146Let jobs
$656,862,408Total low bids
$707,463,274Total estimates
-7.2%Low bids vs estimates
Jun 2020 results
Bid tabs (Excel) ExcelCSV| Let date | CCSJ | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Jun 4, 2020 | 0028-02-100C 28-2-100 | Harris Houston |
LANDSCAPEUS 90 · | $2,322,075 | $1,486,714 | TEXAS WALL & LANDSCAPE | -36.0% | 4 |
| Jun 4, 2020 | 0091-06-059STP 2020(486)HES | Dallas Dallas |
TRAFFIC SIGNAL INSTALLATIONSH 289 · | $1,495,443 | $1,235,537 | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. | -17.4% | 5 |
| Jun 4, 2020 | 0906-00-229C 906-00-229 | Ector Odessa |
PROFILE PAVEMENT MARKINGSVA · | $1,601,681 | $1,222,833 | CENTERLINE TECHNOLOGIES, LLC | -23.7% | 8 |
| Jun 4, 2020 | 6355-80-001RMC - 635580001 | Bell Waco |
BASE FAILURE PAVEMENT REPAIRFM 439 · | $1,571,364 | $1,206,361 | TEXAS MATERIALS GROUP, INC. | -23.2% | 4 |
| Jun 4, 2020 | 0077-06-101STP 2020(905)HES | Tom Green San Angelo |
IMPROVE SIGNALS, INSTALL SIDEWALKSUS 67 · | $897,035 | $1,130,458 | RELMCO, INC. | +26.0% | 2 |
| Jun 4, 2020 | 0917-00-047C 917-00-47 | Brazos Bryan |
UPGRADE SIGNALSVA · | $1,255,223 | $1,091,966 | THIRD COAST SERVICES LLC | -13.0% | 2 |
| Jun 4, 2020 | 6361-73-001RMC - 636173001 | Wichita Wichita Falls |
ON-CALL STRIPINGUS 82 · | $860,087 | $977,445 | STRIPING TECHNOLOGY, L.P. | +13.6% | 6 |
| Jun 4, 2020 | 6358-78-001RMC - 635878001 | Collin Dallas |
CLEANING & SWEEPING HIGHWAYS & DEBRIS REMOVALUS 75 · | $1,209,126 | $956,523 | PAVEMENT PARTNERS, LLC | -20.9% | 4 |
| Jun 4, 2020 | 0923-17-079BR 2020(699) | Comanche Brownwood |
REPLACE BRIDGE AND APPROACHESCR · | $932,085 | $939,512 | KNIFE RIVER CORPORATION - SOUTH | +0.8% | 6 |
| Jun 4, 2020 | 6362-22-001RMC - 636222001 | Midland Odessa |
CALLOUT TRAFFIC CONTROL SERVICESIH 20 · | $1,000,000 | $904,300 | BARRICADES UNLIMITED | -9.6% | 2 |
| Jun 4, 2020 | 0923-09-063BR 2020(702) | Eastland Brownwood |
REPLACE BRIDGE AND APPROACHESCR · | $907,023 | $858,823 | HODGES AND SON CONSTRUCTION COMPANY, INC. | -5.3% | 5 |
| Jun 4, 2020 | 6363-48-001BPM - 636348001 | Reeves Odessa |
BRIDGE REPAIRIH 20 · | $749,979 | $831,572 | SCOTT TUCKER CONSTRUCTION COMPANY, LLC | +10.9% | 5 |
| Jun 4, 2020 | 0273-01-066STP 2B20(040)HES | Lampasas Brownwood |
1.5" SUPERPAVE OVERLAY WITH TACK COATUS 183 · | $952,177 | $824,661 | TEXAS MATERIALS GROUP, INC. | -13.4% | 2 |
| Jun 4, 2020 | 6364-09-001MMC - 636409001 | Guadalupe San Antonio |
MATERIALS ONLY (ASPPM PATCHING MATERIAL - BAGGED)SH 46 · | $948,000 | $810,000 | BULLCHASE, INC. | -14.6% | 3 |
| Jun 4, 2020 | 2552-02-034C 2552-2-34 | El Paso El Paso |
MILL & OVERLAY CLEANING/RESEAL BRIDGE JOINTSSL 375 · | $982,043 | $777,686 | DAN WILLIAMS COMPANY | -20.8% | 8 |
| Jun 4, 2020 | 6364-07-001MMC - 636407001 | Garza Maintenance Division |
MATERIALS ONLY (ASPPM PATCHING MATERIAL - BAGGED)US 84 · | $910,080 | $777,600 | BULLCHASE, INC. | -14.6% | 3 |
| Jun 4, 2020 | 0064-05-063STP 2019(495)HES | Sabine Lufkin |
CONSTRUCTION OF SAFETY WORKFM 1 · | $610,907 | $764,437 | A R BROTHERS CONSTRUCTION SERVICES, INC. | +25.1% | 6 |
| Jun 4, 2020 | 6359-96-001RMC - 635996001 | Navarro Dallas |
CLEANING & SWEEPING HIGHWAYS & DEBRIS REMOVALSH 31 · | $1,145,790 | $737,681 | PAVEMENT PARTNERS, LLC | -35.6% | 5 |
| Jun 4, 2020 | 0440-02-021CC 440-2-21 | Williamson Austin |
INTERSECTION & OPERATIONAL IMPRVSH 195 · | $764,311 | $672,280 | PRODIRT SERVICES, LLC | -12.0% | 6 |
| Jun 4, 2020 | 0910-00-113STP 2020(891) | Smith Tyler |
THERMOPLASTIC & PROFILE PAVEMENT MARKINGSVA · | $734,375 | $668,551 | STRIPE-A-ZONE, INC. | -9.0% | 4 |
| Jun 4, 2020 | 6354-88-001RMC - 635488001 | Hunt Paris |
ON CALL METAL BEAM GUARD FENCE REPAIRIH 30 · | $720,650 | $611,418 | CATOCON, INC. | -15.2% | 4 |
| Jun 4, 2020 | 0265-05-087C 265-5-87 | Bastrop Austin |
LANDSCAPE & IRRIGATIONSH 71 · | $643,730 | $592,932 | LEGACY ENERGY SERVICES | -7.9% | 4 |
| Jun 4, 2020 | 6360-75-001RMC - 636075001 | Hidalgo Pharr |
HOT POUR CRACK SEALIH 2 · | $475,505 | $530,042 | D & M CONTRACTORS, LLC | +11.5% | 2 |
| Jun 4, 2020 | 6355-82-001RMC - 635582001 | Coryell Waco |
BASE FAILURE PAVEMENT REPAIRUS 190 · | $903,711 | $527,889 | BIG CREEK CONSTRUCTION, LTD. | -41.6% | 3 |
| Jun 4, 2020 | 6359-49-001RMC - 635949001 | Jasper Beaumont |
METAL BEAM GUARD FENCE REPAIRSUS 69 · | $556,520 | $525,580 | ELITE CASTLE RESOURCES LLC | -5.6% | 1 |
| Jun 4, 2020 | 0160-04-051C 160-4-51 | Val Verde Laredo |
MILLED RUMBLE STRIPS EDGE LINE AND CENTER LINEUS 277 · | $602,520 | $524,312 | DOUBLE A CONTRACTING, L.P. | -13.0% | 5 |
| Jun 4, 2020 | 0914-00-427C 914-00-427 | Travis Austin |
LARGE SIGN REPLACEMENTVA · | $597,642 | $523,663 | BATTERSON, LLP | -12.4% | 5 |
| Jun 4, 2020 | 6355-76-001RMC - 635576001 | Bosque Waco |
BASE FAILURE PAVEMENT REPAIRFM 219 · | $1,037,076 | $488,477 | TEXAS MATERIALS GROUP, INC. | -52.9% | 4 |
| Jun 4, 2020 | 0432-02-096STP 2020(915)HES | Victoria Yoakum |
INSTALL SIDEWALKSSH 185 · | $509,918 | $469,931 | TI-ZACK CONCRETE, INC. | -7.8% | 5 |
| Jun 4, 2020 | 0903-28-070BR 2020(074) | Montague Wichita Falls |
REPLACE BRIDGE AND APPROACHESCR · | $459,084 | $443,571 | HODGES AND SON CONSTRUCTION COMPANY, INC. | -3.4% | 5 |
| Jun 4, 2020 | 6355-83-001RMC - 635583001 | Hamilton Waco |
BASE FAILURE PAVEMENT REPAIRUS 84 · | $598,163 | $429,199 | BIG CREEK CONSTRUCTION, LTD. | -28.2% | 4 |
| Jun 4, 2020 | 6360-05-001RMC - 636005001 | Dallas Dallas |
DRIFTWOOD REMOVALIH 20 · | $371,700 | $410,430 | DBI SERVICES, LLC | +10.4% | 4 |
| Jun 4, 2020 | 6360-10-001RMC - 636010001 | Fort Bend Houston |
FULL DEPTH CONCRETE REPAIRUS 59 · | $484,750 | $396,395 | ISI CONTRACTING, INC. | -18.2% | 2 |
| Jun 4, 2020 | 6360-23-001RMC - 636023001 | Waller Houston |
ASPHALT PAVEMENT REPAIRUS 290 · | $348,750 | $395,350 | MAIN LANE INDUSTRIES LTD. | +13.4% | 2 |
| Jun 4, 2020 | 6363-18-001RMC - 636318001 | Kerr San Antonio |
CLEANING AND SEALING CRACKSIH 10 · | $338,078 | $384,374 | D & M CONTRACTORS, LLC | +13.7% | 2 |
| Jun 4, 2020 | 0902-49-075STP 2020(492) | Erath Fort Worth |
LANDSCAPE DEVELOPMENTVA · | $397,761 | $370,983 | CENTRAL NORTH CONSTRUCTION, LLC | -6.7% | 3 |
| Jun 4, 2020 | 0342-01-099BR 2020(913) | Hidalgo Pharr |
BRIDGE MAINTENANCESH 107 · | $240,752 | $325,600 | VALLEY INFRASTRUCTURE, INC. | +35.2% | 3 |
| Jun 4, 2020 | 0365-01-051C 365-1-51 | Parker Fort Worth |
LANDSCAPE DEVELOPMENTSH 171 · | $360,037 | $321,472 | CENTRAL NORTH CONSTRUCTION, LLC | -10.7% | 2 |
| Jun 4, 2020 | 0008-14-133C 8-14-133 | Tarrant Fort Worth |
LANDSCAPE DEVELOPMENTIH 820 · | $318,458 | $236,887 | CENTRAL NORTH CONSTRUCTION, LLC | -25.6% | 4 |
| Jun 4, 2020 | 6364-15-001MMC - 636415001 | Henderson Tyler |
MATERIALS ONLY (PRE-PACKAGED CONCRETE)SL 7 · | $218,736 | $216,384 | AKA-MATERIALS | -1.1% | 3 |
| Jun 4, 2020 | 6363-12-001RMC - 636312001 | Gray Amarillo |
MOWING HIGHWAY RIGHT OF WAYIH 40 · | $212,926 | $207,986 | BERT WHITAKER | -2.3% | 1 |
| Jun 4, 2020 | 6363-11-001RMC - 636311001 | Oldham Amarillo |
MOWING HIGHWAY ROWIH 40 · | $199,102 | $187,123 | GORMAN OUTDOOR, INC. | -6.0% | 2 |
| Jun 4, 2020 | 2102-01-076C 2102-1-76 | Travis Austin |
LANDSCAPE & SCENIC ENHANCEMENTRM 2244 · | $157,144 | $179,997 | TIGHT LINE CONSTRUCTION, LLC | +14.5% | 2 |
| Jun 4, 2020 | 6364-14-001MMC - 636414001 | Garza Maintenance Division |
MATERIALS ONLY (PRE-PACKAGED CONCRETE)US 84 · | $197,904 | $165,558 | KLP COMMERCIAL, L.L.C. | -16.3% | 3 |
| Jun 4, 2020 | 0026-02-035STP 2020(914)HES | Fayette Yoakum |
INSTALL/UPGRADE ROADWAY LIGHTINGUS 90 · | $150,052 | $140,775 | ALLSTATE SIGNAL & CONSTRUCTION, LLC | -6.2% | 3 |
| Jun 4, 2020 | 6364-08-001MMC - 636408001 | Henderson Tyler |
MATERIALS ONLY (ASPPM PATCHING MATERIAL - BAGGED)SL 7 · | $442,400 | $111,440 | KLP COMMERCIAL, L.L.C. | -74.8% | 3 |
101–146 of 146‹ Prev
Source: TxDOT Bid Tabulations (data.texas.gov), which covers state and local lettings from the previous 24 months. Bid Potato keeps every month it has loaded, so history grows past that window. Totals are as read at the letting; on packaged proposals the low bid can be the whole package total. Confirm against TxDOT's official tabulations.