(22,23)DR
- Let date
- Friday, April 24, 2020
- Contract
- 72L60 · job page
- District
- District 6
- County
- Morgan, Scott
- Highway
- Limits
- Culvert replacement on Old US 36 from east of the Scott / Morgan County line to east of Jacksonville.
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Lee Hood d/b/a Hood Demolition & Excavation Low bidder | $114,850 | ||
| 2 | L. W. Rouland Trucking Service, Inc. | $161,161 | +40.3% | |
| 3 | K. E. Vas Company | $169,862 | +47.9% | |
| 4 | CSD Environmental Services, Inc. | $169,879 | +47.9% | |
| 5 | Scruggs Machinery Equipment Construction Commodity Co. | $171,464 | +49.3% | |
| 6 | County Contractors, Inc. | $181,896 | +58.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Lee Hood d/b/a … | #2 L. W. Rouland T… | #3 K. E. Vas Compa… | #4 CSD Environment… | #5 Scruggs Machine… | #6 County Contract… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 20800150 | TRENCH BACKFILL | 250 | CU YD | $40.00 | $31.00 | $38.00 | $64.00 | $135.00 | $65.00 | |
| 2 | 44201389 | CL C PATCH T2 13 | 22 | SQ YD | $150.00 | $450.00 | $190.00 | $342.31 | $278.00 | $425.00 | |
| 3 | 44201396 | CL C PATCH T4 13 | 270 | SQ YD | $150.00 | $219.00 | $186.00 | $164.90 | $232.00 | $230.00 | |
| 4 | 50104400 | CONC HDWL REM | 8 | EACH | $700.00 | $290.00 | $1,500.00 | $650.00 | $875.00 | $450.00 | |
| 5 | 50105220 | PIPE CULVERT REMOV | 229 | FOOT | $40.00 | $10.00 | $10.00 | $5.00 | $32.00 | $46.00 | |
| 6 | 542A0235 | P CUL CL A 1 30 | 218 | FOOT | $105.00 | $175.00 | $264.00 | $274.34 | $95.00 | $214.00 | |
| 7 | 54213675 | PRC FLAR END SEC 30 | 8 | EACH | $1,425.00 | $1,632.00 | $2,265.00 | $800.00 | $1,490.00 | $2,170.00 | |
| 8 | 67100100 | MOBILIZATION | 1 | L SUM | $6,000.00 | $6,665.00 | $5,000.00 | $15,313.00 | $10,000.00 | $12,000.00 | |
| 9 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $6,000.00 | $21,900.00 | $11,000.00 | $13,961.00 | $12,000.00 | $4,050.00 |