(27)RS-1
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Herbig Blacktop Construction Low bidder | $261,874 | ||
| 2 | G. M. Sipes Construction, Inc. | $325,985 | +24.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Herbig Blacktop… | #2 G. M. Sipes Con… |
|---|---|---|---|---|---|---|---|
| 1 | Z0030850 | TEMP INFO SIGNING | 42 | SQ FT | $40.00 | $50.00 | |
| 2 | Z0033700 | LONG JOINT SEALANT | 1,244 | FOOT | $7.50 | $4.50 | |
| 3 | 35100500 | AGG BASE CSE A 6 | 609 | SQ YD | $15.00 | $40.00 | |
| 4 | 40600275 | BIT MATLS PR CT | 274 | POUND | $6.00 | $1.00 | |
| 5 | 40600290 | BIT MATLS TACK CT | 2,072 | POUND | $2.50 | $1.00 | |
| 6 | 40600400 | MIX CR JTS FLANGEWYS | 1.1 | TON | $200.00 | $200.00 | |
| 7 | 40600900 | HMA BC HM N50 | 2 | TON | $200.00 | $200.00 | |
| 8 | 40600990 | TEMPORARY RAMP | 90 | SQ YD | $10.00 | $20.00 | |
| 9 | 40602965 | HMA BC IL-9.5FG N50 | 223 | TON | $110.00 | $115.00 | |
| 10 | 40604000 | HMA SC IL-9.5FG C N50 | 223 | TON | $110.00 | $115.00 | |
| 11 | 40800050 | INCIDENTAL HMA SURF | 3 | TON | $200.00 | $300.00 | |
| 12 | 44000154 | HMA SURF REM 1 1/4 | 41 | SQ YD | $10.00 | $7.00 | |
| 13 | 44000158 | HMA SURF REM 2 1/4 | 2,580 | SQ YD | $10.50 | $7.00 | |
| 14 | 44004250 | PAVED SHLD REMOVAL | 1,069 | SQ YD | $30.00 | $20.00 | |
| 15 | 44201761 | CL D PATCH T1 10 | 32 | SQ YD | $195.00 | $295.00 | |
| 16 | 44201765 | CL D PATCH T2 10 | 120 | SQ YD | $195.00 | $295.00 | |
| 17 | 44201769 | CL D PATCH T3 10 | 123 | SQ YD | $195.00 | $295.00 | |
| 18 | 44201771 | CL D PATCH T4 10 | 96 | SQ YD | $195.00 | $295.00 | |
| 19 | 48102100 | AGG WEDGE SHLD TYPE B | 28 | TON | $50.00 | $50.00 | |
| 20 | 48203029 | HMA SHOULDERS 8 | 459 | SQ YD | $50.00 | $40.00 | |
| 21 | 60300305 | FR & LIDS ADJUST | 1 | EACH | $750.00 | $2,000.00 | |
| 22 | 67100100 | MOBILIZATION | 1 | L SUM | $13,400.00 | $25,000.00 | |
| 23 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $8,300.00 | $35,000.00 | |
| 24 | 70300100 | SHORT TERM PAVT MKING | 211 | FOOT | $1.00 | $1.00 | |
| 25 | 70300150 | SHRT TRM PAVT MK REM | 70 | SQ FT | $2.20 | $15.00 | |
| 26 | 78000200 | THPL PVT MK LINE 4 | 2,184 | FOOT | $1.75 | $1.75 | |
| 27 | 78000400 | THPL PVT MK LINE 6 | 295 | FOOT | $2.50 | $2.63 | |
| 28 | 78000650 | THPL PVT MK LINE 24 | 9 | FOOT | $9.50 | $20.00 |