FY26 - Brazos Tree Removal - 01
6495-51-001 · let Jan 13, 2026 · Brazos, Bryan · Routine Maintenance Project
$111,514Low bid: M&D CONSTRUCTION SERVICES-20.1% vs estimate $139,500
$362Left on the table0.3% gap to the second bid
6BiddersSpread 78% low to high
13Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | M&D CONSTRUCTION SERVICES | $111,514 | -20.1% | $362 | 1+$26,770 | 0 | |
| 2 | RHINO EQUITY, LLC | $111,876 | +0.3% | -19.8% | $26,128 | 2+$28,170 | 2-$11,591 |
| 3 | WASTE SOLUTIONS USA LLC | $138,004 | +23.8% | -1.1% | $11,541 | 1+$32,113 | 0 |
| 4 | GV LANDSCAPE AND CONSTRUCTION LLC | $149,545 | +34.1% | 7.2% | $4,601 | 1+$7,197 | 0 |
| 5 | ORTEGA'S LAWN AND LANDSCAPING, LLC | $154,146 | +38.2% | 10.5% | $44,164 | 6+$78,946 | 2-$19,078 |
| 6 | PREMIER CONTRACTORS LLC | $198,310 | +77.8% | 42.2% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
M&D CONSTRUCTION SERVICES vs RHINO EQUITY, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 500 EA | $37.93 | $110.00 | $60.77 | $36,035 |
| 505-7001 TMA (STATIONARY) | 70 DAY | $600.00 | $100.00 | $217.57 | -$35,000 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 150 EA | $75.84 | $115.00 | $100.44 | $5,874 |
| 752-7004 STUMP REMOVAL | 25 EA | $75.84 | $300.00 | $157.73 | $5,604 |
| 752-7009 TREE REMOVAL (30" - 36" DIA) | 20 EA | $303.45 | $125.00 | $293.05 | -$3,569 |
| 752-7008 TREE REMOVAL (24" - 30" DIA) | 35 EA | $202.30 | $125.00 | $208.61 | -$2,706 |
| 752-7013 TREE REMOVAL (60" - 72" DIA) | 2 EA | $1,112.40 | $250.00 | $529.99 | -$1,725 |
| 500-7033 MOBILIZATION (EMERGENCY) | 1 EA | $1,703.01 | $1.00 | $844.81 | -$1,702 |
| 752-7012 TREE REMOVAL (48" - 60" DIA) | 2 EA | $808.60 | $250.00 | $450.06 | -$1,117 |
| 752-7010 TREE REMOVAL (36" - 42" DIA) | 5 EA | $455.18 | $250.00 | $334.81 | -$1,026 |
| 752-7011 TREE REMOVAL (42" - 48" DIA) | 2 EA | $606.90 | $250.00 | $436.67 | -$714 |
| 500-7002 MOBILIZATION (CALLOUT) | 3 EA | $817.40 | $1,000.00 | $600.85 | $548 |
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 100 EA | $126.41 | $125.00 | $141.37 | -$141 |
Positive: the low bidder was cheaper on that item. These 13 items account for $362 of the $362 gap.
M&D CONSTRUCTION SERVICES: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 70 DAY | $600.00 | $217.57 | 2.76x | $26,770 |
RHINO EQUITY, LLC: unbalanced items
Placed 2WASTE SOLUTIONS USA LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 500 EA | $125.00 | $60.77 | 2.06x | $32,113 |
GV LANDSCAPE AND CONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 3 EA | $3,000.00 | $600.85 | 4.99x | $7,197 |
ORTEGA'S LAWN AND LANDSCAPING, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 500 EA | $120.00 | $60.77 | 1.97x | $29,613 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 150 EA | $220.00 | $100.44 | 2.19x | $17,934 |
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 100 EA | $300.00 | $141.37 | 2.12x | $15,863 |
| 752-7008 TREE REMOVAL (24" - 30" DIA) | 35 EA | $400.00 | $208.61 | 1.92x | $6,699 |
| 752-7009 TREE REMOVAL (30" - 36" DIA) | 20 EA | $600.00 | $293.05 | 2.05x | $6,139 |
| 500-7002 MOBILIZATION (CALLOUT) | 3 EA | $1,500.00 | $600.85 | 2.50x | $2,697 |
| 505-7001 TMA (STATIONARY) | 70 DAY | $1.00 | $217.57 | 0.00x | -$15,160 |
| 752-7004 STUMP REMOVAL | 25 EA | $1.00 | $157.73 | 0.01x | -$3,918 |