(06-1)SCR
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $52,700 | ||
| 2 | Phoenix Corporation of the Quad Cities | $54,620 | +3.6% | |
| 3 | Gensini Excavating, Inc. | $55,400 | +5.1% | |
| 4 | Miller Trucking & Excavating Company | $72,450 | +37.5% | |
| 5 | Curnyn Construction Co. | $77,200 | +46.5% | |
| 6 | Stark Excavating, Inc. | $93,205 | +76.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Phoenix Corpora… | #3 Gensini Excavat… | #4 Miller Trucking… | #5 Curnyn Construc… | #6 Stark Excavatin… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 28100809 | STONE DUMP RIP CL A5 | 800 | TON | $55.00 | $54.50 | $50.00 | $72.50 | $68.00 | $85.86 | |
| 2 | 67100100 | MOBILIZATION | 1 | L SUM | $3,000.00 | $3,800.00 | $5,000.00 | $2,500.00 | $5,000.00 | $3,660.05 | |
| 3 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $5,000.00 | $5,190.00 | $9,000.00 | $9,500.00 | $15,000.00 | $20,315.12 | |
| 4 | 70107025 | CHANGEABLE MESSAGE SN | 7 | CAL DA | $100.00 | $290.00 | $200.00 | $350.00 | $400.00 | $77.47 |