22 (PICKUP) | 200 TON | $83.00 | $87.00 | $111.44 | $800 |
Positive: the low bidder was cheaper on that item. These 2 items account for $4,800 of the $4,800 gap.