(16,17,28)RS-3
- Let date
- Friday, April 24, 2020
- Contract
- 66D56 · job page
- District
- District 3
- County
- Livingston
- Highway
- Limits
- 3P milling and resurfacing (Designed Overlay) from IL 18 to West Fork Mazon River, 1.4 miles W of I-55.
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Kankakee Valley Construction Company, Inc. Low bidder | $5,416,536 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Kankakee Valley… |
|---|---|---|---|---|---|---|
| 1 | X0326341 | REATTACH END SECTION | 4 | EACH | $475.00 | |
| 2 | X0327809 | LINEAR DELIN PANELS 4 | 40 | EACH | $60.00 | |
| 3 | X4401198 | HMA SURF REM VAR DP | 4,244 | SQ YD | $14.00 | |
| 4 | Z0005305 | BOX CUL TO BE CLEANED | 441 | FOOT | $40.00 | |
| 5 | Z0030850 | TEMP INFO SIGNING | 42 | SQ FT | $35.00 | |
| 6 | Z0033700 | LONG JOINT SEALANT | 60,898 | FOOT | $2.60 | |
| 7 | Z0034105 | MATL TRANSFER DEVICE | 37,542 | TON | $4.10 | |
| 8 | Z0055300 | RUMBLE STRIP | 3 | EACH | $1,450.00 | |
| 9 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | |
| 10 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | |
| 11 | 20300100 | CHANNEL EXCAVATION | 60 | CU YD | $105.00 | |
| 12 | 21400100 | GRADING & SHAP DITCH | 2,600 | FOOT | $14.00 | |
| 13 | 25000210 | SEEDING CL 2A | 0.7 | ACRE | $2,700.00 | |
| 14 | 25000400 | NITROGEN FERT NUTR | 58 | POUND | $5.00 | |
| 15 | 25000500 | PHOSPHORUS FERT NUTR | 58 | POUND | $5.00 | |
| 16 | 25000600 | POTASSIUM FERT NUTR | 58 | POUND | $5.00 | |
| 17 | 25100630 | EROSION CONTR BLANKET | 3,222 | SQ YD | $1.50 | |
| 18 | 40600290 | BIT MATLS TACK CT | 122,580 | POUND | $0.0100 | |
| 19 | 40600400 | MIX CR JTS FLANGEWYS | 54 | TON | $395.00 | |
| 20 | 40600900 | HMA BC HM N50 | 89 | TON | $395.00 | |
| 21 | 40600990 | TEMPORARY RAMP | 975 | SQ YD | $25.00 | |
| 22 | 40602985 | HMA BC IL-9.5 N70 | 20,022 | TON | $88.00 | |
| 23 | 40604052 | HMA SC IL-9.5 C N70 | 17,520 | TON | $88.00 | |
| 24 | 40800050 | INCIDENTAL HMA SURF | 626 | TON | $218.00 | |
| 25 | 44000164 | HMA SURF REM 3 3/4 | 178,771 | SQ YD | $4.15 | |
| 26 | 48101200 | AGGREGATE SHLDS B | 5,782 | TON | $28.75 | |
| 27 | 63000001 | SPBGR TY A 6FT POSTS | 737.5 | FOOT | $23.00 | |
| 28 | 63000030 | SPGR ATT TO CULVERT | 100 | FOOT | $250.00 | |
| 29 | 63000370 | LSG OVER CUL 25' SPAN | 200 | FOOT | $23.00 | |
| 30 | 63100167 | TR BAR TRM T1 SPL TAN | 20 | EACH | $2,800.00 | |
| 31 | 63200310 | GUARDRAIL REMOV | 2,275 | FOOT | $6.75 | |
| 32 | 66700205 | PERM SURV MKRS T1 | 22 | EACH | $175.00 | |
| 33 | 67000400 | ENGR FIELD OFFICE A | 5 | CAL MO | $3,500.00 | |
| 34 | 67100100 | MOBILIZATION | 1 | L SUM | $228,000.00 | |
| 35 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $15,000.00 | |
| 36 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $45,000.00 | |
| 37 | 70300100 | SHORT TERM PAVT MKING | 5,854 | FOOT | $1.25 | |
| 38 | 70300150 | SHRT TRM PAVT MK REM | 651 | SQ FT | $7.00 | |
| 39 | 78000100 | THPL PVT MK LTR & SYM | 62 | SQ FT | $7.50 | |
| 40 | 78000200 | THPL PVT MK LINE 4 | 10,568 | FOOT | $1.20 | |
| 41 | 78000500 | THPL PVT MK LINE 8 | 558 | FOOT | $2.40 | |
| 42 | 78000600 | THPL PVT MK LINE 12 | 256 | FOOT | $3.61 | |
| 43 | 78000650 | THPL PVT MK LINE 24 | 61 | FOOT | $7.25 | |
| 44 | 78001110 | PAINT PVT MK LINE 4 | 255,560 | FOOT | $0.1000 | |
| 45 | 78001130 | PAINT PVT MK LINE 6 | 29,170 | FOOT | $0.1500 | |
| 46 | 78100100 | RAISED REFL PAVT MKR | 862 | EACH | $30.72 | |
| 47 | 78200005 | GRDRAIL REF TYPE A | 60 | EACH | $10.00 | |
| 48 | 78300200 | RAISED REF PVT MK REM | 862 | EACH | $10.00 |