Bid Tab X-ray: 6495-51-001

Jan 13, 2026 · Brazos Sign up free
Set your company to personalize scores

FY26 - Brazos Tree Removal - 01

6495-51-001 · let Jan 13, 2026 · Brazos, Bryan · Routine Maintenance Project

$111,514Low bid: M&D CONSTRUCTION SERVICES-20.1% vs estimate $139,500
$362Left on the table0.3% gap to the second bid
6BiddersSpread 78% low to high
13Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1M&D CONSTRUCTION SERVICES $111,514-20.1% $362 1+$26,770 0
2RHINO EQUITY, LLC $111,876+0.3%-19.8% $26,128 2+$28,170 2-$11,591
3WASTE SOLUTIONS USA LLC $138,004+23.8%-1.1% $11,541 1+$32,113 0
4GV LANDSCAPE AND CONSTRUCTION LLC $149,545+34.1%7.2% $4,601 1+$7,197 0
5ORTEGA'S LAWN AND LANDSCAPING, LLC $154,146+38.2%10.5% $44,164 6+$78,946 2-$19,078
6PREMIER CONTRACTORS LLC $198,310+77.8%42.2%

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

M&D CONSTRUCTION SERVICES vs RHINO EQUITY, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
752-7005 TREE REMOVAL (4" - 12" DIA)500 EA $37.93$110.00$60.77 $36,035
505-7001 TMA (STATIONARY)70 DAY $600.00$100.00$217.57 -$35,000
752-7006 TREE REMOVAL (12" - 18" DIA)150 EA $75.84$115.00$100.44 $5,874
752-7004 STUMP REMOVAL25 EA $75.84$300.00$157.73 $5,604
752-7009 TREE REMOVAL (30" - 36" DIA)20 EA $303.45$125.00$293.05 -$3,569
752-7008 TREE REMOVAL (24" - 30" DIA)35 EA $202.30$125.00$208.61 -$2,706
752-7013 TREE REMOVAL (60" - 72" DIA)2 EA $1,112.40$250.00$529.99 -$1,725
500-7033 MOBILIZATION (EMERGENCY)1 EA $1,703.01$1.00$844.81 -$1,702
752-7012 TREE REMOVAL (48" - 60" DIA)2 EA $808.60$250.00$450.06 -$1,117
752-7010 TREE REMOVAL (36" - 42" DIA)5 EA $455.18$250.00$334.81 -$1,026
752-7011 TREE REMOVAL (42" - 48" DIA)2 EA $606.90$250.00$436.67 -$714
500-7002 MOBILIZATION (CALLOUT)3 EA $817.40$1,000.00$600.85 $548
752-7007 TREE REMOVAL (18" - 24" DIA)100 EA $126.41$125.00$141.37 -$141

Positive: the low bidder was cheaper on that item. These 13 items account for $362 of the $362 gap.

M&D CONSTRUCTION SERVICES: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
505-7001 TMA (STATIONARY)70 DAY $600.00$217.572.76x$26,770

RHINO EQUITY, LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
752-7005 TREE REMOVAL (4" - 12" DIA)500 EA $110.00$60.771.81x$24,613
752-7004 STUMP REMOVAL25 EA $300.00$157.731.90x$3,557
505-7001 TMA (STATIONARY)70 DAY $100.00$217.570.46x-$8,230
752-7009 TREE REMOVAL (30" - 36" DIA)20 EA $125.00$293.050.43x-$3,361

WASTE SOLUTIONS USA LLC: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
752-7005 TREE REMOVAL (4" - 12" DIA)500 EA $125.00$60.772.06x$32,113

GV LANDSCAPE AND CONSTRUCTION LLC: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
500-7002 MOBILIZATION (CALLOUT)3 EA $3,000.00$600.854.99x$7,197

ORTEGA'S LAWN AND LANDSCAPING, LLC: unbalanced items

Placed 5
ItemQtyTheir priceMarketx market$ vs market
752-7005 TREE REMOVAL (4" - 12" DIA)500 EA $120.00$60.771.97x$29,613
752-7006 TREE REMOVAL (12" - 18" DIA)150 EA $220.00$100.442.19x$17,934
752-7007 TREE REMOVAL (18" - 24" DIA)100 EA $300.00$141.372.12x$15,863
752-7008 TREE REMOVAL (24" - 30" DIA)35 EA $400.00$208.611.92x$6,699
752-7009 TREE REMOVAL (30" - 36" DIA)20 EA $600.00$293.052.05x$6,139
500-7002 MOBILIZATION (CALLOUT)3 EA $1,500.00$600.852.50x$2,697
505-7001 TMA (STATIONARY)70 DAY $1.00$217.570.00x-$15,160
752-7004 STUMP REMOVAL25 EA $1.00$157.730.01x-$3,918