234Let jobs
$671,404,829Total low bids
$868,953,854Total estimates
-22.7%Low bids vs estimates
Sep 2025 results
Bid tabs (Excel) ExcelCSV| Let date | CCSJ | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Sep 30, 2025 | 6479-54-001RMC - A00213877 | Galveston Houston |
FY 25 REFLECTIVE PAVEMENT MARKINGSSH0146 · Routine Maintenance Project - Sealed | $724,903 | $663,355 | TRP INFRASTRUCTURE SERVICES, LLC | -8.5% | 5 |
| Sep 30, 2025 | 6489-60-001RMC - A00217502 | Jefferson Beaumont |
SH 87 Roadway RepairSH 87 · Routine Maintenance Project | $493,475 | $596,904 | TEXAS MATERIALS GROUP, INC. | +21.0% | 1 |
| Sep 30, 2025 | 6491-43-001MMC - A00217841 | Liberty Beaumont |
FY 26 LAO HMCLUS0090 · Material Maintenance Project - Sealed | $373,000 | $405,500 | TEXAS MATERIALS GROUP, INC. | +8.7% | 1 |
| Sep 30, 2025 | 6491-17-001MMC - A00217770 | Jefferson Beaumont |
FY 26 BAO Hot Mix Cold LaidUS0069 · Material Maintenance Project - Sealed | $291,000 | $322,000 | TEXAS MATERIALS GROUP, INC. | +10.7% | 1 |
| Sep 30, 2025 | 6486-10-001MMC - A00216198 | Stonewall Abilene |
ABL-District Brine SaltUS0083 · Material Maintenance Project | $256,186 | $275,962 | NSG LOGISTICS, LLC | +7.7% | 1 |
| Sep 30, 2025 | 6491-38-001MMC - A00217834 | Orange Beaumont |
FY 26 OAO HMCLSH0062 · Material Maintenance Project - Sealed | $220,000 | $235,500 | TEXAS MATERIALS GROUP, INC. | +7.0% | 1 |
| Sep 30, 2025 | 6491-07-001MMC - A00217749 | Zavala Laredo |
DISTRICTWIDE AGGREGATESUS0083 · Material Maintenance Project - Sealed | $120,000 | $143,750 | TOUCHSTONE RESOURCES, LLC | +19.8% | 1 |
| Sep 30, 2025 | 6486-62-001SUP - A00216387 | Karnes Corpus Christi |
6486-62-001 Karnes GuardrailUS0181 · State Use Project - Sealed | $425,505 | — | 0 | ||
| Sep 30, 2025 | 6486-68-001SUP - A00216394 | Jim Wells Corpus Christi |
6486-68-001 Jim Wells Cable BarrierUS0281 · State Use Project - Sealed | $394,225 | — | 0 | ||
| Sep 29, 2025 | 6486-37-001SUP - A00216258 | Nueces Corpus Christi |
6486-37-001 Nueces Cable BarrierIH0037 · State Use Project - Sealed | $259,611 | — | 0 | ||
| Sep 29, 2025 | 6486-58-001SUP - A00216382 | San Patricio Corpus Christi |
6486-58-001 San Patricio GuardrailUS0077 · State Use Project - Sealed | $723,096 | — | 0 | ||
| Sep 29, 2025 | 6486-59-001SUP - A00216383 | San Patricio Corpus Christi |
6486-59-001San Patricio Cable BarrierUS0077 · State Use Project - Sealed | $259,611 | — | 0 | ||
| Sep 29, 2025 | 6486-64-001SUP - A00216389 | Karnes Corpus Christi |
6486-64-001 Karnes Cable BarrierUS0181 · State Use Project - Sealed | $151,857 | — | 0 | ||
| Sep 26, 2025 | 6488-97-001SUP - A00217238 | Harris Houston |
SUP 6488-97-001 Litter RemovalUS0290 · State Use Project | $512,371 | — | 0 | ||
| Sep 26, 2025 | 6489-00-001SUP - A00217256 | Harris Houston |
SUP 6489-00-001 Litter RemovalUS0290 · State Use Project | $285,800 | — | 0 | ||
| Sep 25, 2025 | 6492-08-001SUP - A00217994 | Mills Brownwood |
SU JANITORIAL MAINTENANCE MILLSUS0084 · State Use Project | $31,569 | — | 0 | ||
| Sep 24, 2025 | 6490-44-001BPM - A00217632 | Shelby Lufkin |
2025-09 Clean and Seal JointsUS0084 · Bridge Preventative Maintenance - Sealed | $878,495 | $589,785 | GARRET SHIELDS INFRASTRUCTURE | -32.9% | 9 |
| Sep 24, 2025 | 6488-94-001RMC - A00217232 | Nacogdoches Lufkin |
2025-08 Nacogdoches (North) TreeUS0059 · Routine Maintenance Project | $585,500 | $539,000 | FLORES TREE SERVICE LLC | -7.9% | 5 |
| Sep 24, 2025 | 6488-49-001RMC - A00217122 | Houston Lufkin |
2025-09 Houston MBGFUS0287 · Routine Maintenance Project - Sealed | $193,750 | $176,050 | RHINO EQUITY, LLC | -9.1% | 3 |
| Sep 24, 2025 | 6490-33-001RMC - A00217606 | Gray Amarillo |
Sweeping Pampa AE FY 26IH0040 · Routine Maintenance Project | $185,186 | $161,356 | PANHANDLE SWEEPING & MAINTENANCE, LLC | -12.9% | 1 |
| Sep 23, 2025 | 6470-03-001RMC - A00210697 | Lubbock Lubbock |
US87 Mill and Inlay Pavement RepairUS0087 · Routine Maintenance Project - Sealed | $945,677 | $1,305,474 | LONE STAR DIRT & PAVING, LTD. | +38.0% | 1 |
| Sep 23, 2025 | 6483-91-001BPM - A00215319 | De Witt Yoakum |
Erosion Repair FY 2026 #1FM0682 · Bridge Preventative Maintenance - Sealed | $473,155 | $305,712 | CRACKSEAL OF TEXAS, LLC | -35.4% | 8 |
| Sep 23, 2025 | 6491-68-001SUP - A00217919 | Delta Paris |
Janitorial - Delta FY25SH0024 · State Use Project | $12,031 | — | 0 | ||
| Sep 23, 2025 | 6492-38-001SUP - A00218092 | Brazos Bryan |
FY26 Bryan Headquarters JanitorialSH0006 · State Use Project | $140,699 | — | 0 | ||
| Sep 22, 2025 | 6486-98-001MMC - A00216496 | De Witt Yoakum |
Hot Mix CL-DeWitt Co. (Materials Only)US0183 · Material Maintenance Project | $540,000 | $504,000 | BRAUNTEX MATERIALS, INC. | -6.7% | 4 |
| Sep 22, 2025 | 6486-96-001MMC - A00216494 | Colorado Yoakum |
Brine FY26 (Materials Only)IH0010 · Material Maintenance Project | $300,000 | $353,200 | TOUCHSTONE RESOURCES, LLC | +17.7% | 1 |
| Sep 19, 2025 | 6489-03-001EMC - A00217259 | Tom Green San Angelo |
US 67 W OF BELL ST FLOOD DAMAGEUS 67 · Emergency Maintenance Project - Sealed | $11,781,879 | — | 0 | ||
| Sep 19, 2025 | 6486-79-001MMA - A00216455 | Dallas Dallas |
MMA for Irving 2025IH0635 · Miscellaneous Maintenance Agreement | $845,770 | — | 0 | ||
| Sep 18, 2025 | 6488-93-001RMC - A00217231 | Grayson Paris |
Crack Seal-SAO FY26SH0056 · Routine Maintenance Project - Sealed | $432,989 | $839,451 | D & M CONTRACTORS, LLC | +93.9% | 2 |
| Sep 18, 2025 | 6490-34-001MMC - A00217610 | Tom Green San Angelo |
WINTER WEATHER MATERIALS FY 26US0087 · Material Maintenance Project | $586,035 | $631,352 | NSG LOGISTICS, LLC | +7.7% | 2 |
| Sep 18, 2025 | 6488-54-001MMC - A00217135 | Parker Fort Worth |
FY2026 - Winter Weather Mtrls - ParkerIH0020 · Material Maintenance Project | $586,238 | $589,470 | NSG LOGISTICS, LLC | +0.6% | 1 |
| Sep 18, 2025 | 6487-05-001MMC - A00216506 | Tarrant Fort Worth |
FY 2026 - Salt & Chloride S. Tarrant MMCIH0020 · Material Maintenance Project | $494,941 | $484,591 | NSG LOGISTICS, LLC | -2.1% | 1 |
| Sep 18, 2025 | 6487-81-001MMC - A00216796 | Parker Fort Worth |
FY 2026 - MMC Brine Solution - ParkerIH0020 · Material Maintenance Project | $436,500 | $414,000 | NSG LOGISTICS, LLC | -5.2% | 2 |
| Sep 18, 2025 | 6488-91-001RMC - A00217229 | Red River Paris |
Crack Seal-PAO FY26US0082 · Routine Maintenance Project - Sealed | $320,722 | $400,320 | SCOUT 5 CONSTRUCTION LLC | +24.8% | 4 |
| Sep 18, 2025 | 6488-85-001MMC - A00217221 | Johnson Fort Worth |
FY 2026 - MMC Wntr Wthr Mtrl - JohnsonIH0035W · Material Maintenance Project | $389,000 | $367,185 | NSG LOGISTICS, LLC | -5.6% | 1 |
| Sep 18, 2025 | 6489-02-001MMC - A00217258 | Erath Fort Worth |
FY2026 - Wntr Wthr Mtl - HESUS0377 · Material Maintenance Project | $298,273 | $322,861 | NSG LOGISTICS, LLC | +8.2% | 1 |
| Sep 18, 2025 | 6488-60-001RMC - A00217145 | Hunt Paris |
Crack Seal-GAO FY26US0069 · Routine Maintenance Project - Sealed | $257,027 | $289,673 | SCOUT 5 CONSTRUCTION LLC | +12.7% | 4 |
| Sep 18, 2025 | 6484-12-001RMC - A00215395 | Parker Fort Worth |
FY26 Tree & Brush Removal Parker/PPIH0020 · Routine Maintenance Project - Sealed | $447,961 | $261,175 | RHINO EQUITY, LLC | -41.7% | 8 |
| Sep 18, 2025 | 6487-78-001MMC - A00216773 | Tarrant Fort Worth |
FY 26 - MMC Wntr Wthr Rd & Br Salt - NTIH0820 · Material Maintenance Project | $204,500 | $200,750 | NSG LOGISTICS, LLC | -1.8% | 2 |
| Sep 18, 2025 | 6489-06-001MMC - A00217294 | Erath Fort Worth |
FY2026 - Wntr Wthr Mtrl Brine Sol - HESUS0377 · Material Maintenance Project | $165,680 | $176,320 | NSG LOGISTICS, LLC | +6.4% | 2 |
| Sep 18, 2025 | 6488-95-001RMC - A00217234 | Hopkins Paris |
Crack Seal-SSAO FY26IH0030 · Routine Maintenance Project - Sealed | $144,388 | $163,397 | SCOUT 5 CONSTRUCTION LLC | +13.2% | 4 |
| Sep 18, 2025 | 6477-36-001BPM - A00213015 | Parker Fort Worth |
FY25 BRIDGE BEAM REPAIR, PARKER COUNTYSH0199 · Bridge Preventative Maintenance - Sealed | $285,428 | $142,050 | GARRET SHIELDS INFRASTRUCTURE | -50.2% | 5 |
| Sep 18, 2025 | 6487-10-001MMC - A00216519 | Wise Fort Worth |
FY2026 - J & W Salt & Cmplx Clrd - MMCUS0081 · Material Maintenance Project | $134,500 | $134,470 | NSG LOGISTICS, LLC | 0.0% | 1 |
| Sep 18, 2025 | 6487-11-001MMC - A00216520 | Wise Fort Worth |
FY 2026 - J&W Brine Solution - MMCUS0081 · Material Maintenance Project | $116,550 | $114,200 | NSG LOGISTICS, LLC | -2.0% | 2 |
| Sep 18, 2025 | 6488-86-001MMC - A00217222 | Johnson Fort Worth |
FY2025 - WW MMC Brine SOL - JohnsonIH0035W · Material Maintenance Project | $191,400 | $104,720 | NSG LOGISTICS, LLC | -45.3% | 2 |
| Sep 18, 2025 | 6481-23-001BPM - A00214350 | Fannin Paris |
BPM Grayson FY26US0082 · Bridge Preventative Maintenance - Sealed | $174,277 | $86,644 | 12TWELVE ROAD AND BRIDGE LLC | -50.3% | 9 |
| Sep 18, 2025 | 6490-35-001MMC - A00217612 | Tom Green San Angelo |
BRINE SALT FY 26US0067 · Material Maintenance Project | $71,516 | $79,200 | TOUCHSTONE RESOURCES, LLC | +10.7% | 2 |
| Sep 18, 2025 | 6487-47-001MMC - A00216659 | Parker Fort Worth |
FY 2026 MMC Flowable Backfill - ParkerIH0020 · Material Maintenance Project | $36,600 | $51,000 | TOUCHSTONE RESOURCES, LLC | +39.3% | 2 |
| Sep 17, 2025 | 6486-91-001RMC - A00216488 | Bowie Atlanta |
Crack Seal - District Wide FY '26US0059 · Routine Maintenance Project | $687,136 | $1,068,558 | D & M CONTRACTORS, LLC | +55.5% | 1 |
| Sep 17, 2025 | 6491-12-001MMC - A00217755 | Jefferson Beaumont |
FY 26 LRASH0347 · Material Maintenance Project - Sealed | $730,700 | $672,636 | MARTIN MARIETTA MATERIALS, INC. | -7.9% | 2 |
| Sep 17, 2025 | 6480-15-001RMC - A00214053 | San Augustine Lufkin |
2025-09 SAN AUG Culvert Repair(District)US0096 · Routine Maintenance Project - Sealed | $772,027 | $617,373 | A R BROTHERS CONSTRUCTION SERVICES, INC. | -20.0% | 7 |
| Sep 17, 2025 | 6489-75-001RMC - A00217528 | Medina San Antonio |
FY 26 Debris RemovalIH0035 · Routine Maintenance Project | $842,140 | $589,992 | BIG TEX CONTRACTORS, LLC | -29.9% | 11 |
| Sep 17, 2025 | 6489-91-001RMC - A00217548 | Kerr San Antonio |
FY 26 KERR PICNIC MAINTENANCEIH0010 · Routine Maintenance Project | $798,208 | $524,272 | BK FIELD OPERATIONS LLC | -34.3% | 9 |
| Sep 17, 2025 | 6489-92-001RMC - A00217549 | Bexar San Antonio |
FY 26 TRAFFIC SIGNAL EMERGENCY REPAIRIH0035 · Routine Maintenance Project - Sealed | $369,806 | $399,960 | E-Z BEL CONSTRUCTION, LLC | +8.2% | 2 |
| Sep 17, 2025 | 6486-76-001RMC - A00216418 | Nacogdoches Lufkin |
2025-09 Nacogdoches Tree RemovalUS0059 · Routine Maintenance Project - Sealed | $354,500 | $315,375 | K & R CONTRACTORS | -11.0% | 4 |
| Sep 17, 2025 | 6487-93-001RMC - A00216930 | Angelina Lufkin |
2025 Install of Raised Pavement MarkersUS0059 · Routine Maintenance Project - Sealed | $320,625 | $257,750 | TRP INFRASTRUCTURE SERVICES, LLC | -19.6% | 3 |
| Sep 17, 2025 | 6488-64-001BPM - A00217164 | Bandera San Antonio |
SH 16 AT MEDINA RIVER FY25 FLOODSH0016 · Bridge Preventative Maintenance - Sealed | $83,556 | $92,080 | GARRET SHIELDS INFRASTRUCTURE | +10.2% | 3 |
| Sep 16, 2025 | 6491-04-001MMC - A00217746 | Newton Beaumont |
FY 26 EmulsionFM1012 · Material Maintenance Project - Sealed | $887,040 | $866,030 | CLEVELAND ASPHALT PRODUCTS, INC. | -2.4% | 1 |
| Sep 16, 2025 | 6490-63-001MMC - A00217673 | Jefferson Beaumont |
FY 26 Flex BaseUS0069 · Material Maintenance Project - Sealed | $933,500 | $744,450 | VULCAN CONSTRUCTION MATERIALS, LLC | -20.3% | 5 |
| Sep 16, 2025 | 6490-65-001MMC - A00217677 | Karnes Corpus Christi |
6490-65-001 Cement Karnes AreaUS0181 · Material Maintenance Project | $519,000 | $570,000 | TOUCHSTONE RESOURCES, LLC | +9.8% | 1 |
| Sep 16, 2025 | 6483-21-001RMC - A00215012 | Henderson Tyler |
FY 26 South Crack SealUS0175 · Routine Maintenance Project - Sealed | $436,550 | $547,291 | D & M CONTRACTORS, LLC | +25.4% | 1 |
| Sep 16, 2025 | 6486-71-001RMC - A00216399 | Hale Lubbock |
Traffic Control - PlainviewIH0027 · Routine Maintenance Project - Sealed | $234,500 | $476,450 | AWP SAFETY | +103.2% | 1 |
| Sep 16, 2025 | 6486-69-001RMC - A00216397 | Terry Lubbock |
Traffic Control - BrownfieldUS0062 · Routine Maintenance Project - Sealed | $566,250 | $471,580 | AUSTIN BARRICADE COMPANY, L.L.C. | -16.7% | 2 |
| Sep 16, 2025 | 6486-70-001RMC - A00216398 | Lamb Lubbock |
Traffic Control - LittlefieldUS0084 · Routine Maintenance Project - Sealed | $234,000 | $470,125 | AWP SAFETY | +100.9% | 1 |
| Sep 16, 2025 | 6489-49-001MMC - A00217442 | Bexar San Antonio |
DW 8C-B Brine Salt & 4A Sodium ChlorideIH0010 · Material Maintenance Project | $430,720 | $452,700 | TOUCHSTONE RESOURCES, LLC | +5.1% | 1 |
| Sep 16, 2025 | 6457-29-001RMC - A00204765 | Lubbock Lubbock |
FY 2026 Illumination MaintenanceIH0027 · Routine Maintenance Project - Sealed | $248,250 | $395,450 | VACA UNDERGROUND UTILITIES INC | +59.3% | 1 |
| Sep 16, 2025 | 6490-71-001MMC - A00217688 | Jefferson Beaumont |
FY 26 Winter Weather MaterialUS0069 · Material Maintenance Project - Sealed | $349,240 | $388,220 | TOUCHSTONE RESOURCES, LLC | +11.2% | 1 |
| Sep 16, 2025 | 6490-66-001MMC - A00217678 | Aransas Corpus Christi |
6490-66-001 Rockport LRASH0035 · Material Maintenance Project | $352,500 | $374,440 | VULCAN CONSTRUCTION MATERIALS, LLC | +6.2% | 2 |
| Sep 16, 2025 | 6490-67-001MMC - A00217679 | Refugio Corpus Christi |
6490-67-001 Refugio Maint LRAUS0077 · Material Maintenance Project | $343,000 | $356,320 | VULCAN CONSTRUCTION MATERIALS, LLC | +3.9% | 2 |
| Sep 16, 2025 | 6489-51-001MMC - A00217444 | Bexar San Antonio |
2025 DW Brine SolutionIH0010 · Material Maintenance Project | $269,100 | $321,250 | TOUCHSTONE RESOURCES, LLC | +19.4% | 1 |
| Sep 16, 2025 | 6490-68-001MMC - A00217680 | Aransas Corpus Christi |
6490-68-001 Rockport Maint. FlexbaseSH0035 · Material Maintenance Project | $329,000 | $298,760 | MARTIN MARIETTA MATERIALS, INC. | -9.2% | 5 |
| Sep 16, 2025 | 6483-20-001RMC - A00215011 | Gregg Tyler |
FY 26 North Crack SealSH0031 · Routine Maintenance Project - Sealed | $430,395 | $283,388 | SCOUT 5 CONSTRUCTION LLC | -34.2% | 2 |
| Sep 16, 2025 | 6487-85-001BPM - A00216833 | Nueces Corpus Christi |
6487-85-001 Bridge Preventative Maint.SH0358 · Bridge Preventative Maintenance - Sealed | $199,787 | $276,452 | TAYLOR BRIDGE LLC | +38.4% | 6 |
| Sep 16, 2025 | 6487-22-001RMC - A00216532 | Smith Tyler |
Smith Co. FY 26 Tree TrimmingUS0069 · Routine Maintenance Project | $238,882 | $188,686 | SHAWNEE MISSION TREE SERVICE, INC. | -21.0% | 12 |
| Sep 16, 2025 | 6489-50-001MMC - A00217443 | Bexar San Antonio |
2025 DW Type 5 Modified AggregateIH0010 · Material Maintenance Project | $136,300 | $159,500 | TOUCHSTONE RESOURCES, LLC | +17.0% | 1 |
| Sep 15, 2025 | 6490-49-001SUP - A00217637 | Navarro Dallas |
Navarro Litter 2 0925SH0031 · State Use Project | $34,992 | — | 0 | ||
| Sep 15, 2025 | 6489-95-001SUP - A00217552 | Navarro Dallas |
Navarro Litter IH45 0925IH0045 · State Use Project | $134,281 | — | 0 | ||
| Sep 12, 2025 | 6488-99-001MMC - A00217255 | Wichita Wichita Falls |
2026 - De-Icing/Anti-Icing MaterialsUS0287 · Material Maintenance Project | $589,690 | $538,693 | NSG LOGISTICS, LLC | -8.6% | 1 |
| Sep 11, 2025 | 6482-12-001BPM - A00214666 | Kent Abilene |
2026 Bridge Preventative MaintenanceUS0380 · Bridge Preventative Maintenance - Sealed | $997,965 | $611,250 | BLACKSMITH VENTURES LLC | -38.8% | 12 |
| Sep 10, 2025 | 6488-84-001MMC - A00217207 | Ellis Dallas |
Limestone Rock Asphalt 09 0925FM0876 · Material Maintenance Project | $622,500 | $678,458 | MARTIN MARIETTA MATERIALS, INC. | +9.0% | 2 |
| Sep 10, 2025 | 6484-81-001MMC - A00215617 | Dallas Dallas |
Aggregate - Materials Only - East DALIH0030 · Material Maintenance Project | $291,375 | $291,375 | ARCOSA LWS, LLC | 0.0% | 1 |
| Sep 10, 2025 | 6484-82-001MMC - A00215618 | Dallas Dallas |
Aggregate - Materials Only - West DALIH0020 · Material Maintenance Project | $275,625 | $275,625 | ARCOSA LWS, LLC | 0.0% | 1 |
| Sep 10, 2025 | 6485-54-001MMC - A00215979 | Dallas Dallas |
Road Salt - Materials Only - West DALIH0020 · Material Maintenance Project | $259,875 | $253,881 | NSG LOGISTICS, LLC | -2.3% | 2 |
| Sep 10, 2025 | 6485-53-001MMC - A00215978 | Dallas Dallas |
Road Salt - Materials Only - East DALIH0030 · Material Maintenance Project | $259,875 | $253,527 | NSG LOGISTICS, LLC | -2.4% | 2 |
| Sep 10, 2025 | 6485-47-001TMC - A00215967 | Dallas Dallas |
Battery Back Up System APC 2025US0080 · Material Only Traffic | $147,756 | $243,600 | TOUCHSTONE RESOURCES, LLC | +64.9% | 1 |
| Sep 10, 2025 | 6487-62-001RMC - A00216743 | Blanco Austin |
BTAO FY 26 Blanco Co. MowingUS0281 · Routine Maintenance Project - Sealed | $260,400 | $240,523 | P-VILLE, INCORPORATED | -7.6% | 4 |
| Sep 10, 2025 | 6484-55-001RMC - A00215495 | Brewster El Paso |
Janitorial & Landscape Maint - 11 SitesUS0067 · Routine Maintenance Project | $305,578 | $226,830 | 2H, LLC | -25.8% | 3 |
| Sep 10, 2025 | 6486-29-001MMC - A00216246 | Navarro Dallas |
Flex Base 01 0925SH0031 · Material Maintenance Project | $201,924 | $217,250 | TOUCHSTONE RESOURCES, LLC | +7.6% | 2 |
| Sep 10, 2025 | 6482-19-001MMC - A00214680 | Collin Dallas |
Brine Salt FY26SH0005 · Material Maintenance Project | $196,000 | $204,052 | NSG LOGISTICS, LLC | +4.1% | 2 |
| Sep 10, 2025 | 6485-52-001MMC - A00215977 | Dallas Dallas |
Brine Salt - Materials Only - West DALIH0020 · Material Maintenance Project | $184,625 | $176,062 | NSG LOGISTICS, LLC | -4.6% | 2 |
| Sep 10, 2025 | 6485-51-001MMC - A00215976 | Dallas Dallas |
Brine Salt - Materials Only - East DALIH0030 · Material Maintenance Project | $163,625 | $163,441 | NSG LOGISTICS, LLC | -0.1% | 1 |
| Sep 10, 2025 | 6486-16-001MMC - A00216206 | Navarro Dallas |
Emulsion 0925SH0031 · Material Maintenance Project | $187,530 | $148,170 | WRIGHT ASPHALT PRODUCTS COMPANY LLC | -21.0% | 2 |
| Sep 10, 2025 | 6485-87-001MMC - A00216133 | Navarro Dallas |
Winter Weather Materials 01 0925SH0031 · Material Maintenance Project | $145,560 | $145,171 | NSG LOGISTICS, LLC | -0.3% | 1 |
| Sep 10, 2025 | 6480-92-001RMC - A00214300 | Navarro Dallas |
Tree Trimming and Brush Removal 01 0925FM0667 · Routine Maintenance Project - Sealed | $162,069 | $127,261 | RHINO EQUITY, LLC | -21.5% | 10 |
| Sep 10, 2025 | 6486-07-001MMC - A00216195 | Navarro Dallas |
Hydraulic Cement 0925SH0031 · Material Maintenance Project | $123,200 | $120,000 | TOUCHSTONE RESOURCES, LLC | -2.6% | 1 |
| Sep 10, 2025 | 6482-18-001MMC - A00214679 | Collin Dallas |
Road Salt FY26SH0005 · Material Maintenance Project | $108,000 | $105,117 | NSG LOGISTICS, LLC | -2.7% | 3 |
| Sep 10, 2025 | 6485-50-001MMC - A00215975 | Navarro Dallas |
Limestone Rock Asphalt 01 0925SH0031 · Material Maintenance Project | $74,000 | $74,240 | VULCAN CONSTRUCTION MATERIALS, LLC | +0.3% | 2 |
| Sep 10, 2025 | 6484-56-001RMC - A00215496 | Hudspeth El Paso |
Picnic Area & Landscaping Maint -DellUS0062 · Routine Maintenance Project | $75,210 | $47,586 | CM COMPANY | -36.7% | 3 |
| Sep 9, 2025 | 6484-53-001RMC - A00215493 | El Paso El Paso |
Districtwide Crack Seal -WAOIH0010 · Routine Maintenance Project | $804,925 | $1,308,890 | CRACKSEAL OF TEXAS, LLC | +62.6% | 2 |
| Sep 9, 2025 | 6486-41-001RMC - A00216262 | Swisher Lubbock |
FM928 and IH27 Bridge RepairIH0027 · Routine Maintenance Project - Sealed | $590,933 | $963,871 | L A FULLER & SONS CONSTRUCTION, LTD. | +63.1% | 3 |
1–100 of 234Next ›
Source: TxDOT Bid Tabulations (data.texas.gov), which covers state and local lettings from the previous 24 months. Bid Potato keeps every month it has loaded, so history grows past that window. Totals are as read at the letting; on packaged proposals the low bid can be the whole package total. Confirm against TxDOT's official tabulations.