| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Apr 24, 2020 | 60D77 | CookDistrict 1 | Roadway Construction and ramp rehab. Includes replace. concrete deck, bearings expansion joint and wingwalls. Substructure will be repaired. Project 3,709 LF. , Project 3,709 LF. Roadway reconstruction and ramp bridge rehab. Replacement of concrete deck, bearings, expansion joint and wingwall. Substructure will be repaired. | — | Executed | Lorig Construction Company $4,711,922 · | ||
| Apr 24, 2020 | 60V40 | WillDistrict 1 | Intersection channelization and new traffic signal on US-6. (Maple Rd.) at Gougar Rd. Proposed intersection lighting. | — | Executed | Austin Tyler Construction, Inc. $2,663,060 · | ||
| Apr 24, 2020 | 60Y00 | CookDistrict 1 | Construction of the Intelligent Transportation System infrastructure including a new Comm. Hut, LED lighting for U/P expwys, retrofit of existing HMLTs with LED, and fiber optic cables for the Jane Byrne interchange corridor along I-90/94/290. | — | Executed | Meade Inc. $2,709,903 · | ||
| Apr 24, 2020 | 61G02 | KaneDistrict 1 | New construction/extension of Longmeadow Parkway from west of Sandbloom road to IL 25, and construction of a new bridge over Sandbloom Road in Carpentersville | — | Executed | Lake County Grading Company, LLC $23,531,420 · | ||
| Apr 24, 2020 | 61G06 | DuPageDistrict 1 | Construction of a PCC multi-use path, curb and gutter, culvert extension, storm sewer and pavement markings. Located on the east side of IL 83 from Bryn Mawr Avenue to Foster Avenue in Bensenville. | — | Executed | Alliance Contractors, Inc. $1,434,446 · | ||
| Apr 24, 2020 | 61G43 | McHenryDistrict 1 | Construction of a multi-use path adjacent to Reed Road from Vine Street to IL 47 in the Village of Huntley. | — | Executed | Martam Construction Incorporated $239,749 · | ||
| Apr 24, 2020 | 62A76 | CookDistrict 1 | 9,508 FT Construction and widening the Kennedy mainline Expwy NB from Roosevelt Rd. to Lake/Madison Sts, construction/rehab. of 10 ret. walls total, lighting, ITS, interstate resurfacing from the north. project limits to Ohio St through Hubbard's Cave. | — | Executed | Lorig Construction Company $56,078,988 · | ||
| Apr 24, 2020 | 62A77 | CookDistrict 1 | Construction and wideing the Kennedy mainline Expwy SB from Lake/Madison St. to Roosevelt Rd., rehab. of 3 exist. ret. walls, lighting, ITS, interstate resurfacing from the north limits to Ohio St. thru Hubbard's Cave. Construction of detention storage under the AIS. | — | Executed | Lorig Construction Company $43,795,682 · | ||
| Apr 24, 2020 | 62D36 | McHenryDistrict 1 | Project 14,023 LF. Pavement widening, pavement reconstruction, construction of a turnabout, curb and gutter, sidewalk, proposed drainage. replacement of a box culvert with three box culverts and two retaining walls. | — | Executed | Curran Contracting Company $9,727,727 · | ||
| Apr 24, 2020 | 62D42 | CookDistrict 1 | Bridge removal, roadway widening and sidewalk improvements on Pulaski Road at Ford City Drive in the City of Chicago. (SN 016-0750) | — | Executed | Dunnet Bay Construction Company $2,218,412 · | ||
| Apr 24, 2020 | 62F18 | CookDistrict 1 | Drainage improvement, and ADA improvements at the drainage ditch along the N side of FAU Fullerton Ave from Sarah St to Silver Creek Dr in Franklin Park. | — | Executed | Pan-Oceanic Engineering Co., Inc. $449,389 · | ||
| Apr 24, 2020 | 62G85 | WillDistrict 1 | Removal and replacement of the culvert, constructing a new culvert under a driveway, filling existing culvert under roadway, guardrail removal and replacement. (SN 099-0450,SN 099-0441) | — | Executed | Iroquois Paving Corporation $1,087,469 · | ||
| Apr 24, 2020 | 62H64 | CookDistrict 1 | Culvert headwall repair in the Village of Schiller Park. | — | Executed | Lakes & Rivers Contracting, Inc. $156,700 · | ||
| Apr 24, 2020 | 62H71 | CookDistrict 1 | Bridge repair project on IL-83 at Sanitary and Ship Canal. | — | Executed | Path Construction Company, Inc. $2,378,102 · | ||
| Apr 24, 2020 | 62H79 | WillDistrict 1 | Traffic Signal modernization and Traffic Signal Retroreflective Backplate Installation at various locations in the City of Joliet. | — | Rejected | John Burns Construction Company $2,648,889 · | ||
| Apr 24, 2020 | 62J17 | VariousDistrict 1 | Drainage improvements on routes IL 47, IL 31, IL 19, IL 58 and US 41 in the Village of Algonquin, Niles, Roselle, Skokie and Unincorpated McHenry County. | — | Executed | Martam Construction Incorporated $491,584 · | ||
| Apr 24, 2020 | 62J36 | KaneDistrict 1 | Bridge deck overlay and joint repairs on IL 72 over the Fox River. | — | Executed | ERA-Valdivia Contractors, Inc. $500,326 · | ||
| Apr 24, 2020 | 62J43 | WillDistrict 1 | Designed overlay and ADA improvements on US 52 from Eden Ln to E of Joyce Rd. | — | Executed | Austin Tyler Construction, Inc. $1,748,994 · | ||
| Apr 24, 2020 | 62J59 | CookDistrict 1 | Designed overlay including milling and resurfacing, installation of shoulder rumble strips, and other safety and drainage improvements along I-90 from IL 43 to I-94. | — | Executed | Plote Construction, Inc. $19,665,312 · | ||
| Apr 24, 2020 | 62J67 | CookDistrict 1 | Designed overlay and pedestrian ramps on US 41 from 31 ft SE of the centerline of Kedzie Ave to 44 ft N of the centerline of Foster Ave. | — | Executed | MAT Construction Leasing, Inc. $2,257,684 · | ||
| Apr 24, 2020 | 62J70 | CookDistrict 1 | SMART Overlay and ADA improvements on US 6 from IL-50 to E of I-294. | — | Executed | Iroquois Paving Corporation $1,256,078 · | ||
| Apr 24, 2020 | 62J80 | CookDistrict 1 | HMA Design Overlay of Touhy Ave from 240 ft W of the intersection of Lee St, E to 100 ft E of US-14. | — | Executed | Arrow Road Construction Co. $7,128,300 · | ||
| Apr 24, 2020 | 62J82 | CookDistrict 1 | Smart Overlay and ADA improvements on US 12 from IL 19 to N of US 20. | — | Executed | Plote Construction, Inc. $4,589,135 · | ||
| Apr 24, 2020 | 62J94 | KaneDistrict 1 | SMART overlay, ADA improvements, and milled rumble strips on IL 47 from IL 64 to Seavey Rd. The net length of this project is approximately 7.9 miles. | — | Executed | Builders Paving, LLC $2,288,000 · | ||
| Apr 24, 2020 | 62J96 | CookKaneDistrict 1 | Centerline joint repair and patching project on US 20 that starts at Plank Rd and extends E for 7.4 miles to a point approximately 80 ft W of the centerline of Shales Pkwy. | — | Executed | Geneva Construction Company $1,396,008 · | ||
| Apr 24, 2020 | 62K06 | VariousDistrict 1 | Landscape repair work at various expressway and primary locations in District 1. | — | Executed | McGinty Bros., Inc. $546,171 · | ||
| Apr 24, 2020 | 62K21 | CookDistrict 1 | Bridge Deck Overlay and Bridge Repairs on I-57 over Little Calumet River in Dixmoor. | — | Executed | Dunnet Bay Construction Company $2,168,250 · | ||
| Apr 24, 2020 | 62K22 | DuPageWillDistrict 1 | ADA improvements along various state routes in Dupage and Will Counties. | — | Executed | Davis Concrete Construction Co. $558,989 · | ||
| Apr 24, 2020 | 62K23 | CookDistrict 1 | Bridge repairs and improvements on various bridges over I-290 from 25th Ave to Ridgeland Ave. | — | Executed | Lorig Construction Company $1,727,469 · | ||
| Apr 24, 2020 | 62K31 | CookDistrict 1 | Bridge repair, bridge joint repair, and bridge deck overlay on the structure carrying Ashland Ave at Cal Sag Channel in Blue Island. | — | Executed | Rausch Infrastructure, LLC $1,597,411 · | ||
| Apr 24, 2020 | 62K34 | WillDistrict 1 | Bridge deck repairs including full and partial depth bridge deck patching, and the removal of existing asphalt over the patches on I-80 from Center St to Rowel Ave in Joliet. | — | Executed | D. Construction, Inc. $607,895 · | ||
| Apr 24, 2020 | 62K50 | WillDistrict 1 | Bridge deck repairs and shoulder reconstruction on I-55 over IL 53, Joliet Rd, and S Madison St in Bolingbrook and Burr Ridge. | — | Executed | K-Five Construction Corporation $3,075,389 · | ||
| Apr 24, 2020 | 62K54 | WillDistrict 1 | Pavement patching including asphalt surface removal, HMA surface course, pavement patching, and placement of pavement markings on I-55 from S of I-80 to S of Weber Rd. | — | Executed | Gallagher Asphalt Corporation $4,277,656 · | ||
| Apr 24, 2020 | 62K57 | McHenryDistrict 1 | Light tower and foundation removal, install new light poles, metal foundations, LED luminaires, conduits, cables, excavation and site restorations at US 14 at IL 31 in Crystal Lake. | — | Executed | Hecker and Company, Inc. $679,721 · | ||
| Apr 24, 2020 | 64J28 | Rock IslandDistrict 2 | 2.44 miles cold milling, pavement patching, and HMA resurfacing in Carbon Cliff . | — | Executed | Valley Construction Co. $3,379,769 · | ||
| Apr 24, 2020 | 64M07 | WinnebagoDistrict 2 | 1.49 miles of HMA resurfacing and ADA improvements on BUS Rte US 20 (West State Street) from Merdian Rd to Springfield Ave in Rockford. | — | Executed | Rock Road Companies, Inc. $1,859,375 · | ||
| Apr 24, 2020 | 64M42 | WhitesideDistrict 2 | Cold milling, pavement patching, and HMA resurfacing on US 30 from French Creek E of Morrison to Emerson Rd. | — | Executed | Civil Constructors, Inc. d/b/a/ Helm Civil $2,995,862 · | ||
| Apr 24, 2020 | 64M45 | LeeDistrict 2 | Cold milling, pavement patching, and HMA resurfacing on IL 26 from Bloody Gulch Rd in Dixon to US 30. | — | Executed | Civil Constructors, Inc. d/b/a/ Helm Civil $2,479,194 · | ||
| Apr 24, 2020 | 64N35 | OgleDistrict 2 | Cold milling, pavement patching, and HMA resurfacing on IL 2 from Pines Rd to Jefferson St in Oregon. | — | Executed | Martin & Company Excavating $356,027 · | ||
| Apr 24, 2020 | 64N36 | BooneWinnebagoDistrict 2 | Dowel bar retrofit, pavement patching, profile diamond grind pavement, and pavement marking from Buckley Dr in Rockford to 0.4 mile E of Shaw Rd on US BUS 20. | — | Executed | Martam Construction Incorporated $6,472,317 · | ||
| Apr 24, 2020 | 64N58 | StephensonDistrict 2 | Cold milling, pavement patching, and HMA resurfacing on eastbound US 20 0.6 mile W of IL 26 to IL 75. | — | Executed | Civil Constructors, Inc. d/b/a/ Helm Civil $1,178,254 · | ||
| Apr 24, 2020 | 64N59 | StephensonDistrict 2 | Cold milling, pavement patching, and HMA resurfacing on westbound US 20 from 0.6 mile W of IL 26 to 0.6 mile W of Springfield Rd. | — | Executed | Civil Constructors, Inc. d/b/a/ Helm Civil $1,375,356 · | ||
| Apr 24, 2020 | 64P10 | WinnebagoDistrict 2 | Microsilica concrete overlay and deck patching on SN 101-0166 carrying US 20 WB over Grove Creek. | — | Executed | Civil Constructors, Inc. d/b/a/ Helm Civil $251,143 · | ||
| Apr 24, 2020 | 64P32 | VariousDistrict 2 | Maintain and service all Intelligent Transportation System equipment located in the Department's Districts 2 and 3 to ensure the safety of the motoring public. | — | Executed | Meade Inc. $147,964 · | ||
| Apr 24, 2020 | 66968 | BureauDistrict 3 | 3P milling and resurfacing on FAP 613 (US 34) from Henry County Line to 1200N Rd in Bureau County. | — | Executed | Advanced Asphalt Company $2,572,903 · | ||
| Apr 24, 2020 | 66A87 | LivingstonDistrict 3 | 7.27 miles of 3P milling and resurfacing on IL 116 from 0.7 mile E of IL 47 in Saunemin to W of Cullom. | — | Executed | Kankakee Valley Construction Company, Inc. $3,700,015 · | ||
| Apr 24, 2020 | 66B75 | IroquoisKankakeeDistrict 3 | Milling and resurfacing 3.75" of HMA binder and surface on the mainline (3P Designed Overlay) with guardrail upgrades and drainage improvements. It begins from 0.2 mile S of I-57 to IL 79. | — | Executed | Iroquois Paving Corporation $7,393,021 · | ||
| Apr 24, 2020 | 66B80 | LivingstonDistrict 3 | 3P milling and resurfacing of 3.75" with guardrail replacement from E city limits of Cornell to IL 116 in Pontiac. | — | Executed | Kankakee Valley Construction Company, Inc. $6,285,284 · | ||
| Apr 24, 2020 | 66D56 | LivingstonDistrict 3 | 3P milling and resurfacing (Designed Overlay) from IL 18 to West Fork Mazon River, 1.4 miles W of I-55. | — | Executed | Kankakee Valley Construction Company, Inc. $5,416,536 · | ||
| Apr 24, 2020 | 66E15 | FordIroquoisDistrict 3 | 7.18 miles of milling and resurfacing 2.5" of HMA on IL 54 from IL 115 in Roberts to Spring Creek and updating guardrail at 2 structures. | — | Executed | Iroquois Paving Corporation $2,417,273 · | ||
| Apr 24, 2020 | 66J41 | DeKalbDistrict 3 | Milling and resurfacing 2.75" on mainline pavement and parking located mainly on IL 23 from Sycamore and ending in Genoa. ADA improvements, guardrail updates , and minor drainage work are also included. | — | Executed | Curran Contracting Company $3,661,661 · | ||
| Apr 24, 2020 | 66J63 | KankakeeDistrict 3 | 3.069 miles of milling and resurfacing from 0.1 mile N of Armour Rd in Bourbonnais to IL 17 in Kankakee. | — | Executed | Gallagher Asphalt Corporation $4,614,478 · | ||
| Apr 24, 2020 | 66J73 | DeKalbDistrict 3 | 3P milling and resurfacing (Standard Overlay) on SBI 23 from Coltonville Rd to Highland Dr in Sycamore. | — | Rejected | Herbig Blacktop Construction $261,874 · | ||
| Apr 24, 2020 | 66K30 | BureauDistrict 3 | 5.76 miles of SMART overlay consisting of milling and resurfacing of 2" of HMA and additional ADA, guardrail, and drainage improvements from E of IL 40 to Hazelwood Dr in Wyanet. | — | Executed | Advanced Asphalt Company $1,697,790 · | ||
| Apr 24, 2020 | 66K45 | LaSalleDistrict 3 | 3P milling and resurfacing (designed overlay) and ADA from Bureau County Line to IL 251 in Mendota. | — | Executed | Advanced Asphalt Company $1,104,965 · | ||
| Apr 24, 2020 | 66K58 | BureauDistrict 3 | Milling 3" and resurfacing 3.75" on the first mile, the rest of the project will be milled and resurfaced with 3.75" of HMA. The city of Princeton will participate with milling and resurfacing the parking lanes and ADA improvements. Minor drainage improvements are included. The project length is 1.34 miles. | — | Executed | Advanced Asphalt Company $967,303 · | ||
| Apr 24, 2020 | 66K72 | FordDistrict 3 | 4.15 miles of 3.75" HMA milling and resurfacing with spot guardrail updating and culvert cleaning on IL 9 from the McLean County Line to just W of IL 47 in Gibson City. | — | Executed | Cross Construction, Inc. $2,121,820 · | ||
| Apr 24, 2020 | 66K92 | BureauDistrict 3 | Furnishing and installing stone dumped riprap to armor existing foreslope erosion on NB I-180 0.2 mile S of TR 281 (SN 006-0126). | — | Executed | D. Construction, Inc. $52,700 · | ||
| Apr 24, 2020 | 68953 | FultonDistrict 4 | 2.88 miles of HMA cold-in-place, milling and resurfacing along US Rte 24 in Lewistown with minor drainage work and ADA requirements. | — | Executed | Gunther Construction, a div of UCM, Inc. $2,661,940 · | ||
| Apr 24, 2020 | 68A81 | PeoriaDistrict 4 | Resurfacing on IL 29 from 0.2 mile S of Cloverdale Rd in Chillicothe to Dickison Run Creek, N of IL 6 in Peoria County. | — | Executed | Advanced Asphalt Company $9,418,655 · | ||
| Apr 24, 2020 | 68C92 | PeoriaDistrict 4 | Intersection improvement at IL Rte 40 and Lake Ave in Peoria. (Offset left turn lanes.) | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $915,345 · | ||
| Apr 24, 2020 | 68D41 | KnoxDistrict 4 | Replacement of both structures carrying I-74 over French Creek, Class B patching, variable depth milling, placement of HMA, HMA shoulders, and placement of pavement markings in Knox County. | — | Executed | Stark Excavating, Inc. $4,105,900 · | ||
| Apr 24, 2020 | 68E88 | PeoriaDistrict 4 | Repair to ramps on I-474 at Airport Rd and US Rte 24 interchanges in Peoria. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $476,329 · | ||
| Apr 24, 2020 | 68E90 | VariousDistrict 4 | Bridge deck sealing on various bridges. | — | Executed | M & M Concrete, Inc. $236,989 · | ||
| Apr 24, 2020 | 68F01 | FultonDistrict 4 | 4 miles of microsurfacing on US 24 from the eastern city limits of Astoria to west of Izaak Walton Rd. | — | Executed | Microsurfacing Contractors, LLC, a Division of Byrne and Jones Holding Company $272,635 · | ||
| Apr 24, 2020 | 68F04 | VariousDistrict 4 | Pavement markings on various routes in various counties. | — | Executed | Varsity Striping & Construction Co. $245,934 · | ||
| Apr 24, 2020 | 68F16 | McDonoughWarrenDistrict 4 | 8 miles of microsurfacing on IL 110/US 67 from 0.4 mile S of N 2100 Rd to N of 40th Ave in Warren and McDonough Counties. | — | Executed | Microsurfacing Contractors, LLC, a Division of Byrne and Jones Holding Company $826,923 · | ||
| Apr 24, 2020 | 68F20 | PeoriaTazewellDistrict 4 | Replacement of traffic signal mast arms at various locations in Peoria and Tazewell Counties. | — | Executed | Oberlander Electric Co. $374,200 · | ||
| Apr 24, 2020 | 68F22 | McDonoughDistrict 4 | Resurfacing on IL 61 from IL 336 to CH 24 in Colmar. | — | Executed | Gunther Construction, a div of UCM, Inc. $2,345,362 · | ||
| Apr 24, 2020 | 68F25 | McDonoughDistrict 4 | 10.5 miles of microsurfacing on US 136/IL 336 from the Hancock County Line to IL 336; IL 110/IL 336 from US 136 W to 0.5 mile S of US 136, W of Macomb. | — | Executed | Microsurfacing Contractors, LLC, a Division of Byrne and Jones Holding Company $1,210,945 · | ||
| Apr 24, 2020 | 68F42 | PeoriaDistrict 4 | Ramp metering along the entrance ramp from Fayette St to Eastbound I-74 in Peoria. | — | Executed | Laser Electric, Inc. $174,042 · | ||
| Apr 24, 2020 | 68F48 | WoodfordDistrict 4 | Bridge painting along the I-39 corridor in Woodford County on SNs 102-0058, 102-0059, 102-0060, 1020061, and 1020062. | — | Executed | ERA-Valdivia Contractors, Inc. $1,367,875 · | ||
| Apr 24, 2020 | 68F56 | VariousDistrict 4 | Light pole replacement, luminaire replacement, and miscellaneous electrical work at various locations. | — | Executed | Laser Electric, Inc. $191,438 · | ||
| Apr 24, 2020 | 70B38 | ChampaignDistrict 5 | Bridge replacements under mattis ave. NW of Champaign. | — | Executed | Stark Excavating, Inc. $20,849,840 · | ||
| Apr 24, 2020 | 70B98 | ChampaignDistrict 5 | Bridge replacement under US 150 NW of Champaign. | — | Executed | Stark Excavating, Inc. $7,645,546 · | ||
| Apr 24, 2020 | 70D63 | ChampaignDistrict 5 | 321.6 ft of bridge deck repairs on SN 010-0056 carrying IL 47 over I-72. | — | Executed | Stark Excavating, Inc. $714,776 · | ||
| Apr 24, 2020 | 70D65 | McLeanDistrict 5 | Bridge deck overlay of FAI 39 from 2100 N to 2200 N at Hudson. | — | Executed | Stark Excavating, Inc. $3,960,429 · | ||
| Apr 24, 2020 | 70D73 | McLeanDistrict 5 | Rest area improvement at Funks Grove Rest Area. | — | Executed | Otto Baum Company, Inc. $1,123,868 · | ||
| Apr 24, 2020 | 70D80 | ChampaignPiattDistrict 5 | Driving lane inlay on FAI 74 approximately 1.3 miles W of Champaign County Line to 0.2 mile W of IL Rte 47 in Mahomet. | — | Executed | Open Road Paving Company LLC $4,265,475 · | ||
| Apr 24, 2020 | 70E11 | PiattDistrict 5 | 7.288 miles of Bituminous Surface Treatment A-1 on IL 105 from SCL of Bement. | — | Executed | Earl Walker Company, Inc. $308,809 · | ||
| Apr 24, 2020 | 70E15 | McLeanDistrict 5 | Bridge joint replace/repair, bridge deck repairs to SN 057-0022 and 057-0023. | — | Executed | Stark Excavating, Inc. $773,590 · | ||
| Apr 24, 2020 | 70E28 | EdgarDistrict 5 | 0.041 Mile of pavement removal, earth excavation, and jointed PCC pavement at the sign shop parking lot in Paris. | — | Executed | Feutz Contractors, Inc. $383,735 · | ||
| Apr 24, 2020 | 70E40 | DeWittMcLeanDistrict 5 | 25.55 miles of patching Macon/DeWitt to 2.9 miles S of I-74/US 51 interchange. | — | Executed | Beniach Construction Co., Inc. $446,314 · | ||
| Apr 24, 2020 | 70E60 | VariousDistrict 5 | Districtwide smart work zone technology. | — | Executed | ROADSAFE TRAFFIC SYSTEMS, INC. $555,000 · | ||
| Apr 24, 2020 | 72E00 | LoganDistrict 6 | 4.8 miles of milling, resurfacing, shoulder reconstruction and guardrail on US 136 from 0.3 miles west of I-155 to East Union Road. Also includes microsilica overlay, median replacement, preformed joint strip seal and formed concrete repair on SN 054-0079. | — | Executed | Truman L. Flatt & Sons Co., Inc. $4,546,146 · | ||
| Apr 24, 2020 | 72E23 | LoganDistrict 6 | 3 miles of resurfacing on I-155 from 2 miles south of US 136 to the Tazwell County line. Also includes bridge repair on SN 054-0078 carrying Emden Road over I-155. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $7,406,232 · | ||
| Apr 24, 2020 | 72G46 | SangamonDistrict 6 | 4.9 miles of milling, resurfacing, bridge repair and bridge joint repair on I-55 from north of the Glenarm interchange to 0.2 miles south of the Lake Springfield Bridge, and on East Lakeshore Drive from west of Hunt Road to 0.6 miles north of Chatham Road. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $15,744,901 · | ||
| Apr 24, 2020 | 72G70 | ChristianDistrict 6 | 10.6 miles of designed overlay and ADA improvements on IL 29 from south of Velma Road, south of Taylorville, to north of Magnolia Street in Pana. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $5,337,307 · | ||
| Apr 24, 2020 | 72H51 | SangamonDistrict 6 | New bridge decks and slope wall repairs on I-72 over Wabash Avenue and on I-72 over NSRR in Springfield. (SN 084-0127, 084-0128, 084-0148, 084-0149) | — | Executed | Sangamo Construction Company $5,941,551 · | ||
| Apr 24, 2020 | 72K45 | MontgomeryDistrict 6 | ADA improvements at various locations along IL 16 and IL 127 in Hillsboro. | — | Executed | Stutz Excavating, Inc. $344,460 · | ||
| Apr 24, 2020 | 72L45 | MacoupinDistrict 6 | Joint replacement and deck overlay on SN 059-0053 carrying the Shipman Blacktop over Hurricane Creek, 9.6 miles north of IL 16. | — | Executed | Stutz Excavating, Inc. $439,641 · | ||
| Apr 24, 2020 | 72L49 | MacoupinDistrict 6 | Patching on various routes in Macoupin County. | — | Executed | Kinney Contractors, Inc. $487,519 · | ||
| Apr 24, 2020 | 72L52 | ChristianDistrict 6 | Milling, resurfacing, addition of 4- HMA and 4- aggregate shoulders, improvement of existing entrances and guardrail on US 51 / IL 16 in the City of Pana. | — | Executed | Truman L. Flatt & Sons Co., Inc. $991,232 · | ||
| Apr 24, 2020 | 72L60 | MorganScottDistrict 6 | Culvert replacement on Old US 36 from east of the Scott / Morgan County line to east of Jacksonville. | — | Executed | Lee Hood d/b/a Hood Demolition & Excavation $114,850 · | ||
| Apr 24, 2020 | 72L61 | BrownPikeDistrict 6 | Culvert replacement from 1.8 miles north of the Brown / Pike County line to 0.5 miles south of the Brown / Pike County line. | — | Executed | Lee Hood d/b/a Hood Demolition & Excavation $79,521 · | ||
| Apr 24, 2020 | 72L68 | PikeDistrict 6 | Drainage improvements and patching on IL 106 from IL 96 to 0.1 miles east of IL 96. | — | Executed | County Contractors, Inc. $68,360 · | ||
| Apr 24, 2020 | 72L69 | MacoupinDistrict 6 | Deck slab repair, approach slab repair and expansion joints repair on SN 059-0013 carrying IL 111 over Lick Creek and SN 059-0014 carrying IL 111 over Bear Creek. | — | Executed | RCS Construction, Inc. $179,405 · | ||
| Apr 24, 2020 | 72L70 | SchuylerDistrict 6 | Deck repairs on SN 085-0004 carrying IL 103 over Town Branch and SN 085-0005 carrying IL 103 over Crane Creek. | — | Executed | County Contractors, Inc. $268,992 · | ||
| Apr 24, 2020 | 72L71 | SangamonDistrict 6 | Deck patching and joint repair on SN 084-0042 carrying IL 29 NB over South Fork Sangamon River, 2.4 miles east of I-55. | — | Executed | Sangamo Construction Company $170,176 · | ||
| Apr 24, 2020 | 74542 | CumberlandDistrict 7 | 8.3 miles of patching, milling, resurfacing, aggregate wedge shoulders and culvert replacement on US 40 in Greenup. | — | Executed | Howell Paving, Inc. $5,394,688 · |
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.