2018-063-CR&D
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Iroquois Paving Corporation Low bidder | $1,087,469 | ||
| 2 | P. T. Ferro Construction Co. | $1,167,543 | +7.4% | |
| 3 | D. Construction, Inc. | $1,240,789 | +14.1% | |
| 4 | Austin Tyler Construction, Inc. | $1,324,885 | +21.8% | |
| 5 | Copenhaver Construction, Inc. | $1,514,381 | +39.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Iroquois Paving… | #2 P. T. Ferro Con… | #3 D. Construction… | #4 Austin Tyler Co… | #5 Copenhaver Cons… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0326898 | CENTERLN RUM STRIP 16 | 1,123 | FOOT | $3.30 | $1.55 | $1.02 | $1.70 | $6.00 | |
| 2 | X0900064 | MEMBR WTRPR SYS B STR | 120 | SQ YD | $67.00 | $64.00 | $50.00 | $39.00 | $73.00 | |
| 3 | X0900075 | COFFERDAM TYP 1 IS WW | 1 | EACH | $0.0100 | $1.00 | $0.0100 | $30,000.00 | $45,000.00 | |
| 4 | X2502024 | SEEDING CL 4B MOD | 1.1 | ACRE | $3,900.00 | $3,877.00 | $4,264.70 | $4,300.00 | $5,000.00 | |
| 5 | X2840105 | GABION REMOVAL | 29 | CU YD | $50.00 | $75.00 | $50.00 | $135.00 | $100.00 | |
| 6 | X6330725 | SPBGR (SHORT RADIUS) | 60 | FOOT | $32.00 | $32.00 | $35.20 | $35.00 | $60.00 | |
| 7 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $15,400.00 | $16,000.00 | $20,000.00 | $40,000.00 | $113,000.00 | |
| 8 | X7030005 | TEMP PAVT MKING REMOV | 1,476 | SQ FT | $1.00 | $0.0100 | $2.25 | $0.3300 | $0.5000 | |
| 9 | X7800815 | HS THPL PM LN 4 | 1,293 | FOOT | $3.50 | $3.40 | $3.74 | $3.85 | $6.00 | |
| 10 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $20,000.00 | $11,565.00 | $20,000.00 | $15,000.00 | $26,000.00 | |
| 11 | Z0030850 | TEMP INFO SIGNING | 103 | SQ FT | $16.00 | $15.00 | $25.00 | $15.00 | $20.00 | |
| 12 | Z0033700 | LONG JOINT SEALANT | 1,334 | FOOT | $7.50 | $5.65 | $5.26 | $5.50 | $8.00 | |
| 13 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 14 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | |
| 15 | 20100110 | TREE REMOV 6-15 | 14 | UNIT | $100.00 | $100.00 | $110.00 | $100.00 | $60.00 | |
| 16 | 20101100 | TREE TRUNK PROTECTION | 3 | EACH | $100.00 | $400.00 | $137.50 | $100.00 | $40.00 | |
| 17 | 20101200 | TREE ROOT PRUNING | 3 | EACH | $125.00 | $400.00 | $110.00 | $100.00 | $40.00 | |
| 18 | 20200100 | EARTH EXCAVATION | 3,539 | CU YD | $25.00 | $25.00 | $25.00 | $30.00 | $27.00 | |
| 19 | 20800150 | TRENCH BACKFILL | 243 | CU YD | $30.00 | $40.00 | $45.00 | $49.00 | $30.00 | |
| 20 | 21001000 | GEOTECH FAB F/GR STAB | 45 | SQ YD | $2.00 | $3.00 | $7.50 | $6.00 | $5.00 | |
| 21 | 21101505 | TOPSOIL EXC & PLAC | 972 | CU YD | $20.00 | $20.00 | $17.50 | $27.00 | $12.00 | |
| 22 | 21400100 | GRADING & SHAP DITCH | 357 | FOOT | $6.50 | $0.0100 | $12.00 | $8.75 | $15.00 | |
| 23 | 25000300 | SEEDING CL 3 | 2 | ACRE | $2,405.00 | $2,405.00 | $2,645.50 | $2,600.00 | $4,000.00 | |
| 24 | 25000400 | NITROGEN FERT NUTR | 159 | POUND | $3.00 | $3.00 | $3.30 | $3.00 | $1.00 | |
| 25 | 25000600 | POTASSIUM FERT NUTR | 159 | POUND | $3.00 | $3.00 | $3.30 | $3.00 | $1.00 | |
| 26 | 25100115 | MULCH METHOD 2 | 2 | ACRE | $1,800.00 | $1,800.00 | $1,980.00 | $1,800.00 | $2,500.00 | |
| 27 | 25100630 | EROSION CONTR BLANKET | 8,911 | SQ YD | $0.9000 | $0.9000 | $0.9900 | $0.9000 | $2.00 | |
| 28 | 28000250 | TEMP EROS CONTR SEED | 325 | POUND | $5.00 | $5.00 | $5.50 | $5.00 | $0.0100 | |
| 29 | 28000305 | TEMP DITCH CHECKS | 220 | FOOT | $8.80 | $8.80 | $9.68 | $9.00 | $15.00 | |
| 30 | 28000315 | AGG DITCH CHECKS | 38 | TON | $25.00 | $85.00 | $35.00 | $130.00 | $70.00 | |
| 31 | 28000400 | PERIMETER EROS BAR | 4,442 | FOOT | $2.00 | $2.00 | $2.20 | $2.00 | $2.00 | |
| 32 | 28001100 | TEMP EROS CONTR BLANK | 17,822 | SQ YD | $0.8000 | $0.8000 | $0.8800 | $0.0100 | $0.0100 | |
| 33 | 28100107 | STONE RIPRAP CL A4 | 232 | SQ YD | $65.00 | $55.00 | $60.00 | $65.00 | $90.00 | |
| 34 | 28200200 | FILTER FABRIC | 232 | SQ YD | $4.00 | $3.50 | $4.00 | $3.50 | $3.00 | |
| 35 | 30300001 | AGG SUBGRADE IMPROVE | 60 | CU YD | $45.00 | $60.00 | $90.00 | $49.00 | $45.00 | |
| 36 | 30300112 | AGG SUBGRADE IMPR 12 | 3,009 | SQ YD | $17.00 | $13.00 | $17.00 | $17.00 | $14.00 | |
| 37 | 31101900 | SUB GRAN MAT C | 2 | TON | $25.00 | $32.00 | $100.00 | $375.00 | $120.00 | |
| 38 | 35101500 | AGG BASE CSE B | 23 | CU YD | $65.00 | $62.00 | $60.00 | $155.00 | $45.00 | |
| 39 | 35501308 | HMA BASE CSE 6 | 58 | SQ YD | $40.50 | $125.00 | $38.00 | $44.00 | $130.00 | |
| 40 | 35501315 | HMA BASE CSE 7 3/4 | 208 | SQ YD | $41.00 | $50.00 | $48.00 | $37.00 | $95.00 | |
| 41 | 35600707 | HMA BC WID 7 3/4 | 394 | SQ YD | $42.00 | $50.00 | $48.00 | $38.00 | $61.00 | |
| 42 | 40201000 | AGGREGATE-TEMP ACCESS | 24 | TON | $15.00 | $1.00 | $30.00 | $150.00 | $40.00 | |
| 43 | 40600290 | BIT MATLS TACK CT | 4,317 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $1.00 | |
| 44 | 40600982 | HMA SURF REM BUTT JT | 11 | SQ YD | $0.0100 | $50.00 | $50.00 | $50.00 | $59.00 | |
| 45 | 40603085 | HMA BC IL-19.0 N70 | 191 | TON | $72.50 | $80.00 | $85.00 | $66.00 | $115.00 | |
| 46 | 40603200 | P HMA BC IL-4.75 N50 | 176 | TON | $110.00 | $100.00 | $90.00 | $82.00 | $165.00 | |
| 47 | 40604060 | HMA SC IL-9.5 D N50 | 7 | TON | $70.00 | $110.00 | $150.00 | $163.00 | $320.00 | |
| 48 | 40604062 | HMA SC IL-9.5 D N70 | 294 | TON | $70.00 | $80.00 | $90.00 | $73.00 | $111.00 | |
| 49 | 44000100 | PAVEMENT REM | 432 | SQ YD | $25.00 | $30.00 | $12.00 | $26.00 | $15.00 | |
| 50 | 44000152 | HMA SURF REM 3/4 | 1,387 | SQ YD | $1.25 | $2.75 | $5.00 | $1.25 | $2.00 | |
| 51 | 44000158 | HMA SURF REM 2 1/4 | 2,850 | SQ YD | $3.00 | $3.25 | $5.00 | $2.50 | $4.50 | |
| 52 | 48102100 | AGG WEDGE SHLD TYPE B | 42 | TON | $27.00 | $55.00 | $35.00 | $80.00 | $60.00 | |
| 53 | 48203029 | HMA SHOULDERS 8 | 1,943 | SQ YD | $36.50 | $40.00 | $36.00 | $35.00 | $44.00 | |
| 54 | 50100100 | REM EXIST STRUCT | 1 | EACH | $10,000.00 | $15,000.00 | $20,000.00 | $8,000.00 | $25,000.00 | |
| 55 | 50102400 | CONC REM | 19.7 | CU YD | $400.00 | $225.00 | $500.00 | $235.00 | $250.00 | |
| 56 | 50105220 | PIPE CULVERT REMOV | 75 | FOOT | $30.00 | $35.00 | $30.00 | $45.00 | $110.00 | |
| 57 | 50200100 | STRUCTURE EXCAVATION | 185 | CU YD | $35.00 | $28.00 | $50.00 | $55.00 | $65.00 | |
| 58 | 50200450 | REM/DISP UNS MATL-STR | 134 | CU YD | $45.00 | $30.00 | $60.00 | $40.00 | $70.00 | |
| 59 | 50300225 | CONC STRUCT | 12.9 | CU YD | $1,350.00 | $1,200.00 | $1,300.00 | $2,800.00 | $1,700.00 | |
| 60 | 50500505 | STUD SHEAR CONNECTORS | 234 | EACH | $10.00 | $22.50 | $10.00 | $12.00 | $12.00 | |
| 61 | 50800105 | REINFORCEMENT BARS | 12,790 | POUND | $2.25 | $1.50 | $2.20 | $1.58 | $2.50 | |
| 62 | 50800205 | REINF BARS, EPOXY CTD | 10,590 | POUND | $2.25 | $1.60 | $2.20 | $1.68 | $2.60 | |
| 63 | 51500100 | NAME PLATES | 1 | EACH | $600.00 | $500.00 | $600.00 | $500.00 | $900.00 | |
| 64 | 52200010 | TEMP SHT PILING | 730 | SQ FT | $0.0100 | $30.00 | $25.00 | $16.00 | $47.00 | |
| 65 | 52200015 | PERM SHT PILING | 2,201 | SQ FT | $30.00 | $20.00 | $30.00 | $37.00 | $40.00 | |
| 66 | 54003000 | CONC BOX CUL | 106.6 | CU YD | $850.00 | $1,700.00 | $900.00 | $1,850.00 | $900.00 | |
| 67 | 542A0235 | P CUL CL A 1 30 | 44 | FOOT | $60.00 | $100.00 | $105.00 | $88.00 | $170.00 | |
| 68 | 5422C012 | P CUL CL C 2 12 TEMP | 18 | FOOT | $13.25 | $115.00 | $60.00 | $65.00 | $155.00 | |
| 69 | 5422C036 | P CUL CL C 2 36 TEMP | 30 | FOOT | $16.00 | $135.00 | $120.00 | $98.00 | $200.00 | |
| 70 | 54260315 | TRVRS PIPE GRT CON ES | 26 | FOOT | $105.00 | $150.00 | $100.00 | $98.00 | $210.00 | |
| 71 | 54261330 | CONC ES 542001 30 1:3 | 1 | EACH | $3,225.00 | $3,800.00 | $5,000.00 | $3,800.00 | $5,500.00 | |
| 72 | 54261430 | CONC ES 542001 30 1:4 | 1 | EACH | $4,000.00 | $4,500.00 | $5,400.00 | $4,500.00 | $6,200.00 | |
| 73 | 58600101 | GRANULAR BACKFILL STR | 83 | CU YD | $55.00 | $35.00 | $55.00 | $69.00 | $55.00 | |
| 74 | 58700300 | CONCRETE SEALER | 704 | SQ FT | $2.00 | $1.50 | $2.00 | $3.00 | $1.00 | |
| 75 | 59100100 | GEOCOMPOSITE WALL DR | 129 | SQ YD | $25.00 | $18.00 | $30.00 | $20.00 | $20.00 | |
| 76 | 59300100 | CONTR LOW-STRENG MATL | 12 | CU YD | $300.00 | $300.00 | $200.00 | $450.00 | $300.00 | |
| 77 | 63000001 | SPBGR TY A 6FT POSTS | 1,645 | FOOT | $23.89 | $23.89 | $26.28 | $26.00 | $26.00 | |
| 78 | 63000003 | SPBGR TY A 9FT POSTS | 100 | FOOT | $28.06 | $28.06 | $30.87 | $31.00 | $39.00 | |
| 79 | 63000030 | SPGR ATT TO CULVERT | 32 | FOOT | $18.04 | $89.96 | $98.96 | $100.00 | $280.00 | |
| 80 | 63100167 | TR BAR TRM T1 SPL TAN | 7 | EACH | $3,364.72 | $2,941.17 | $3,701.19 | $3,700.00 | $3,400.00 | |
| 81 | 63200310 | GUARDRAIL REMOV | 1,529 | FOOT | $6.01 | $5.03 | $6.61 | $6.00 | $6.00 | |
| 82 | 64200108 | SHOULDER RUM STRIP 8 | 2,294 | FOOT | $3.50 | $1.45 | $1.02 | $1.30 | $6.00 | |
| 83 | 66900200 | NON SPL WASTE DISPOSL | 1,960 | CU YD | $55.00 | $66.00 | $75.00 | $55.00 | $65.00 | |
| 84 | 66900530 | SOIL DISPOSAL ANALY | 3 | EACH | $1,450.00 | $1,800.00 | $1,350.00 | $1,500.00 | $1,600.00 | |
| 85 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $2,600.00 | $2,950.00 | $2,500.00 | $3,000.00 | $3,200.00 | |
| 86 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $900.00 | $900.00 | $2,500.00 | $2,000.00 | $2,600.00 | |
| 87 | 66901006 | REG SUB MON | 15 | CAL DA | $680.00 | $680.00 | $800.00 | $0.0100 | $1,000.00 | |
| 88 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $2,750.00 | $1.00 | $3,500.00 | $2,800.00 | $1,000.00 | |
| 89 | 67100100 | MOBILIZATION | 1 | L SUM | $45,000.00 | $70,000.00 | $65,000.00 | $78,000.00 | $85,700.00 | |
| 90 | 70300100 | SHORT TERM PAVT MKING | 440 | FOOT | $1.00 | $0.0100 | $12.60 | $1.00 | $2.00 | |
| 91 | 70300150 | SHRT TRM PAVT MK REM | 440 | SQ FT | $1.00 | $0.0100 | $8.40 | $1.00 | $2.00 | |
| 92 | 70300904 | PAVT MARK TAPE T4 4 | 4,283 | FOOT | $1.35 | $0.0100 | $1.05 | $1.00 | $1.20 | |
| 93 | 70300924 | PAVT MARK TAPE T4 24 | 24 | FOOT | $7.50 | $0.0100 | $6.27 | $6.00 | $8.00 | |
| 94 | 72501000 | TERMINAL MARKER - DA | 7 | EACH | $45.43 | $45.43 | $49.97 | $50.00 | $50.00 | |
| 95 | 78000200 | THPL PVT MK LINE 4 | 3,490 | FOOT | $2.00 | $1.38 | $1.52 | $2.00 | $2.20 | |
| 96 | 78000650 | THPL PVT MK LINE 24 | 24 | FOOT | $3.00 | $10.00 | $11.00 | $3.00 | $15.00 | |
| 97 | 78100100 | RAISED REFL PAVT MKR | 64 | EACH | $80.00 | $45.00 | $49.50 | $80.00 | $125.00 | |
| 98 | 78200005 | GRDRAIL REF TYPE A | 36 | EACH | $9.09 | $9.09 | $10.00 | $10.00 | $12.00 | |
| 99 | 78300200 | RAISED REF PVT MK REM | 64 | EACH | $6.50 | $8.00 | $36.00 | $35.00 | $10.00 |