(21,104,105)SW
- Let date
- Friday, April 24, 2020
- Contract
- 72K45 · job page
- District
- District 6
- County
- Montgomery
- Highway
- Limits
- ADA improvements at various locations along IL 16 and IL 127 in Hillsboro.
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Stutz Excavating, Inc. Low bidder | $344,460 | ||
| 2 | Kinney Contractors, Inc. | $369,323 | +7.2% | |
| 3 | Keller Construction, Inc. | $409,662 | +18.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Stutz Excavatin… | #2 Kinney Contract… | #3 Keller Construc… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0327008 | REM/REL SIGN SPECIAL | 1 | EACH | $600.00 | $350.00 | $495.00 | |
| 2 | X4240420 | PC CONC SIDEWALK 4 SP | 6,426 | SQ FT | $12.00 | $15.50 | $15.20 | |
| 3 | X5030225 | CONC STRUCT SPL | 13 | CU YD | $1,170.00 | $1,850.00 | $2,805.00 | |
| 4 | X6061005 | CONC CURB TB SPL | 143 | FOOT | $66.50 | $98.00 | $104.54 | |
| 5 | Z0012450 | CONCRETE STEPS | 0.5 | CU YD | $3,500.00 | $2,500.00 | $2,999.00 | |
| 6 | Z0012455 | CONC STEP REMOV | 3 | EACH | $150.00 | $250.00 | $349.00 | |
| 7 | 25000200 | SEEDING CL 2 | 0.25 | ACRE | $3,360.00 | $8,200.00 | $7,140.00 | |
| 8 | 25000400 | NITROGEN FERT NUTR | 1 | POUND | $290.00 | $1.50 | $1.21 | |
| 9 | 25000500 | PHOSPHORUS FERT NUTR | 1 | POUND | $290.00 | $1.50 | $1.21 | |
| 10 | 25000600 | POTASSIUM FERT NUTR | 1 | POUND | $290.00 | $1.50 | $1.21 | |
| 11 | 25000700 | AGR GROUND LIMESTONE | 0.5 | TON | $935.00 | $250.00 | $221.00 | |
| 12 | 25100115 | MULCH METHOD 2 | 0.25 | ACRE | $4,300.00 | $6,340.00 | $5,460.00 | |
| 13 | 35400300 | PCC BASE CSE W 8 | 107 | SQ YD | $227.00 | $78.00 | $146.00 | |
| 14 | 42400800 | DETECTABLE WARNINGS | 627 | SQ FT | $21.00 | $30.50 | $45.00 | |
| 15 | 44000300 | CURB REM | 5 | FOOT | $40.00 | $50.00 | $49.50 | |
| 16 | 44000500 | COMB CURB GUTTER REM | 617 | FOOT | $34.50 | $20.00 | $21.00 | |
| 17 | 44000600 | SIDEWALK REM | 5,566 | SQ FT | $3.85 | $3.50 | $3.50 | |
| 18 | 50901760 | PIPE HANDRAIL | 12 | FOOT | $315.00 | $325.00 | $300.00 | |
| 19 | 60255500 | MAN ADJUST | 2 | EACH | $350.00 | $850.00 | $1,100.00 | |
| 20 | 60266600 | VALVE BOX ADJ | 3 | EACH | $175.00 | $450.00 | $749.00 | |
| 21 | 60603800 | COMB CC&G TB6.12 | 143 | FOOT | $54.00 | $62.00 | $67.00 | |
| 22 | 60604400 | COMB CC&G TB6.18 | 21 | FOOT | $58.00 | $68.00 | $67.00 | |
| 23 | 60605000 | COMB CC&G TB6.24 | 453 | FOOT | $89.00 | $69.00 | $67.00 | |
| 24 | 66900105 | UNDERGR STOR TANK REM | 1 | EACH | $7,500.00 | $20,000.00 | $0.0100 | |
| 25 | 66900200 | NON SPL WASTE DISPOSL | 110 | CU YD | $117.75 | $175.00 | $168.00 | |
| 26 | 66900530 | SOIL DISPOSAL ANALY | 6 | EACH | $725.00 | $1,050.00 | $893.00 | |
| 27 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $2,310.00 | $2,500.00 | $2,310.00 | |
| 28 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $1,940.00 | $2,500.00 | $2,310.00 | |
| 29 | 66901006 | REG SUB MON | 12 | CAL DA | $840.00 | $1,150.00 | $987.00 | |
| 30 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $2,500.00 | $1,800.00 | $1,100.00 | |
| 31 | 67100100 | MOBILIZATION | 1 | L SUM | $20,000.00 | $18,000.00 | $37,536.00 | |
| 32 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $11,920.00 | $12,500.00 | $36,000.00 | |
| 33 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $890.00 | $1,050.00 | $1,320.00 |