$46.13Avg low bid / SQ FT
$48.18Avg of all bids
—Avg engineer's estimate
9Jobs · 42,704 SQ FT
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 5 | 24,699 | $47.34 | $52.67 |
| 2025 | 4 | 18,005 | $44.46 | $43.80 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jul 31, 2026 | 62T84 | CookDistrict 1 | 875 SQ FT | $45.00 | D. Construction, Inc. |
| Jun 12, 2026 | 62M71 | Kane, KendallDistrict 1 | 8,580 SQ FT | $60.00 | D. Construction, Inc. |
| Apr 24, 2026 | 62K33 | CookDistrict 1 | 3,284 SQ FT | $22.00 | Plote Construction, Inc. |
| Apr 24, 2026 | 61L86 | MchenryDistrict 1 | 6,205 SQ FT | $49.00 | Dunnet Bay Construction Company |
| Apr 24, 2026 | 89871 | HendersonDistrict 4 | 5,755 SQ FT | $41.50 | County Contractors, Inc. |
| Sep 19, 2025 | 61L28 | KaneDistrict 1 | 5,270 SQ FT | $58.86 | Martam Construction Incorporated |
| Jun 13, 2025 | 78A39 | Gallatin, WhiteDistrict 9 | 1,309 SQ FT | $70.00 | Samron Midwest Contracting, Inc. |
| Mar 7, 2025 | 61K89 | CookDistrict 1 | 9,094 SQ FT | $30.00 | D. Construction, Inc. |
| Jan 17, 2025 | 87840 | GrundyDistrict 3 | 2,332 SQ FT | $54.00 | D. Construction, Inc. |