FY27 - Brenham AO Crack Seal -06
6502-31-001 · let Jun 9, 2026 · Washington, Bryan · Routine Maintenance Project
$150,270Low bid: D & M CONTRACTORS, LLC-2.3% vs estimate $153,735
$24,638Left on the table16.4% gap to the second bid
4BiddersSpread 112% low to high
3Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | D & M CONTRACTORS, LLC | $150,270 | -2.3% | $24,638 | 0 | 2-$520,251 | |
| 2 | GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY | $174,907 | +16.4% | 13.8% | $24,517 | 0 | 2-$522,315 |
| 3 | FYL ENTERPRISES, LLC | $199,424 | +32.7% | 29.7% | $118,840 | 0 | 2-$497,330 |
| 4 | CRACKSEAL OF TEXAS, LLC | $318,264 | +111.8% | 107.0% | 0 | 1-$443,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
D & M CONTRACTORS, LLC vs GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 712-7001 JT / CRCK SEAL (RUBBER - ASPHALT) | 156.15 LMI | $917.00 | $1,088.00 | $868.20 | $26,702 |
| 500-7001 MOBILIZATION | 1 LS | $7,000.00 | $5,000.00 | $523,850.32 | -$2,000 |
| 505-7001 TMA (STATIONARY) | 16 DAY | $5.00 | $1.00 | $217.57 | -$64 |
Positive: the low bidder was cheaper on that item. These 3 items account for $24,638 of the $24,638 gap.
D & M CONTRACTORS, LLC: unbalanced items
Placed 1GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY: unbalanced items
Placed 2FYL ENTERPRISES, LLC: unbalanced items
Placed 3CRACKSEAL OF TEXAS, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $80,000.00 | $523,850.32 | 0.15x | -$443,850 |